While CR’s submission may have some merit, the problem is that it does not appear to be supported by the manner in which the pertinent provisions of the Act are drafted. Further, for every good argument that CR may make, there is a counter-argument that can be made for the other side. The Act was enacted to establish a quick and inexpensive regime for the resolution of disputes over payment claims that would facilitate cash flow in the construction industry. Adjudication determinations would have “temporary finality” so that cash can flow quickly and smoothly, and parties are to finally resolve all disputes between them in arbitration or court proceedings after the construction works are completed. The introduction of an additional layer of review runs the risk of protracting proceedings further. If construction works are still in progress, this could be an unwelcome distraction for the parties. Hence, the legislature deemed it necessary to limit the right to apply for review to cases where the difference between the adjudicated amount and the response amount is large. Presently, this is set at $100,000. It is also conceivable that the legislature deemed it necessary to place a further restraint in that once an adjudication review is set in motion, the entire adjudication determination is open for review and not just the parts that the respondent is dissatisfied with. It must be borne in mind that in many adjudication determinations, there will be parts where the adjudicator gets it right and parts where he gets it wrong. To permit a respondent to cherry-pick the parts which he is unhappy with, without a corresponding right on the part of the claimant to seek a review of the parts where the adjudicator may have gotten it wrong, could also be unfair. Indeed, the Narrow Interpretation would tend to encourage respondents to apply for an adjudication review as there would be nothing to lose, but everything to gain.