High Court · Decided 29 June 2020
CKR Contract Services Pte Ltd v Asplenium Land Pte Ltd and others [20 20] SGHC 133
Feedback & support[2020] SGHC 133 · Case no. Suit No 1274 of 2015 (Summons No 4732 of 2019)
✱ What happened, in plain English
There is no plain-English summary of this judgment yet.
Ask about this judgment →Grounds of decision
Official text from eLitigation
- [1]
[1] This judgment concerns an application by the first defendant (Summons No 4732 of 2019) to strike out the action brought by the plaintiff against it in Suit No 1274 of 2015 (“Suit 1274”) under O 18 r 19(1) of the Rules of Court (Cap 322, R 5, 2014 Rev Ed) (“ROC”). It was fixed and heard together with a similar application taken out by the second defendant to strike out the action against him (Summons No 5859 of 2019), but that latter application was withdrawn in the course of the hearing.
- [2]
[2] In Suit 1274, the plaintiff has brought proceedings against the first to ninth defendants for the torts of lawful means conspiracy and unlawful means conspiracy, and against the first and second defendants for the tort of intimidation. In its striking out application, the first defendant’s main contention, in gist, is that the plaintiff’s claims should be struck out because they have already been dealt with in the arbitration brought by the plaintiff (see [16] below), and the claims in this suit are thus barred by the principles of res judicata.
- [3]
[3] The striking out application which is the subject of the present judgment should not be seen in isolation, but in its proper context. It is the latest salvo in a long-running dispute arising from a building and construction project where the plaintiff was appointed and later terminated as the main contractor. As will be outlined below, the longstanding nature of this dispute between the plaintiff on the one hand and the project developer and consultants on the other, has engendered an entire series of pronouncements and findings by, inter alia, an arbitral tribunal and the Courts, and it is against this backdrop that the present application is brought.
Background
Dramatis personae
- [4]
[4] Given the number of defendants, it will be useful to first set out the dramatis personae involved in Suit 1274.
- [5]
[5] The plaintiff, CKR Contract Services Pte Ltd, was appointed as the main contractor for a condominium project known as the Seletar Park Residences (“the Project”) from 15 January 2013. Its appointment as the main contractor was terminated on 24 October 2014.
- [6]
[6] The first defendant, Asplenium Land Pte Ltd, was the developer for the Project, and is a subsidiary of Tuan Sing Holdings Pte Ltd. The first defendant had been incorporated for the development of the Project. The second defendant, Sia Wee Long (“Mr Sia”), was an employee of Tuan Sing Holdings Pte Ltd and was, at the material time, the project manager of the Project.
- [7]
[7] The third defendant, SCDA Architects Pte Ltd, was the architectural firm engaged as the Project’s architects. At the material time, the fourth and fifth defendants were employees of the third defendant. The fourth defendant, who remains employed by the third defendant, was the architect named as the Qualified Person for the Project, and the fifth defendant also worked on the Project as an architect. In the course of this judgment, for convenience, I will refer to the third to fifth defendants as “the architects”.
- [8]
[8] The sixth defendant, Rich-Link Construction Pte Ltd, was engaged by the first defendant to replace the plaintiff as the main contractor for the Project after the first defendant had terminated the plaintiff’s services in October 2014.
- [9]
[9] The seventh defendant, Rider Levett Bucknall LLP, was the firm of quantity surveyors engaged for the Project. The eighth defendant, RLB Consultancy Pte Ltd, is a related company of the seventh defendant. The ninth defendant, Lam Chye Shing, is an employee of the seventh defendant and was the designated Quantity Surveyor for the Project. The seventh, eighth, and ninth defendants were involved in the replacement tender process through which the sixth defendant was engaged to replace the plaintiff as main contractor for the Project. For context, the seventh defendant is in the business of providing property and construction consultancy services, while the eighth defendant is in the business of providing consultancy and project management services in the construction industry. The seventh and eighth defendants have the same registered address, and the nine registered partners of the seventh defendant are also directors and shareholders of the eighth defendant.
Background to the disputes
- [10]
[10] A brief chronology of the relevant facts is as follows.
- [11]
[11] On 15 January 2013, the plaintiff and first defendant entered into a contract (“the Contract”) concerning the development of the Project. The first defendant had engaged the plaintiff as the main contractor to carry out building and construction works for the Project. Three points bear note in relation to the Contract:
(a) The value of the Contract upon the plaintiff’s appointment as main contractor was S$88,063,838.00 (the “Contract Sum”). The commencement date of the Project was 21 January 2013, and the scheduled completion date was 20 January 2015.
(b) The Contract incorporated the Singapore Institute of Architects’ Articles and Conditions of Building Contract (Lump Sum Contract) 9th Edition (Reprint August 2011) (the “SIA Conditions”) and the Supplemental Articles and Conditions of Contract.
(c) Pursuant to the Contract, a performance bond was procured by the plaintiff in favour of the first defendant in the sum of S$8,806,383.80 (being 10% of the Contract Sum).
- [12]
[12] On 24 October 2014, the plaintiff was terminated as main contractor of the Project by the first defendant pursuant to a Notice of Termination issued that very day. The Notice of Termination was issued on the basis of two Termination Certificates issued by the third defendant and signed by the fourth defendant. The first of these certificates (“Certificate No. 260”) was issued on the basis that the plaintiff had failed to proceed with the Project with due diligence and expedition for one month even after the third defendant had issued it a notice to do so (“Notice 260”) pursuant to cl 32(3)(d) of the SIA Conditions on 11 September 2014. The other Termination Certificate (“Certificate No. 262”) proceeded on the basis that the plaintiff had failed to comply with various architect’s directions (“ADs”) issued by the architects within one month after the third defendant had issued it a notice to do so (“Notice 262”) pursuant to cl 32(3)(h) of the SIA Conditions on 11 September 2014. For completeness, I note that two other written notices pursuant to cll 32(3)(e) and 32(3)(h) respectively of the SIA Conditions, Notice 261 and Notice 265, had been issued by the third defendant. However, these two other written notices were not relied upon by the third defendant as the bases for the issuance of Termination Certificates. I shall refer to Notices 260, 261, 262 and 265 collectively as “the Notices”.
- [13]
[13] For ease of reference, cll 32(3)(d) and 32(3)(h) of the SIA Conditions, pursuant to which Notices 260 and 262, and subsequently Termination Certificates No. 260 and 262 respectively were issued, are set out below:
- [14]
[14] Following the plaintiff’s termination in October 2014, a replacement tender exercise was held and a new contractor, the sixth defendant, was appointed to complete the Project.
- [15]
[15] On 4 November 2014, consequent to the termination of the Contract, the first defendant made a call on the performance bond for the full sum. While the call amount was subsequently reduced by the first defendant to around S$7.7 million, a second call was made on the performance bond for the remaining balance of approximately S$1.1 million about a year later, after the completion of the Project.
- [16]
[16] On 10 November 2014, the plaintiff commenced arbitral proceedings (“the Arbitration”) against the first defendant pursuant to the parties’ arbitration agreement in cl 37 of the SIA Conditions. The arbitration clause provided that any dispute between the parties arising out of the Contract was to be “referred to the arbitration and final decision of a person to be agreed by the parties”. The parties agreed to appoint Mr Chow Kok Fong (the “tribunal” or “arbitrator”) as the sole arbitrator. The Arbitration was bifurcated into two phases – a liability phase and a quantum phase. The liability phase of the Arbitration ran from 10 November 2014 to 14 February 2018, and two awards were issued in this regard.
- [20]
[20] On 15 December 2015, more than a year after the plaintiff had commenced arbitration against the first defendant and while the liability phase of the Arbitration was still pending, the plaintiff commenced Suit 1274 against the nine defendants outlined from [6] to [9] above. The first to sixth defendants took out applications for a stay of Suit 1274. These were resisted by the plaintiff, which argued that Suit 1274 should be allowed to proceed. Notably, counsel for the plaintiff conceded during the course of the hearing of the stay applications that, if the plaintiff succeeded in the Arbitration, the plaintiff would discontinue Suit 1274. After hearing the arguments, Judith Prakash J (as she then was) granted a case management stay of the proceedings against all nine defendants, pending the outcome of the Arbitration.
- [21]
[21] After the issuance of Partial Award 4 and the conclusion of the Arbitration, the plaintiff obtained leave to amend its Statement of Claim in Suit 1274, which had originally been filed on 30 December 2015. The plaintiff filed its amended Statement of Claim on 9 September 2019 and wanted to proceed with the Suit. In the amended Statement of Claim, the plaintiff outlined the three causes of action set out at [2] above.
Other legal proceedings
- [23]
[23] As alluded to above, the present applications are but the latest skirmish in what has proven to be an extended campaign of legal proceedings. I will briefly outline the other proceedings below.
- [24]
[24] First, the Arbitration formed the most substantive aspect of legal proceedings between the plaintiff and first defendant and is the central focus of the arguments for striking out. As described above, the Arbitration was protracted. Spanning a period of around five years, the bifurcated arbitration involved four Partial Awards, many days of hearing, and multiple rounds of submissions before the arbitrator. A total of 55 witnesses gave evidence during the Arbitration, and no fewer than 93 witness statements were tendered as evidence. The first defendant called, at the Arbitration, representatives of all the nine defendants in this Suit 1274, who are the alleged co-conspirators, to give evidence, and they were cross-examined by the plaintiff. These representatives called as witnesses included, inter alia:
(a) The second defendant,
(b) Mr Lau Kah Kyn Edward, who is a former director of the third defendant;
(c) The fourth defendant;
(d) The fifth defendant;
(e) Mr Loi Teck Han, who is the General Manager of the sixth defendant; and
(f) The ninth defendant, who is a director and shareholder of the seventh and eighth defendants.
- [25]
[25] A total of three applications to the High Court (in HC/OS 1263/2017, HC/OS 293/2018, and HC/OS 976/2019) for leave to appeal on questions of law arising from three of the four Partial Awards were made by the plaintiff. HC/OS 293/2018 was eventually withdrawn by the plaintiff prior to its determination, while the other two applications were dismissed. Apart from the three applications by the plaintiff for leave to appeal on questions of law arising from the Arbitration, one such application (in HC/OS 1269/2017), for leave to appeal on questions of law arising from Partial Award 1, was made by the first defendant. This application was wholly discontinued before its determination.
- [26]
[26] Second, around 14 January 2015, after the plaintiff had commenced the Arbitration against the first defendant, the plaintiff initiated separate proceedings in HC/S 37/2015 (“Suit 37”) against the seventh, eighth, and ninth defendants. Suit 37 entails claims for, inter alia, negligence in the conduct of the replacement tender exercise, the assessment of the tender returns, and the computation of the sum claimed by the first defendant on the performance bond (see [11(c)] above). The seventh and ninth defendants, as professional quantity surveyors, had been instructed by the first defendant to conduct and supervise the replacement tender exercise, to evaluate the tender returns (the bids) submitted by the tenderers, and to recommend which tender return to accept for award of the replacement contract. The eighth defendant had been instructed by the first defendant to assess the tender returns in the replacement tender in respect of the tenderers’ resources and scheduling proposals. The crux of the allegations against the seventh to ninth defendants in this Suit are that they carried out their work in a negligent manner.
- [28]
[28] Fourth, on 6 April 2018, over two years after the plaintiff had commenced the Arbitration, it commenced HC/S 349/2018 against the third and fourth defendants. Specifically, the plaintiff alleged that the third and fourth defendants were liable in the tort of deceit for issuing wrongful ADs, Notices, and Termination Certificates.
- [29]
[29] I note that Suit 37 and Suit 349 remain pending as at the time of this judgment’s release. The plethora of legal proceedings I have outlined above provide further context to the present suit and the application I have to determine.
The applicable legal principles
The law on striking out
(a) Disclose no reasonable cause of action or defence (O 18 r 19(1)(a));
(b) Are scandalous, frivolous or vexatious (O 18 r 19(1)(b);
(c) May prejudice, embarrass or delay the fair trial of the action (O 18 r 19(1)(c)); or
(d) Are otherwise an abuse of process of the Court (O 18 r 19(1)(d)).
- [31]
[31] The principles governing the application of O 18 r 19(1) of the ROC are fairly well-established. Broadly, it would only be in “plain and obvious” cases that the power of striking out should be invoked: Gabriel Peter & Partners (suing as a firm) v Wee Chong Jin and others [1997] 3 SLR(R) 649 (“Gabriel Peter”) at [18]. This is anchored on the judicial policy to afford a litigant the right to institute a bona fide claim before the courts and to prosecute it in the usual way unless the case is wholly and clearly unarguable: Tan Eng Khiam v Ultra Realty Pte Ltd [1991] 1 SLR(R) 844 at [31].
- [32]
[32] A more recent restatement of the position on striking out is as outlined by the authors of Singapore Civil Procedure 2020, vol 1 (Chua Lee Ming gen ed) (Sweet & Maxwell, 10th ed, 2020) (“Singapore Civil Procedure 2020”) at [18/19/6] that “[t]he claim must be obviously unsustainable, the pleadings unarguably bad and it must be impossible, not just improbable, for the claim to succeed before the court will strike it out”.
- [33]
[33] Each limb of O 18 r 19(1) of the ROC provides a separate and distinct basis for the Court’s exercise of its power to strike out pleadings: The “Bunga Melati 5” [2012] 4 SLR 546 (“The Bunga Melati”) at [31].
- [34]
[34] Turning to the first limb of O 18 r 19(1) of the ROC, that the pleadings disclose no reasonable cause of action, the Court of Appeal held in Ng Chee Weng v Lim Jit Ming Bryan and another [2012] 1 SLR 457 at [110] that:
- [35]
[35] The principle that striking out is only appropriate in fairly narrow and constrained grounds also applies in relation to the second limb of O 18 r 19(1) of the ROC, that the pleadings are scandalous, frivolous or vexatious. The phrase “frivolous and vexatious” refers to actions which are obviously unsustainable or wrong, or which show a lack of purpose or seriousness in the party’s conduct of proceedings: The “Osprey” [1999] 3 SLR(R) 1099 at [8]. In The Bunga Melati at [39], the Court of Appeal further elucidated that a “plainly or obviously” unsustainable action is one which is either:
- [36]
[36] The third limb of O 18 r 19(1) of the ROC addresses situations where the pleadings may prejudice, embarrass or delay the fair trial of the action. I accept the view of the authors of Singapore Civil Procedure 2020 at [18/19/13] that a liberal interpretation of what might “prejudice, embarrass or delay the fair trial of the action” should be adopted, though this will no doubt depend on the individual facts of each case (see also Tong Seak Kan and another v Jaya Sudhir a/l Jayaram [2016] 5 SLR 887 at [30]).
- [37]
[37] In Gabriel Peter ([31] supra) at [22], the Court of Appeal clearly set out the ambit of the phrase “abuse of process of the Court”. I do not propose to reproduce the Court of Appeal’s views in full, save to note that the phrase “has been given a wide interpretation by the courts”, “includes considerations of public policy and the interests of justice”, “will depend on all the relevant circumstances of the case”, and that the “bringing of an action for a collateral purpose” has been “judicially acknowledged as an abuse of process”.
- [38]
[38] In the present application, all four limbs of O 18 r 19(1) of the ROC have been relied on to justify the striking out of the plaintiff’s claims.
The principles on res judicata
- [39]
[39] The central basis of the present application is that the matters raised by the plaintiff in Suit 1274 have already been decided by the arbitrator and/or ought to have been raised by the plaintiff in the Arbitration. The argument is that the doctrine of res judicata precludes the plaintiff from raising these claims and that the plaintiff’s claims should accordingly be struck out.
- [40]
[40] In the case of Goh Nellie v Goh Lian Teck and others [2007] 1 SLR(R) 453 (“Goh Nellie”), Sundaresh Menon JC (as he then was) outlined at [17] to [25] that the doctrine of res judicata encompasses three conceptually distinct though interrelated principles – cause of action estoppel, issue estoppel, and the extended doctrine of res judicata.
- [41]
[41] The first subspecies under the umbrella of res judicata is cause of action estoppel. As the Court noted at [17] of Goh Nellie, cause of action estoppel prevents a party from asserting or denying, as against the other party, the existence of a particular cause of action, the non-existence or existence of which has been determined by a court of competent jurisdiction in previous litigation between the same parties.
- [42]
[42] In Zhang Run Zi v Koh Kim Seng and another [2015] SGHC 175 (“Zhang Run Zi”) at [67], George Wei JC (as he then was) set out the requirements for cause of action estoppel as follows:
(a) There must be a final and conclusive judgment on the merits;
(b) The court pronouncing the earlier judgment must have been a competent court;
(c) Identity of parties; and
(d) Identity of causes of action.
It bears note that the first three requirements as set out at (a) to (c) above are in pari materia with the first three requirements for issue estoppel (see [44] below).
- [44]
[44] The requirements for issue estoppel are fourfold and are set out at [14] to [15] of the Court of Appeal’s judgment in Lee Tat Development Pte Ltd v Management Corporation of Strata Title Plan No 301 [2005] 3 SLR(R) 157. The majority of the Court of Appeal held that the following requirements have to be met to establish an issue estoppel:
(a) There must be a final and conclusive judgment on the merits;
(b) That judgment must be of a court of competent jurisdiction;
(c) There must be identity between the parties to the two actions that are being compared; and
(d) There must be an identity of subject-matter in the two proceedings.
- [45]
[45] The third subspecies of res judicata, known as the “extended doctrine of res judicata”, has also been referred to as the defence of abuse of process: BNX v BOE at [127] and Goh Nellie ([40] supra) at [41]. The extended doctrine of res judicata has its origins in the seminal decision of Sir James Wigram VC in Henderson v Henderson [1843] 3 Hare 999 at 114, and has been developed incrementally in both England and Singapore. In Lim Geok Lin Andy v Yap Jin Meng Bryan and another appeal [2017] 2 SLR 760, the Court of Appeal made the following observations at [39]:
- [46]
[46] The Court of Appeal went on at [44] to observe that:
- [47]
[47] The policy reasons underlying the doctrine were further examined in Antariksa Logistics Pte Ltd and others v Nurdian Cuaca and others [2018] 3 SLR 117 (“Antariksa Logistics”), where George Wei J expressed the view (at [82] of that judgment) that the doctrine aims to bring finality to litigation and avoid multiplicity of proceedings. This promotes the public interest of efficiency and economy in the conduct of litigation, and also prevents litigants from being oppressed and unfairly harassed by legal proceedings. At [77] of Antariksa Logistics, Wei J outlined the test for the extended doctrine of res judicata. Specifically, the focus is on whether, “in all the circumstances, a party is abusing the process of the court by seeking to raise before it an issue which could have been raised before” (emphasis added). The Court may also consider other factors, including whether there are bona fide reasons an issue that ought to have been raised in the earlier action was not raised, and whether, holistically speaking, the later proceedings are in substance nothing more than a collateral attack on the previous decision.
- [48]
[48] What is evident from my summary of the applicable legal principles is that the extended doctrine of res judicata, unlike cause of action estoppel and issue estoppel, is based on a more pragmatic rationale of not allowing parties to repeatedly come to court for matters which should have been dealt with in earlier proceedings. The extended doctrine is more concerned with the proper administration of justice than the fact that parties’ rights have been extinguished by reason of an estoppel. Cause of action estoppel and issue estoppel are unified on the basis that they address considerations which had in fact been raised in earlier proceedings, but the extended doctrine of res judicata goes beyond that to consider points which should have been raised, but were not in fact raised.
The key issues
- [50]
[50] In relation to the plaintiff’s claims for lawful and unlawful means conspiracy against the first to ninth defendants, my analysis centres on whether these claims are barred by the doctrine of res judicata in all its three iterations as outlined at [40] above, and thus whether they should be struck out under O 18 r 19(1)(b) and/or (d) of the ROC.
- [51]
[51] In relation to the plaintiff’s claim against the first and second defendants in the tort of intimidation, I will consider the plaintiff’s revised position on that claim (see [122] below), as well as the first defendant’s arguments to have the revised claim struck out on all four limbs of O 18 r 19(1) of the ROC.
The plaintiff’s claims for the torts of lawful and unlawful means conspiracy
- [52]
[52] The plaintiff’s claims for lawful and unlawful means conspiracy have consistently centred on two factual situations, as illustrated by its initial Statement of Claim (filed on 30 December 2015):
- [53]
[53] The plaintiff’s present claims in conspiracy are grounded on the same two factual matrices, as outlined in its Statement of Claim (Amendment No. 1) dated 9 September 2019 (“ASOC”), save that the claims have been amended to reflect the arbitrator’s finding that the Contract had been validly terminated. Before me, counsel for the plaintiff described these two factual matrices as two “sub-plots” to the conspiracy it was alleging, as follows:
(a) The first “sub-plot” pertains to the plaintiff’s allegations of a conspiracy between, inter alia, the first to fifth defendants to procure the issuance of ADs and Notices which eventually gave rise to the first defendant’s termination of the Contract.
(b) The second “sub-plot” concerns the plaintiff’s allegations of a conspiracy between, in particular, the first, second, sixth, seventh, eighth and/or ninth defendants to structure the replacement tender in such a manner as to ensure the appointment of the sixth defendant as the replacement contractor, and, more significantly, to maximise costs and thereby inflate the amount claimable from the plaintiff following the first defendant’s termination of the Contract.
It bears note that the first “sub-plot” goes towards the allegedly wrongful issuance of ADs and Notices giving rise to termination of the Contract. The second “sub-plot”, by contrast, goes towards the manner in which the replacement contract was procured and priced. The latter, unlike the first “sub-plot”, deals with events after the termination of the Contract.
- [55]
[55] In this application, I am not being asked to assess the merits of the distinction between the pleaded cases of lawful and unlawful means conspiracy. In any event, in my view, it is not necessary to distinguish between lawful and unlawful means conspiracy for the purposes of my analysis of the striking out application, whether for the first or second “sub-plot” of conspiracy. This is because, as I will go on to explain, the main thrust of the striking out application is that the issues of (a) whether there is agreement between the various alleged conspirators, and (b) whether the plaintiff has suffered any recoverable loss from those conspiracies, have both already been decided in the Arbitration. Hence, the first defendant argues, the doctrine of res judicata bars the bringing of all these conspiracy claims in these proceedings. As these issues of agreement and loss are critical elements of both lawful and unlawful means conspiracy, my conclusions on res judicata will determine whether the claims on these sub-plots should be permitted to go to trial, regardless of the type of conspiracy they relate to.
- [56]
[56] In seeking to strike out the plaintiff’s claims in conspiracy, the first defendant relies on all three subspecies of res judicata outlined in Goh Nellie ([40] supra). Given the commonality between cause of action estoppel and issue estoppel outlined at [48] above, I will consider those two subspecies of res judicata first, before moving on to consider, if necessary, the extended doctrine of res judicata.
- [58]
[58] I note for completeness, and as already mentioned, that the plaintiff has discontinued the action against the second to fifth defendants. My analysis on the plaintiff’s claims in conspiracy focuses, in any event, only on the first defendant’s application for striking out the claims that have been brought against it.
The first “sub-plot”
- [59]
[59] The first defendant argues that the plaintiff’s claims in conspiracy arising from the first “sub-plot” should be struck out on the basis of cause of action estoppel, as well as issue estoppel. The first defendant further argues that the remedies claimed in relation to the first “sub-plot” had already been sought in the Arbitration.
Cause of action estoppel
- [60]
[60] The crux of cause of action estoppel is, as the plaintiff pithily points out in its submissions, that a party will be barred from asserting or denying a cause of action that has already been determined by a competent court in previous litigation between the parties (see also above at [41]). The four requirements for cause of action estoppel, as outlined by the Court in Zhang Run Zi, have been set out above (see [42] supra).
- [61]
[61] The first requirement is satisfied as Partial Award 1 is a final and conclusive determination of the parties’ disputes on their merits. The parties commenced the Arbitration pursuant to the arbitration clause they had agreed to at cl 37 of the SIA Conditions, and the resolution of the disputes is described in the clause as being subject to the “final” decision of the arbitrator. For completeness, I set out the relevant portion of the arbitration clause below:
The Arbitration dealt extensively with the parties’ contentions on the various claims that were put forward by the plaintiff. In the process, voluminous factual and expert evidence on the contested issues was heard by the tribunal.
- [62]
[62] My view that the Arbitration is a final and conclusive determination on the merits is buttressed by the fact that, as outlined at [24] above, all of the applications for leave to appeal questions of law arising from the Arbitration have been rejected or withdrawn. As the Court of Appeal observed in AKN and another v ALC and others and other appeals [2016] 1 SLR 966 (“AKN”) at [57], “[j]ust as finality is of significance to the courts, so too is it of importance to arbitration. Thus, the courts will typically not rehear matters that have already been determined in arbitration …”. The Court of Appeal thus accepted in principle that arbitration awards can be final and conclusive determinations for the purposes of invoking res judicata. In any event, I note that the plaintiff does not appear to contest the finality and conclusiveness of the awards issued in the Arbitration.
- [63]
[63] Turning to the second requirement, I accept that the tribunal was a competent tribunal with jurisdiction over the parties. This flows from the fact that there was a valid and enforceable arbitration agreement between the parties, and a tribunal was constituted in accordance with the parties’ arbitration agreement. The plaintiff does not appear to challenge this point, and any challenge by the plaintiff would in any event be inconsistent with its own acts recognising the validity and competence of the tribunal. These acts include acting in accordance with awards made by the tribunal.
I see no reason, in principle, why the above approach should not equally apply in the case of cause of action estoppel.
- [65]
[65] The view that “[i]dentity of parties is not viewed narrowly” is also echoed at [40] of Tan Bee Hoon (executrix for the estate of Quek Cher Choi, deceased) and another v Quek Hung Heong and others [2015] SGHC 229. In a similar vein, this Court also concluded in Goh Nellie at [33] that, notwithstanding the fact that the parties to both actions were not exactly identical, identity of parties existed because “the principal players in both actions … are effectively identical” (emphasis added).
- [66]
[66] In this context, I am of the view that it would be simplistic to take the position that there is no identity of parties purely because the Arbitration only involved the plaintiff and first defendant, while Suit 1274 includes other defendants. This formalistic approach should be eschewed in favour of recognising that the allegations in relation to the first “sub-plot” mainly concern the plaintiff on one side, and the first defendant on the other. The second to fifth defendants are said to have conspired with the first defendant against the plaintiff for this first “sub-plot”. It is the first defendant which is at the centre of the conspiracy because, according to the plaintiff, it is the party that wanted to get rid of the plaintiff as the main contractor, and which had enlisted the help of the architects to achieve this end by the issuing of the relevant Notices and Termination Certificates. Further, it is the first defendant that stands to gain the most financially from this first “sub-plot”. In my judgment, the principal players in both actions are effectively identical, and the requirement of identity of parties is met on the instant facts.
- [67]
[67] Turning to the final requirement, that there is identity of causes of action, it was observed at [44] of Zhang Run Zi ([42] supra) that:
- [68]
[68] The Court then went on to consider a number of authorities, and distilled the principle outlined therein as follows, at [49]:
- [69]
[69] In Zhang Run Zi, the Court went on to strike out the plaintiff’s claims on the basis, inter alia, that cause of action estoppel applied, notwithstanding the fact that the heads of claim relied on by the plaintiff in Zhang Run Zi (namely, misrepresentation and breach of contract) were not expressly pleaded in the earlier proceedings: [72] to [74] of Zhang Run Zi.
- [70]
[70] I agree with the reasoning in Zhang Run Zi that, in ascertaining the identity of causes of action, reference should be had to the substance of the claims and the facts relied upon, and not the form of the cause of action invoked. In my view, this means that the task of the Court is to examine the matrix of factual allegations that the plaintiff is relying on to support its claim to relief, and to determine whether the same set of factual allegations was raised and adjudicated upon in the previous proceedings. The Court does not simply accept the labels applied by the parties to the claims in the later legal proceedings. In other words, the fact that the claim in the Arbitration is a claim for breach of contract, while the plaintiff raises claims for conspiracy in the present proceedings, is not determinative of whether cause of action estoppel can apply.
- [71]
[71] For the first “sub-plot”, there are two central bases upon which the first defendant asserts that identity of causes of action is present. First, the plaintiff is relying on materially the same facts to establish the first “sub-plot” in Suit 1274 as it sought to rely on to establish a wrongful and unjustifiable termination of the Contract in the Arbitration. Second, the plaintiff is, in effect, seeking the same remedies as it was seeking in the Arbitration. I examine these arguments below.
- [72]
[72] In seeking to establish its claim for conspiracy in relation to the first “sub-plot” in Suit 1274, the plaintiff pleads, inter alia, in its ASOC the following facts to establish that claim:
(a) First, the plaintiff asserts that, in the first quarter of 2014, the second defendant made unlawful demands for monetary gratification from the plaintiff. It further asserts that many invalid ADs were issued by the architects (whether at the direction of the second defendant or otherwise), and that the plaintiff was flooded with “an excessively high number of ADs in August and September 2014” by the second, third, fourth, and fifth defendants.
(b) The plaintiff then outlines a further series of instances in its ASOC where the second plaintiff had allegedly demanded monetary gratification from it. This leads to the key claim made by the plaintiff that, “(d)ue to [the second defendant’s] failure to obtain the monetary gratification that he sought … [the second defendant] and the other Defendants (or any two or more of them) did conspire in the manner pleaded … above”.
(c) The plaintiff then proceeds to outline in its ASOC the effects of the alleged conspiracy. These include claims that the first, second, third, fourth and/or fifth defendants had “conspired and or combined with each other to cause a Notice of Termination dated 24 October 2014 to be issued to [the plaintiff] and the Contract to be terminated”.
(d) The plaintiff also provides further particulars of how the conspiracy came to fruition, namely through the issuance of ADs by the third defendant. One such AD, which the plaintiffs alleged to be unwarranted, was AD 42 of 2014, which required the plaintiff to remove already constructed brickwalls and replace them using a “full English bond”. Other such particulars include allegedly increasing the rate of ADs being issued as the date which the first defendant “purported” to terminate the Contract approached. The plaintiff further set out a table outlining how the number of ADs issued had increased from eight in February 2014 to 39 in September 2014.
(e) The plaintiff finally ties together the various elements of the tort of conspiracy and asserts that Termination Certificate 262 issued by the first defendant was “in furtherance of the conspiracy pleaded above”.
The endpoint of the plaintiff’s pleadings in Suit 1274 in relation to this first “sub-plot” is clear. In gist, the plaintiff asserts that the defendants came together in pursuance of a conspiracy to cause the plaintiff loss, carried out the conspiracy by causing the issuance of wrongful and unwarranted ADs, and finally issued the Notices, two of which eventually gave rise to Termination, in furtherance of the conspiracy.
- [73]
[73] The facts relied in relation to this first “sub-plot” in Suit 1274 are strikingly similar to those relied on in the Arbitration concerning the termination of the Contract. As the plaintiff itself recognises, the “Central Issue in the Arbitration was whether Asplenium had validly terminated the Contract” (emphasis original) and “(w)hether the [third defendant] had, in the course of issuing the relevant Architect’s Directions, Notices and the Termination Certificates, acted under improper pressure and interference by [the second defendant] or any other person acting on behalf of the [first defendant] and/or failed to act in accordance with his duties as an Architect”.
- [74]
[74] To further elaborate, one of the main facets of the plaintiff’s case in the Arbitration for damages for breach of contract was that the first defendant had wrongfully repudiated the Contract by acting on, inter alia, Termination Certificate 262 issued by the third defendant when many of the ADs referred to in that termination certificate as not having been complied with were in fact invalid ADs because the first and/or second defendant had pressured the third defendant to issue them. Put another way, the third defendant had not acted impartially or independently in the exercise of its own judgment in deciding to issue many of the ADs, but had allowed itself to be influenced and pressured by the first defendant and its employees or agents, such as the second defendant, in doing so. As a result, these ADs set out in Termination Certificate 262 were invalid and could not be relied on as bases for the issuance of that termination certificate.
- [75]
[75] A review of the plaintiff’s Statement of Case (Amendment No. 2) in the Arbitration (“SOCA”) shows that the plaintiff relied on the following facts in the Arbitration in support of its cause of action that the first defendant had committed repudiatory breach of contract in terminating the Contract:
(a) First, the plaintiff asserted that the first defendant had not validly terminated the Contract because there was no basis to issue the Termination Certificates relied on to terminate the Contract (see [12] above). The plaintiff asserted that the third defendant had no basis to issue Termination Certificate No. 260, and that notwithstanding the plaintiff already having taken all reasonable and available steps towards proceeding with diligence and due expedition in respect of the works, “the Architect nevertheless proceeded to issue Termination Certificate [No. 260] on the basis of the [plaintiff’s] alleged non-compliance with Notice 260”. The plaintiff also averred in the SOCA that “[a]ny allegation that the [plaintiff] had failed to comply with the Architect’s specific written directions is completely without basis and is strictly denied”. The plaintiff went to address ADs in relation to the brickwalls constructed as part of the Project. The plaintiff’s analysis of the brickwall issue formed the bulk of its analysis in relation to Termination Certificate No. 262, and the plaintiff further alleged in the SOCA that “several of the ADs issued by the [third defendant] did not relate to ‘defects’ per se, but rather were issued in respect of works that were still in progress”, and that the “so called alleged defects, in any event, were frivolous and inconsequential”.
(b) Second, not only did the plaintiff assert that the Termination Certificates were issued without basis, it went on to allege that the third defendant had not acted independently in issuing the ADs. In the SOCA, the plaintiff further claimed that “(d)uring the course of the Project, [the second defendant] had control over the issuance of ADs by the Consultants”.
(c) Third, the plaintiff alleged that the second defendant made several unlawful demands for monetary gratification, and that these demands, among other things, “precluded the [first defendant] from relying on the effect and consequences of such acts on the progress of the Project Works to terminate the contract”.
As is evident from the above, the plaintiff’s SOCA setting out its claim for breach of contract in the Arbitration centred on claims that (a) many of the ADs were without basis and had been improperly/wrongfully issued by the third defendant, (b) the third defendant had not acted independently in issuing the ADs, but was acting in concert with or under the influence of other parties, and (c) the second defendant’s wrongful acts contributed to the limited progress of work on the Project and therefore could not be a basis for the first defendant to terminate the Contract.
- [76]
[76] At the arbitration hearing and in its submissions to the tribunal, as noted in Partial Award 1, part of the plaintiff’s case was that:
More pointedly, the plaintiff argued before the arbitrator that:
- [77]
[77] The arbitrator devoted an entire chapter in his Partial Award 1 titled “Improper Pressure and Undue Influence” to deal with this aspect of the plaintiff’s case. He specifically considered the allegations in relation to the improper pressure exerted on the third defendant by the first defendant and its agents or employees. He concluded that the actions of the second defendant, as agent of the first defendant, did not establish that “improper pressure or undue influence” had operated on the third defendant for the issuance of the ADs and Notices which eventually formed the basis of Termination Certificates 260 and 262. He also concluded separately that the conduct of the first defendant’s CEO Mr William Liem did not have any effect on the third defendant’s decisions to issue the ADs, Notices, and the Termination Certificates. In all instances when it came to the issuance of ADs, the arbitrator found that the third defendant had acted independently and impartially, even though in certain situations it might have acted without due care and skill when a few of the ADs were issued. The arbitrator eventually concluded:
- [78]
[78] I find that a comparison between the essential facts grounding the cause of action in the Arbitration for breach of contract and the cause of action in Suit 1274 for conspiracy, insofar as the first “sub-plot” in concerned, makes clear that they are materially similar, particularly in the following respects.
- [80]
[80] Second, the notion that the third defendant was not independent is another essential similarity in both causes of action. The alleged non-independence of the third defendant was specifically relied on in the Arbitration to undermine the validity of the ADs issued, while the assertion that the architects were part of the first “sub-plot” in Suit 1274 by definition precludes their independence and impartiality. This latter point, in particular, is one which troubles me and for which the plaintiff’s counsel was not able to satisfactorily address in his submissions before me. Put simply, since the arbitrator had found in his Partial Award 1 that the architects had acted independently and properly in the issuance of the ADs, how then is it possible for the plaintiff to argue that the first defendant had conspired with the architects to procure the wrongful issuance of the ADs without necessarily running into the estoppel that operates by reason of the arbitrator’s decision on this point?
- [81]
[81] Third, the second defendant’s acts in demanding monetary gratification were raised in the Arbitration, and now again in these proceedings. In the action for breach of contract in the Arbitration, the plaintiff claimed that the second defendant’s acts, inter alia, improperly pressured or influenced the third defendant to issue the ADs, interfered with the plaintiff’s progress on the Project, and/or constituted improper acts by the first defendant, which precluded the first defendant from relying on those acts to terminate the Contract. In the alleged first “sub-plot” in Suit 1274, the second defendant’s acts and the responses from the plaintiff are framed as having been a reason the second defendant sought to conspire with the other defendants to issue improper ADs.
- [82]
[82] All three of these aspects of the plaintiff’s complaints were adjudicated upon in the Arbitration. While the tribunal recognised that some of the ADs were in fact invalid because they were, for example, not matters that should be properly covered by an AD or that the third defendant had been mistaken as to the facts when it issued the AD, he found that there was no basis to assert that any of the ADs that were issued were the result of illegitimate pressure or interference on the part of the first defendant or its agents. The arbitrator found that, at all times, the architects acted independently and were not influenced in their decisions concerning the ADs. Significantly, the arbitrator found that there were a number of ADs which were valid and which had not been complied with by the first defendant. These ADs provided sufficient basis for the issuance of Termination Certificates 260 and 262, which in turn permitted the first defendant to lawfully terminate the Contract with the plaintiff. The tribunal also rejected any suggestion that the architects had acted improperly in collusion with the first defendant, and indicated that while they had occasionally erred, there was not enough to suggest that they had done so pursuant to any improper purpose or pressure in relation to the issuance of any of the ADs. Further, the tribunal also accepted that the second defendant had behaved improperly in relation to the monetary gratifications that he sought, but that these acts did not cause the third defendant to issue invalid and unwarranted ADs.
- [83]
[83] It can therefore be seen that, on all the above-mentioned aspects of the factual matrix relied upon, all three of which were central to the claims for breach of contract in the Arbitration and the claims for conspiracy in relation to the first “sub-plot” as pleaded in this suit, fundamental similarities exist.
- [84]
[84] I then consider the remedies to which the plaintiff claims to be entitled arising from these facts. It appears to me that the reliefs sought by the plaintiff in relation to the first “sub-plot” in Suit 1274 are materially similar to those sought for breach of contract in the Arbitration. In the Arbitration, the plaintiff sought the following reliefs:
(a) A claim for loss of profits arising from the termination of the Contract;
(b) A claim for work done under the schedule of works;
(c) A claim for piped services installation;
(d) A claim for prime cost and provisional sums, which take into account attendance and profit costs in respect of the various nominated and domestic subcontractors for the respective trades on the Project;
(e) A claim for preliminaries;
(f) A claim for materials on-site and rental charges for equipment, materials, and tools left on-site;
(g) A claim for materials purchased or for which deposits had already been paid, but which remained off-site;
(h) A claim for variation works;
(i) The sum claimed by the first defendant in and in relation to the performance bond; and
(j) A declaration that the Contract was wrongfully terminated by the first defendant.
- [85]
[85] The plaintiff’s claims in the present proceedings are substantially similar with the above-listed claims. In particular, the plaintiff seeks:
(a) Loss of profit arising out of and/or related to the termination of the Contract;
(b) Loss and damage caused by the conduct of the replacement tender and the appointment of the sixth defendant;
(c) Costs and expenses incurred by the plaintiff in its attempts to comply fully with the ADs and Notices issued to it;
(d) Costs and expenses arising out of and/or related to the termination of the Contract, the call on the Performance Bond and disputes arising from the same, including but not limited to legal costs and disbursements and/or staff and managerial costs; and
(e) Interest costs arising out of and/or related to the call on the Performance Bond.
- [86]
[86] For the purposes of my analysis at this juncture, I will only consider the reliefs that are being pursued by the plaintiff flowing from the alleged first “sub-plot”. I will consider the reliefs sought that flow from the alleged second “sub-plot” when I consider (see [113] below) whether the claims in relation to that second “sub-plot” should be struck out on an application of the principles of issue estoppel.
- [87]
[87] From my review of the plaintiff’s case, the main relief being pursued which flows from the first “sub-plot” is damages arising from the termination of the Contract. This is because the object of the first “sub-plot” was the termination of the Contract. As is immediately evident, the claim for loss of profit arising out of or related to the termination of the Contract in Suit 1274 is entirely similar to the claim made in the Arbitration for lost profits (see [84(a) above].
- [89]
[89] An examination of the awards issued by the tribunal in the Arbitration makes especially clear that the remedies sought by the plaintiff in relation to the first “sub-plot” were already specifically addressed by the tribunal:
(a) In respect of the plaintiff seeking damages for loss of profit arising out of or in relation to the termination of the Contract, this was disposed of at the Arbitration by the tribunal deciding that the first defendant was entitled to terminate the Contract, meaning that by extension, the plaintiff was not entitled to damages for loss of profit.
(b) In relation to the plaintiff’s claim for costs and expenses it incurred in attempting to comply fully with the ADs and Notices issued to it, this was fully addressed at the Arbitration:
(i) In relation to the variation works carried out by the plaintiff on the instructions of the architects, the tribunal specifically found that S$121,736.71, representing the value of the variation works, was to be added to the original Contract sum. In reaching this figure, the tribunal adjusted the figures claimed by the plaintiffs in several categories of variation works, including, inter alia, floor finishes and metalwork.
(ii) Further, in relation to the plaintiff’s claim for costs and expenses it incurred in attempting to comply with invalid ADs and Notices issued to it, the tribunal concluded that this claim was untenable because of the plaintiff’s non-compliance with cl 1(5) of the SIA Conditions, which required the plaintiff to give prior notice in writing for claims for extra payment or compensation for variation works. Absent notice in writing, cl 1(5) provides that the contractor “shall be conclusively deemed to have undertaken to comply with the direction without an increase in the Contract Sum or any additional payment or compensation”. On the basis that no such notice in writing had been provided, the tribunal rejected the plaintiff’s claims for costs and expenses incurred in complying with the invalid ADs.
- [91]
[91] What the above analysis on the reliefs being pursued in Suit 1274 underscores is the identity of causes of action on the instant facts. Not only does the cause of action in relation to the first “sub-plot” rely on the same material facts as the plaintiff had relied on in the Arbitration, the plaintiff seeks remedies for the first “sub-plot” which it had already sought in the Arbitration. In short, the same factual matrix is relied upon by the plaintiff to give rise to its claim to be entitled to substantially the same kind of reliefs in these legal proceedings. In my judgment, this illustrates that there is identity of causes of action, and given that all the four requirements for cause of action estoppel are met, cause of action estoppel applies in the present suit as a basis for striking out the plaintiff’s claims for lawful and unlawful means conspiracy in relation to the first “sub-plot”.
Issue estoppel
- [92]
[92] My findings in relation to cause of action estoppel above would in and of themselves suffice to address the application to strike out the first “sub-plot” of the plaintiff’s claims in conspiracy. But, be that as it may, I will proceed to explain why I find that the claims arising out of that first “sub-plot” are nonetheless also untenable on the basis of issue estoppel, even if one is to take the strict view that the claim in the Arbitration was one for breach of contract and is conceptually distinct from the claims for conspiracy pleaded in this suit.
- [93]
[93] Of the requirements for issue estoppel outlined at [44] above, the first three are identical to the first three requirements for cause of action estoppel. The analysis on whether those three requirements are met is therefore similar (see above from [61] to [66]), and I do not propose to repeat it here. Rather, the central issue for present purposes is whether the fourth requirement, for identity of subject-matter, is met in relation to the first “sub-plot”.
- [94]
[94] At [34] to [35] of Goh Nellie ([40] supra), the Court provided the following guidance on the fourth requirement:
- [95]
[95] Turning first to whether the Arbitration traverses the same ground as the present proceeding in relation to the first “sub-plot”, I am of the view that it clearly does. The factual matrices in both the Arbitration and the first “sub-plot” in Suit 1274 are similar, focusing on the origins of the Contract, the second defendant’s alleged wrongdoing, the purported impropriety on the part of the architects, the issuance of the ADs, and ultimately, the termination of the Contract. Both proceedings traverse the same ground and rely on, fundamentally, the same acts. In this regard, [72] to [75] above are instructive in illustrating how striking the similarities are in terms of the factual matrices relied upon.
- [96]
[96] The key determination by the arbitrator was that the Contract had been validly terminated. This determination was reached despite the plaintiff’s arguments at the Arbitration that the architects had behaved improperly, were improperly influenced by the first and/or second defendants, and/or had not acted in an independent manner in wrongfully issuing ADs which were without basis. These arguments were central to the plaintiff’s case at the Arbitration, and essentially the same points are being made in the present Suit – that the architects were party to a conspiracy with the first and second defendants pursuant to which they acted improperly in issuing ADs and, eventually, the Termination Certificates.
- [97]
[97] The basis of the determination by the arbitrator that the Contract had been validly terminated was, in effect, that the ADs had been issued validly, formed a sound basis for the Notices, and that the termination was ultimately warranted. The facts and circumstances giving rise to this determination have not changed and are not capable of change given that the ADs, Notices, and Termination are all past events. My attention has not been drawn to any fresh evidence that will change that factual matrix.
- [98]
[98] As to whether the arbitrator’s determination on these issues was fundamental to his decision, I am of the view that it clearly was. It was at the very heart of the tribunal’s decision as to liability for breach of contract. If the arbitrator had not found in favour of the first defendant on these issues as to the independence of the third defendant and the validity of the ADs, he would not have found that the first defendant had validly terminated the Contract. This is made clear by the arbitrator’s finding as to the applicable legal principle that, if the third defendant had not acted independently in issuing any of the ADs referred to in the Termination Certificates, this would have rendered the certificate(s) invalid and ineffective notwithstanding the existence of other ADs referred to in the Termination Certificates which were not tainted. Specifically, the arbitrator found in Partial Award 1 that:
- [99]
[99] The effect of this finding by the arbitrator cannot be overstated. The arbitrator, in finding that the termination of the Contract was valid, found that none of the ADs relied on in Termination Certificates 260 and 262 were tainted by improper pressure and/or undue influence. Put another way, the arbitrator rejected any suggestion that the third defendant had acted improperly under the influence of the first defendant or in a non-independent manner in relation to all of the ADs relied on in Termination Certificates 260 and 262. In the present Suit, for the plaintiff to establish that there was a conspiracy, it would necessarily have to show that that the first defendant had asked for, and the architects had agreed to, the issuance of ADs which were not the product of their independent decision-making. That would effectively require this Court to come to a view that is the opposite of what the arbitrator had found in relation to the independence of the third defendant and the validity of each of the ADs. A finding of conspiracy in this Suit would therefore necessarily impugn the arbitrator’s findings, which were fundamental to his decision in the Arbitration. Such a collateral attack on a previous binding decision of a properly-constituted tribunal is precisely what the doctrine of issue estoppel seeks to prevent.
- [100]
[100] In reaching this conclusion, I bore in mind the observation by the Court at [37] of Goh Nellie ([40] supra), that:
Having reference to the full panoply of legal proceedings which have transpired between the parties, I am satisfied that the plaintiff has had ample opportunity to ventilate its entire suite of arguments. I do not agree with the plaintiff’s counsel’s submission that finding an issue estoppel on the present facts would foreclose the plaintiff from arguing an issue which was not the central issue decided in the Arbitration. Rather, it is quite the reverse – the plaintiff succeeding in Suit 1274 that there was a conspiracy necessitates a finding that the conspiracy gave rise to the termination of the Contract, which caused the plaintiff to suffer loss. The plaintiff succeeding in the present suit would undoubtedly undermine the arbitrator’s findings that (a) there was no collusion, (b) the third defendant was independent in his decision-making, (c) none of the ADs were tainted and invalid by reason of improper pressure, (d) the first defendant’s termination of the Contract was therefore justified, and (e) that the plaintiff is accordingly not entitled to damages from the termination of the Contract. I do not accept, given the totality of the circumstances, that the plaintiff should be permitted to re-litigate these points.
- [101]
[101] Given my finding that all the requirements for issue estoppel are met in relation to the first “sub-plot”, I conclude that the plaintiff’s claims in conspiracy relating to the first “sub-plot” are precluded on the basis of both issue estoppel and cause of action estoppel (see [60] to [100] above). I therefore agree with the first defendant that there is a proper basis to strike out those claims under O 18 r 19(1)(b) and/or (d) of the ROC.
The second “sub-plot”
- [102]
[102] I now turn to the question of whether the plaintiff’s claims in conspiracy arising from the second “sub-plot” should be struck out on the basis of issue estoppel. In this regard, the first defendant argues that the issues underlying the remedies claimed for the second “sub-plot” were already dealt with in the Arbitration.
The judgment continues past this page. Read the rest at eLitigation.