High Court · Decided 6 August 2020
Comfort Management Pte Ltd v OGSP Engineering Pte Ltd and another
Feedback & support[2020] SGHC 165 · Case no. Suit No 509 of 2017
✱ What happened, in plain English
There is no plain-English summary of this judgment yet.
Ask about this judgment →Grounds of decision
Official text from eLitigation
Introduction
- [1]
[1] This action arises out of a lump sum construction contract which the plaintiff entered into with the first defendant in October 2013 for a project in Jurong (“the Project”). The first defendant carried out the works for the air conditioning ducting system and mechanical ventilation system (“the Works”) for the Project. The main contractor for the Project subcontracted the Works to Lead Management Engineering & Construction Pte Ltd (“Lead”). Lead in turn sub-subcontracted the Works to the plaintiff under a lump sum contract (“the Lead Contract”). The plaintiff then sub-sub-subcontracted the Works to the first defendant under a back-to-back lump sum contract (“the Comfort Contract”).
- [2]
[2] The first defendant duly commenced work under the Comfort Contract in October 2013. However, it demobilised its team and withdrew from the site on 9 October 2014. It is common ground that the first defendant carried out no works of any kind for the Project after that date. The plaintiff’s case in this action is that the first defendant had completed only 65% of the Works before it withdrew from the site. The first defendant’s case is that it had completed or substantially completed the Works before it withdrew.
- [3]
[3] In this action, the plaintiff claims the following sums against the first defendant:
(a) approximately $410,000, being the plaintiff’s overpayment to the first defendant for the Works;
(b) $81,000 in liquidated damages for 162 days of delay;
(c) $86,606.41, being back charges imposed by Lead on the plaintiff for the first defendant’s defective work; and
(d) $918,306.09, being the sum which the plaintiff paid to the first defendant pursuant to an Adjudication Determination (“AD”) in 2017.
In the alternative, the plaintiff claims damages against the first defendant to be assessed.
- [4]
[4] To supervise the Works on site, the plaintiff engaged the second defendant as its project manager. In this action, the plaintiff claims against the second defendant the sum by which the plaintiff alleges it overpaid the first defendant (see [3(a)] above). The plaintiff’s case against the second defendant is that he is liable to the plaintiff for this sum because he breached his duties to the plaintiff in contract and in tort by over-certifying the sum due from the plaintiff to the first defendant under the Comfort Contract.
- [5]
[5] The first defendant in turn brings a counterclaim in this action against the plaintiff seeking the following relief:
(a) if the AD is set aside:
(i) $180,013.27 as outstanding payment under the Comfort Contract price for completion of the Works;
(iv) $30,178.78 arising from materials which the first defendant alleges it purchased at the request of the plaintiff;
(b) if the AD is not set aside, a declaration that the first defendant is entitled to the moneys awarded under the AD; or
(c) alternatively, a quantum meruit for the work the first defendant actually did.
The issues
- [6]
[6] The claim and counterclaim raise the following issues:
(a) How much of the Works did the first defendant complete before it left the site on 9 October 2014 and is the first defendant liable to pay liquidated damages for delay (“the Works Issue”)?
(b) Were there any defects in the Works and is the plaintiff entitled to impose back charges on the first defendant (“the Defects Issue”)?
(d) Is the first defendant entitled to recover on two variation orders and, if so, in what amount (“the Variation Orders Issue”)?
(e) Did the second defendant breach his duties in contract or tort by over-certifying the amount of work completed by the first defendant or by acting in a position of conflict of interest, thereby causing the plaintiff to suffer loss (“the Personal Duty Issue”)?
- [7]
[7] Having considered and analysed the parties’ evidence and submissions, I have come to the following conclusions:
(a) On the Works Issue, I find that the first defendant had completed 95.29% of the Works as at 9 October 2014. I accordingly dismiss the plaintiff’s claim that the first defendant has been overpaid. The plaintiff is in fact obliged to pay the first defendant a further sum of $121,138.27. The plaintiff, however, is entitled to recover $81,000 from the first defendant as liquidated damages for 162 days of delay.
(b) On the Defects Issue, I dismiss the plaintiff’s claim against the first defendant.
(c) On the Variation Orders Issue, I find that the first defendant is entitled to recover its entire counterclaim of $14,300 on VO1. I find that the first defendant is not entitled to recover its counterclaim on VO2 in contract but is entitled to a quantum meruit for the work done on VO2. I assess the value of the quantum meruit at two-thirds of its claim of $621,828.73 on VO2.
(d) On the Materials Issue, I dismiss the first defendant’s counterclaim against the plaintiff.
(e) On the Personal Duty Issue, I dismiss the plaintiff’s claim against the second defendant.
- [8]
[8] I now set out the reasons for my decision.
The Works Issue
- [9]
[9] By the time the first defendant withdrew from the site on 9 October 2014, the plaintiff had paid the first defendant just over $1.18m under the Comfort Contract. After adjusting for variations and back charges, the plaintiff’s case is that it had overpaid the first defendant by about $410,000.
- [10]
[10] The contemporaneous evidence on the Works Issue is an email which the second defendant, as the plaintiff’s project manager, sent on 9 October 2014 at 6.44am (“9 October Email”) to Mr Natarajan Chidambaram (“Mr Ram”), the first defendant’s project manager. The second defendant attached to this email a list of items which the first defendant had failed to complete. The second defendant derived this list from a list of outstanding items which Lead had compiled and attached to an email to the plaintiff dated 3 October 2014 (described in more detail at [24] below). Lead followed this with three further emails to the plaintiff after the first defendant withdrew from the site attaching virtually the same list of outstanding items.
- [11]
[11] The plaintiff’s case is that the bulk of the items which it listed in the 9 October Email relate to the Works, ie, works within the scope of the Comfort Contract, and not to variations, ie, works which the parties agreed outside the scope of the Comfort Contract. To support its case, the plaintiff says it had to spend the substantial sum of over $397,000 after 9 October 2014 to complete the Works.
- [12]
[12] The first defendant’s case is that the Works were complete or substantially complete by 9 October 2014. It says that the 9 October Email relates entirely to variations and not to any of the Works. In support of its argument, the first defendant relies on Certificate of Payment No 13 (“COP 13”) which Lead issued to the plaintiff on 28 September 2014. In COP 13, Lead certified that 95.29% of the Works had been completed as at 15 September 2014. The value of the Comfort Contract was $1.25m. This necessarily implies that, as at 15 September 2014, the value of the outstanding Works was only 4.71% of $1.25m, or $58,875. Further, the first defendant remained on site and continued work from 15 September 2014 until 9 October 2014. The percentage of the Works actually completed by 9 October 2014 is therefore likely to be even more than the 95.29% which Lead certified complete as at 15 September 2014.
- [13]
[13] The first defendant points out that the second defendant, in the 9 October Email, makes no allegation at all that the first defendant had in fact failed to complete the Works. The first defendant also relies on another email dated 10 October 2014 which the first defendant sent to the second defendant as the plaintiff’s project manager. In that email, the first defendant asserts that the Works were complete. The plaintiff did not reply to this email or challenge this assertion.
- [14]
[14] The first defendant computes its counterclaim of $180,013.27 as follows:
Lump sum contract does not bar the plaintiff’s claim
- [15]
[15] I deal at the outset with a preliminary point raised by the first defendant. It argues that it is fundamentally wrong for the plaintiff to reassess the true proportion of the Works completed as at 9 October 2014 because the Comfort Contract is a lump sum contract. It is back-to-back with the Lead Contract. Lead certified the Works to be 95.29% complete and paid the plaintiff accordingly. A reassessment is both legally and factually unsustainable. The plaintiff should not be entitled to recover any alleged overpayment to the first defendant.
- [17]
[17] Indeed, cl 6.1(c) of the General Conditions of the Lead Contract, read with cl 3 of the Special Conditions provides that the first defendant “shall be paid in the following manner, without prejudice to justifiable deductions … [a]ll progress payment shall be made monthly based on the actual value of work properly executed on site” [emphasis added] (see [49] below). This makes clear that the first defendant’s contractual entitlement to receive progress payments is based on an objective assessment of the actual value of the Works it has properly executed on a month by month basis. In the event of a dispute alleging that the subcontractor was paid more than it was contractually entitled to be paid, a fact-finder must ascertain objectively the actual value of the work which the subcontractor properly executed on site.
- [18]
[18] It is uncontroversial that a contractor is entitled to recover an overpayment from a subcontractor under a lump sum contract, provided that the contractor is able to satisfy the court that the amount paid was not in fact contractually commensurate with the actual work done (see Mansource Interior Pte Ltd v CSG Group Pte Ltd [2017] 5 SLR 203).
- [19]
[19] There is thus no merit to the first defendant’s preliminary point.
Second defendant’s evidence
- [20]
[20] I begin my analysis of the Works issue by considering the evidence of the second defendant. That evidence was before me both in the form of contemporaneous emails which he sent and received in October 2014 and also his oral evidence under cross-examination.
- [21]
[21] I accord great weight to the second defendant’s evidence. He was the plaintiff’s project manager. He was personally involved in supervising the Works on site on a daily basis. He thus supervised construction personnel and activities on site and coordinated with the other contractors. As such, he dealt personally both with Lead and with the first defendant. Crucially, the second defendant was the only person deployed by the plaintiff to be stationed on site to supervise the Works, both before and after 9 October 2014.
- [22]
[22] It is true that the plaintiff’s general manager at the time, Mr Lawrence Wu (“Mr Wu”), also played a role in supervising the Works. But Mr Wu’s role was not as direct as the second defendant’s. In effect, Mr Wu delegated responsibility for the Works and for the daily operations on site to the second defendant. The plaintiff’s director, Mr Lim Fatt Seng (“Mr Lim”), accepted this in cross-examination.
- [23]
[23] I now consider the second defendant’s contemporaneous emails and his oral evidence at trial. The result is that I accept the second defendant’s characterisation of the outstanding items as at 9 October 2014 being mostly variations but including some original Works.
Lead’s email of 3 October 2014
- [24]
[24] On 3 October 2014, Lead emailed the second defendant listing the items then outstanding under the Lead Contract, asking the plaintiff to “[k]indly increase your manpower provisions and expedite all of this outstanding works”. On the same day, the second defendant responded to say that most of the outstanding items contained in the list of 3 October 2014 were variations:
He therefore implied that some of these outstanding items were not variations, ie, part of the Works.
- [25]
[25] The second defendant confirmed this at trial:
The 9 October Email
- [26]
[26] The second defendant then wrote the 9 October Email to the first defendant’s Mr Ram. It bears the title “Outstanding works for ACMV system …”. “ACMV” is the industry initialism for “air-conditioning, mechanical and ventilation”. Attached to this email is a list of 27 items which the second defendant said were outstanding as at 9 October 2014. This list was drawn from Lead’s 3 October 2014 email. I set out an extract from the 9 October Email:
- [27]
[27] It is common ground that the 9 October Email accurately lists the items which were in fact outstanding as at 9 October 2014. Also produced in evidence were three emails which Lead sent to the plaintiff on 16, 17 and 20 October 2014, after the first defendant had withdrawn from the site, repeatedly emphasising the same outstanding items.
- [28]
[28] As mentioned, the fundamental disagreement between the parties is whether the 9 October Email lists items which are part of the Works or which are variations. It is significant to me that the second defendant refers in the body of the 9 October Email both to the plaintiff having paid 90% of total contract sum and variation claims of 80% of total VO value. That indicates to me that the second defendant intended the 9 October Email, read in context, to list both Works and variations. He does not, however, characterise each of the outstanding items as either Works or variations or even their respective proportions.
Cross-examination on the 9 October Email
- [29]
[29] The second defendant confirmed my reading of the 9 October Email in cross-examination. His evidence was that not all of the Works were complete by 9 October 2014. He also confirmed that he listed the outstanding items without distinguishing between Works and variations:
The position after 9 October 2014
- [30]
[30] The second defendant’s evidence was to similar effect when he was asked about the position after 9 October 2014. One of the subcontractors engaged by the plaintiff after 9 October 2014 to complete the Lead Contract was a company of which the second defendant is a director. The second defendant’s evidence was that the work which that company undertook after 9 October 2014 comprised a combination of both Works and variations:
- [32]
[32] However, Ms Lew conceded that this key fact appeared nowhere in her affidavit of evidence in chief. I find it difficult to believe that such a material fact could have been omitted. Further, Ms Lew could not satisfactorily explain how certain items which made up this total of about $397,000 related to the Works at all.
- [33]
[33] I therefore do not accept that the plaintiff spent $397,000 after 9 October 2014 on the Works alone. It spent that sum on both the Works and on items not included in the Works.
The first defendant’s 10 October 2014 email
- [34]
[34] On 10 October 2014, the first defendant sent an email to the second defendant asserting that the Works were complete (see [13] above). The second defendant did not respond to the first defendant to deny or challenge this assertion. The first defendant therefore invites me to draw the inference that the list of outstanding items were all variations.
- [35]
[35] I decline to draw that inference. It is contrary to the contemporaneous documentation and to the tenor of the second defendant’s evidence, which I have accepted. It is also the case that the first defendant in this email did not allege expressly that it had completed the Works before withdrawing on 9 October 2014. Quite the contrary. In this email, the second defendant said merely that it had “already completed almost all main scope (only certain area which conflicts with the main scope)” [emphasis added].
Conclusion on the second defendant’s evidence
- [37]
[37] I accept the second defendant’s evidence that the 9 October Email referred to outstanding items which were both Works and variations. That suffices for me to reject the first defendant’s position that the Works were complete as at 9 October 2014.
- [38]
[38] Unfortunately, the second defendant was unable to take a clear and unequivocal position in cross-examination and re-examination on each outstanding item being Works or variations (see Annex 1). Further evidence and analysis is therefore necessary to determine the actual proportion of the Works which the first defendant had completed by 9 October 2014.
COP 13
- [39]
[39] To establish its case as to the proportion of the Works which were complete by 9 October 2014, the first defendant relies on two points. First, Lead issued COP 13 to the plaintiff on 15 September 2014. COP 13 certified that 95.29% of the Works was complete as at 15 September 2014. Second, the first defendant continued with the Works between 15 September 2014 and 9 October 2014. On this basis, the first defendant submits that it had substantially completed the Works by 9 October 2014.
- [40]
[40] The plaintiff accepts – as it must – that COP 13 does in fact certify 95.29% completion of the Works. However, it argues that this certification is at best equivocal. As observed by the plaintiff’s counsel in the course of oral closing submissions, Lead itself listed a number of outstanding items in its email to the second defendant dated 3 October 2014. COP 13 cannot, therefore, be taken at face value as representing Lead’s position on how much of the Works were complete.
- [41]
[41] I accept that COP 13 accurately sets out the proportion of the Works complete as at 15 September 2014. I do not consider that COP 13 is inconsistent with my finding that the 9 October Email describes both Works and variations. The second defendant confirmed this in cross-examination. His evidence was that 95.29% of the Works, as certified in Lead’s COP 13, was in fact complete by 15 September 2014 and that this was consistent with the plaintiff’s Progress Claim No 12 issued on 18 September 2014 to Lead:
This evidence is not inconsistent with the second defendant’s evidence that most of the outstanding items in the 9 October Email were variations rather than Works.
- [42]
[42] I therefore find that the first defendant had completed at least 95.29% of the Works by 9 October 2014.
Mr McGeoch’s expert report
- [43]
[43] In arriving at this finding, I do not accept the evidence of the plaintiff’s expert, Mr Mark Alexander McGeoch (“Mr McGeoch”). Mr McGeoch’s evidence is that the first defendant had completed only 65% of the Works by 9 October 2014. But my findings of fact have undercut the assumptions of fact which underlie his expert evidence.
The first defendant’s preliminary point
- [44]
[44] The first defendant’s submission that I should accept Lead’s COP 13 certification over Mr McGeoch’s evidence because COP 13 originates from a neutral third-party ie, Lead, who has no interest in the outcome of these proceedings. Implicit in that submission is a suggestion that Mr McGeoch’s evidence should be discounted simply because he is an expert witness engaged and called by the plaintiff.
- [45]
[45] I reject this submission. The partisan expert is certainly a recurring feature and an intractable problem of adversarial litigation. But in an adversarial system like ours, expert evidence is not discounted simply because the expert is selected, engaged and paid by a party. A party who attacks the evidence of an expert witness must do so on the basis of deficiencies in the expert’s credentials, factual premises, methodology or reasoning. The party cannot do so simply because the expert is party-appointed (see Saeng-Un Udom v Public Prosecutor [2001] 2 SLR(R) 1 at [26]).
Mr McGeoch’s methodology
- [47]
[47] Having done all this, Mr McGeoch’s conclusion was that by 9 October 2014, the first defendant had completed only 65% of the Works. In arriving at this conclusion, Mr McGeoch made two critical assumptions. First, he assumed that the 9 October Email was an accurate description of the outstanding items. That assumption is common ground and is not controversial. Second, however, he assumed that all of the outstanding items were Works rather than variations. Mr McGeoch candidly accepted that if the factual premises underlying his opinion were wrong, his conclusions would also be wrong.
- [48]
[48] Given my finding that the list of outstanding items on 9 October 2014 consisted of both Works and variations, Mr McGeoch’s opinion that the first defendant had completed only 65% of the Works as at 9 October 2014 is of no assistance to me. This is not, of course, to attribute fault to Mr McGeoch. As an expert witness, he cannot be faulted for assuming the factual case of the party appointing him to be correct.
Overpayment
- [49]
[49] Clause 6.1 of the Lead Contract, as amended by cl 3 of Appendix B, governs the terms of payment:
- [50]
[50] Clause 6.1(c) expressly provides that the first defendant is entitled to be paid every month based on the actual value of the work it has properly executed on site in the preceding month. It is not disputed that the first defendant’s progress payment for its final month on site has fallen contractually due.
- [51]
[51] The issue then is to determine the actual proportion of the Works that were completed by 9 October 2014. I begin by reiterating that I have accepted the second defendant’s evidence that, although most of the outstanding items listed in the 9 October Email were variations, some of them were Works. It is therefore necessarily the case that the Works were not complete by 9 October 2014. The first defendant, in its own closing submissions, also relies on the second defendant’s evidence that the outstanding items listed in the 9 October Email were a combination of Works and variations. This implicitly accepts that some of the Works remained incomplete on 9 October 2014.
- [52]
[52] The true quantum of the Works completed by 9 October 2014 must lie somewhere between 95.29% and 100%. However, the first defendant presented an all-or-nothing case that the Works were complete as of 9 October 2014. In particular, the first defendant did not plead or present an alternative case on the proportion of Works it had completed if the 9 October Email were to be found to refer to a combination of Works and variations.
- [53]
[53] The burden of establishing the proportion of the Works actually completed by 9 October 2014 lies on the first defendant. I have no basis to find that, as at 9 October 2014, the first defendant had completed any Works beyond the 95.29% certified in COP 13.
- [54]
[54] The first defendant is therefore entitled to be paid as follows:
- [55]
[55] I therefore dismiss the plaintiff’s claim for overpayment and allow the first defendant’s counterclaim in part, in the sum of $121,138.27.
Liquidated damages
The parties’ cases
- [56]
[56] Clause 17 of Appendix A of the Lead Contract, as amended by cl 7 of Appendix B of the contract, entitles the plaintiff to recover liquidated damages at a rate of $500 per day during the period in which the Works remain incomplete:
- [57]
[57] The Temporary Occupation Permit (“TOP”) for the Project was issued on 24 December 2014. It is undisputed that the Comfort Contract stipulated that the Works were to be completed by 15 July 2014 and that no extension of time was either requested or approved. From 24 December 2014 to 15 July 2014 is 162 days of delay. The plaintiff’s case is that it is entitled to rely on cl 17.3 to recover liquidated damages of $81,000 from the first defendant, being liquidated damages for 162 days of delay at the rate of $500 per day.
The liquidated damages clause is not a penalty clause
- [58]
[58] The first defendant submits that there was in fact no delay in completing the Works. And that even if there was delay, it was not caused by the first defendant but by the plaintiff’s own failure to issue proper written instructions or drawings. Moreover, given that the Works were complete by 9 October 2014, any liquidated damages should run up to 9 October 2014 and not to 24 December 2014.
- [59]
[59] The first defendant pleads that liquidated damages of $500 per day “do not represent a genuine pre-estimate of loss and thus, [the liquidated damages clause is] void and unenforceable”. This puts in issue whether the liquidated damages clause is enforceable as a penalty. But the first defendant did not pursue this issue in the evidence or in any of its submissions. The plaintiff submits that $500 is only 0.04% of the total contract price under the Comfort Contract and “is not extravagant nor unconscionable in amount in comparison with the greatest loss conceivable from a breach of the Subcontract”. The plaintiff goes on to point out that besides a bare assertion, the first defendant “has not adduced any such evidence at trial and as such, failed to discharge its legal burden of proof”.
- [60]
[60] I accept the plaintiff’s submissions. To the extent that the first defendant continues to take the point that the liquidated damages clause is unenforceable as a penalty, I find that it is not.
The plaintiff need not prove loss
- [61]
[61] I deal first with a preliminary point raised by the first defendant. The point is that the plaintiff is not entitled to liquidated damages given that the Comfort Contract is back-to-back with the Lead Contract and Lead imposed no liquidated damages on the plaintiff. In short, the argument is that the plaintiff has suffered no actual loss, even if delay is proven.
- [62]
[62] This argument is without merit for two reasons. First, it misunderstands what a back-to-back contract entails. The term “back-to-back” is “not a term of art, even though it is a term found with some regularity in sub-contracts in the construction industry” (GIB Automation Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd [2007] 2 SLR(R) 918 at [35]). It is essentially a pragmatic term of incorporation, allowing a subcontract to use that phrase to incorporate the terms of the head contract. Despite these words of incorporation appearing in a subcontract, the subcontract and the head contract remain distinct contracts. The two contracts have distinct sets of parties and create two distinct sets of contractual rights and obligations.
- [63]
[63] Second, this argument also misunderstands the role of a liquidated damages clause in contracts and in construction contracts in particular. An enforceable liquidated damages clause does not cease to yield damages simply because the party seeking to rely upon the clause has, in fact, suffered no loss. The plaintiff’s right to recover liquidated damages in accordance with the clause accrues when the contract is made and does not depend on proof of loss when the contract is breached. Therefore, whether Lead in fact imposed liquidated damages on the plaintiff is a legally irrelevant consideration and does not affect the plaintiff’s right to recover liquidated damages from the first defendant under the Comfort Contract. After all, there could be any number of reasons for Lead not levying liquidated damages on the plaintiff under the Lead Contract which would have no bearing at all on the first defendant’s liability to the plaintiff under the Comfort Contract. For example, Lead could have agreed to waive its right to liquidated damages against the plaintiff as a gesture of goodwill, as part of a compromise or as a calculated commercial decision in light of potential future dealings with the plaintiff.
The first defendant is liable for liquidated damages
- [64]
[64] For the reasons that follow, I find that the plaintiff is entitled to recover liquidated damages from the first defendant amounting to $81,000.
- [65]
[65] Mr Ram’s evidence was that the first defendant had never received any complaints from the plaintiff or Lead about slow progress in the Works. I do not accept this evidence. A chain of emails from 7 September 2013 to 27 August 2014 establishes that the plaintiff and Lead expressed concerns repeatedly to the first defendant about its ability to complete the Works in time. When confronted with this chain of emails, Mr Ram conceded that they showed complaints about the first defendant’s slow pace in carrying out the Works. I also note that in an email dated 25 September 2014 to Mr Ram, the second defendant informed that “based on contract outstanding works still haven’t completed yet and suppose to completed based on contract by 15th July 2014”. At trial, the second defendant confirmed that this referred to Works that remained incomplete as of 25 September 2014.
- [66]
[66] It follows from my findings above at [53] that the first defendant did not in fact complete the Works by 9 October 2014. I accept the plaintiff’s submission that this prima facie caused delay entitling the plaintiff to claim liquidated damages under cl 17.3 of the Lead Contract.
Variations not proven to be the cause of the delay
- [67]
[67] The first defendant submits in response that any delay in the first defendant completing the Works on time is attributable to the substantial and extensive variations that the plaintiff asked the first defendant to undertake, which were in turn triggered by variations which Lead asked the plaintiff to undertake. In total, Lead issued four variation orders to the plaintiff. I will refer to them by the abbreviations used at trial: (a) CVO1 valued at $50,000; (b) CVO2 valued at $50,000; (c) CVO3 valued at $260,000; and (d) CVO4 valued at $300,000. These are reflected in Lead’s Statement of Final Account dated 8 April 2015.
- [68]
[68] The first defendant submits further that the value of these variation orders in total is $660,000. They were coupled with a back charge of $86,606.41 to total almost $750,000. The price under the Lead Contract was only $1,500,000. The variation orders issued by Lead to the plaintiff amounted to almost 50% of the value of the Lead Contract. These must therefore be regarded as substantial variations which inevitably would have contributed to a delay in the first defendant completing the Works.
- [69]
[69] I am unable to accept this submission. I agree with the plaintiff’s submission made in the course of oral closings that the principles developed in the context of extensions of time, and in particular, the notion of criticality, are helpful in considering liability for delay.
- [70]
[70] Generally, only a supervening activity or an event which lies on the critical path will suffice to relieve a contractor of liability for delay. As set out in Chow Kok Fong, Law and Practice of Construction Contracts, vol 1 (Sweet and Maxwell, 5th Ed, 2018) (“Law and Practice of Construction Contracts”) at para 9.272:
- [71]
[71] It is the first defendant who asserts that the delay arose as a result of the variation orders. The burden is therefore on the first defendant to prove the variations are on the critical path, and hence were causally connected to the delay. However, the first defendant provided no delay analysis at all to establish this.
- [73]
[73] Relative value also fails to address the causal relationship between the variations and the delay occasioned to the Works. For example, if work on the variations could not commence until the first defendant completed the Works, then the variations quite clearly could not have caused the delay. Likewise, if the variations could have been carried out concurrently with the Works, that may – but will not necessarily – imply liability for delay. Another facet relates to the extent which the variations might have in fact delayed the completion of the original Works ie, the amount of additional time required. All these critical variables remain entirely unaddressed by the first defendant’s broad-brush metric of proportionate value.
Start date for the delay
- [74]
[74] It is common ground that the first defendant did not ask the plaintiff for any extension of time. As such, any delay in completion of the Works should run from 16 July 2014, the contractual completion date provided in Appendix D of the Lead Contract.
- [75]
[75] The inference I draw from the first defendant’s failure to seek an extension of time is particularly adverse to the first defendant. If the first defendant was reasonably of the view that these variations might give rise to any delay, it would be expected to seek an extension of time from the plaintiff. Alternatively, it would be expected to have sought a waiver of the plaintiff’s rights under the liquidated damages clause. The first defendant, having been in the construction industry since 2008 and specialising in sheet metal fabrications, thermal installations, fire protections and air-conditioning ducting and mechanical ventilation works and having been involved in more than a dozen projects, must surely not have been ignorant as to its rights and obligations under a construction contract.
Conclusion
- [76]
[76] As such, I allow the plaintiff’s claim for liquidated damages arising from the first defendant’s delay in completing the Works. For this purpose, I adopt the date of TOP as the de facto date of completion. The liquidated damages will therefore run as claimed for 162 days from 16 July 2014 to 24 December 2014, and amount in value to $81,000.
The Defects Issue
The first defendant’s case
- [79]
[79] The first defendant’s case is that it had, on more than one occasion, asked the plaintiff for a list of defects. However, the plaintiff failed to provide a list and did not attend on site to inspect the Works. Moreover, the first defendant points out that the plaintiff failed to adduce any evidence that Lead did in fact impose back charges on the plaintiff amounting to $86,606.41.
- [80]
[80] I begin by reiterating my observation at [62] above. The Comfort Contract and the Lead Contract are two legally distinct sets of contractual rights and obligations. Evidence that Lead imposed a back charge on the plaintiff is not a prerequisite to the plaintiff’s right to recover under this provision. Likewise, Lead’s failure to impose a back charge does not ipso facto extinguish the plaintiff’s right to recover under this provision. The same reasoning applies to the plaintiff’s failure to notify the first defendant of the defects. Notice of defects is not a prerequisite to the plaintiff’s right to recover under this provision.
The plaintiff’s case
- [81]
[81] The key document on this issue is the email dated 8 April 2015 sent by Lead’s Assistant Quantity Surveyor, Ms Hoo Yin Shi (“Ms Hoo”), to the plaintiff, enclosing the Statement of Final Account (“8 April Email”). However, the 8 April Email does not make any reference to the back charge alleged by the plaintiff. In the email, Ms Hoo says that the plaintiff’s “Tax Invoice shall state the amount of S$347,413.52 after net [sic] off the Agreed Backcharges (BC001 & BC002)”. The attachment to the 8 April Email specifies this to be $13,196.25 for BC001 relating to the supply for duct workers and $2,645 for BC002 relating to the fine for hacking of plastered wall.
- [83]
[83] Moreover, Ms Lew could not point to any contemporaneous evidence to support the assertion in her affidavit that Lead had imposed net additional back charges amounting to $86,606.41 on the plaintiff. She did point to Backcharge Notification BC003 dated 28 October 2014 amounting to $48,403.50. But this clearly fails to account for a sum of $38,197.91 out of the $86,606.41. As for BC004, Ms Lew claimed that Lead did not provide a copy of this back charge after the final settlement. Although it was raised at the meeting on 7 April 2015, Lead subsequently refused to accede to her requests for a copy. Ms Lew also conceded that if there was any defective work, there was no evidence that notice was given to the first defendant to rectify it.
The second defendant’s evidence
- [84]
[84] On the other hand, the second defendant’s evidence was that the “Lump Sum Discount” in CVO4 was not a consolidation of BC003 and BC004. He testified further that he had rejected Lead’s BC003 on behalf of the plaintiff on 19 January 2015.
- [85]
[85] It is telling that in the email disputing BC003, the plaintiff’s own position (as taken by the second defendant on its behalf) was that the alleged defects were not the result of the first defendant’s failures, but were due to Lead’s own actions.
- [86]
[86] The second defendant further denied that the back charge resulted from any delay by the first defendant.
My findings
- [88]
[88] I am therefore not satisfied that the plaintiff has proven its entitlement to recover under cl 18.4(a)(ii) of the Lead Contract. I therefore dismiss the plaintiff’s claim for back charges amounting to $86,606.41. This means that any claim that the plaintiff might advance for the smaller sum of $15,841.25 for the back charges reflected only in BC001 and BC002 is also dismissed. It is the plaintiff’s pleaded case that this smaller sum is already accounted for in the figure of $1,185.686.73 which the plaintiff paid to the first defendant up to 9 October 2014.
The Variation Orders Issue
VO1
- [90]
[90] The first defendant’s case is that it completed all the works comprised in VO1. It was therefore entitled to be paid the full $130,000. However, in breach of contract, the plaintiff has paid the first defendant only $115,700 for VO1. The first defendant relies on Lead’s COP 13 issued to the plaintiff which records that CVO3 was 100% complete as at 15 September 2014. The first defendant therefore claims the outstanding sum of $14,300.
- [91]
[91] The plaintiff argues that the first defendant admitted in Payment Claim 12 (“PC 12”), which formed the basis of the AD, that only the VO2 sums were allegedly left unpaid, thereby impliedly admitting that VO1 works were fully paid. This, the plaintiff asserts, is substantiated by Mr McGeoch’s expert report finding that the value of VO1 should at best amount to $115,700. This is in line with the plaintiff’s assessment in Payment Claim 11 (“PC 11”) and also corresponds to the first defendant’s claim in PC 12. Hence, there is nothing due to the first defendant for VO1.
- [92]
[92] At the outset, I do not accept that the first defendant’s claim in PC 12 amounts to an admission precluding it from claiming a further payment on VO1 works. It is undisputed that the price of VO1 was $130,000. It is equally undisputed that the plaintiff paid the first defendant only $115,700 for VO1. The plaintiff does not suggest that PC 12 has raised any sort of estoppel against the first defendant and in favour of the plaintiff. In the absence of an estoppel, there is nothing to preclude the first defendant from claiming the outstanding $14,300 now.
- [93]
[93] The plaintiff also does not suggest that Lead’s certification CVO3, which comprises VO1 downstream, was not accurate. Indeed, in cross-examination, Mr McGeoch accepted that the first defendant should in fact be allowed to recover the balance under VO1 in light of Lead’s certification:
- [94]
[94] Given Mr McGeoch’s own concession that his figure was based only on information available to him at the time and did not take into account Lead’s certification, I allow the first defendant’s counterclaim for the outstanding amount of $14,300 under VO1.
VO2
The first defendant’s case
- [95]
[95] The first defendant contends that it is entitled to the sum of $621,828.73 under VO2 for work carried out at the Commercial Block. The quantum of this claim is evidenced by a tax invoice which the first defendant issued to the plaintiff on 29 June 2016. The plaintiff is obliged to pay because the second defendant, as the plaintiff’s project manager, instructed the first defendant to carry out this work. The second defendant gave these instructions either orally or in the form of written drawings, in both cases accompanied by a promise to pay. The written drawings may be found as part of PC 12 as well as drawings issued by the second defendant to the first defendant. The first defendant’s case is that it completed the variation works under VO2 sometime in September 2014.
- [96]
[96] The variations comprised in VO2 are broken down in an email which Mr Ram sent to the second defendant. These variations were remedial works requiring the first defendant to dismantle and dispose of existing ducts and to fabricate and install replacement ducts.
- [97]
[97] Additionally, as Lead had paid the plaintiff a total sum of $560,000 for additional or variation works under Certificate of Payment No 14R1 dated 13 March 2015 (“COP 14”) for CVO3 and CVO4, the back-to-back nature of the Comfort Contract means that there is no reason for the plaintiff to dispute the first defendant’s entitlement to recover the sum owing under VO2. The first defendant’s implicit position is that variation works carried out under VO2 were part of CVO3 and CVO4.
- [98]
[98] The first defendant’s case is also supported by the fact that the adjudicator accepted the claim for VO2. This was upheld by the Court of Appeal in Comfort Management Pte Ltd v OGSP Engineering Pte Ltd [2018] 1 SLR 979 (“Comfort v OGSP (CA)). Finally, the first defendant asserts that the particulars of the first defendant’s claim under this head have been consistent since 1 October 2014, as evidenced by the email sent from Mr Ram to the second defendant on 1 October 2014 (“1 October 2014 Email”).
The plaintiff’s case
The two-stage approach
- [100]
[100] The court undertakes a two-stage approach to a variation claim. As the learned author of Law and Practice of Construction Contracts at para 5.008 puts it:
- [101]
[101] VO2 constituted variation works within the meaning of the Comfort Contract. The second defendant confirmed this at trial. Hence, I shall proceed to consider whether the contractual requirements for the first defendant to recover have been satisfied.
- [102]
[102] The fact that Lead paid the plaintiff $560,000 for CVO3 and CVO4 does not discharge the first defendant’s burden of proving that it carried out VO2. As I have said above at [62], the Comfort Contract and the Lead Contract are distinct contracts with distinct rights and distinct obligations. The burden rests on the first defendant to make out its right under the Comfort Contract to recover its claim on VO2. Relying on Lead’s payments for CVO3 and CVO4 as evidence that the first defendant should be paid for VO2 presupposes that VO2 falls within CVO3 and CVO4. This is however, disputed. The first defendant must also prove that the conditions precedent for a valid variation under the Comfort Contract are satisfied.
- [103]
[103] Similarly, the Court of Appeal’s decision in Comfort v OGSP (CA) is of no assistance to the first defendant. The question there was the interpretation of s 17(3) of the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) and the grounds on which the AD could be set aside. In upholding the adjudicator’s award, the Court of Appeal merely upheld the interim finality of the adjudicator’s award. The finding does not touch in any way on the ultimate merits of the underlying claim.
The writing requirement
- [104]
[104] The appropriate starting point is cl 11 of Appendix A of the Lead Contract, as amended by cl 5 of Appendix B of the contract. This provision sets out a detailed contractual mechanism for the approval and valuation of variations:
- [105]
[105] Clause 11.1 requires some form of writing as a condition precedent for the first defendant’s right to claim payment for a variation. Further, cl 11.3 allows the plaintiff to require the first defendant to submit a written quotation for any proposed variation within a specified period of time before confirming in writing its instructions to carry out the variation. For example, as stated at [89] above, the first defendant followed this procedure for VO1 by submitting a quotation which the plaintiff accepted.
The evidence
- [106]
[106] The first defendant bases its claim for VO2 on three sets of documents exhibited to Mr Ram’s affidavit of evidence in chief which it says brings its claim within cl 11.1 of the Lead Contract. The first document is a spreadsheet detailing the nature, description, location and quantity of the alleged variations which it submitted to the plaintiff attached to the 1 October 2014 Email. In that email, Mr Ram informed the second defendant that attached were the “variation work details. This is not the final list, we are still working on the balance”. This spreadsheet was also included as part of the first defendant’s written submissions for the AD in June 2016. Second, the first defendant relies on documents which it describes as handwritten sketches or drawings prepared by the first defendant’s site supervisors (“Drawings A”). Finally, the first defendant relies on handwritten drawings that it alleges were prepared by the second defendant (“Drawings B”).
My findings
- [108]
[108] I accept the plaintiff’s submission. On its very face, the spreadsheet in Mr Ram’s affidavit of evidence in chief, which is attached to the first defendant’s 1 October 2014 Email, cannot be a written instruction from the plaintiff within the meaning of cl 11.1 of the Lead Contract. This does not require any further analysis.
- [109]
[109] I also find that neither Drawings A nor Drawings B are a written instruction from the plaintiff within the meaning of cl 11.1.
- [110]
[110] First, Drawings A were not prepared by the second defendant. As Mr Ram testified, these drawings were prepared by the first defendant’s site supervisors. They plainly cannot constitute a written instruction from the plaintiff as cl 11.1 requires. I also note that, given the importance placed on these drawings by the first defendant, it is curious that Drawings A supposedly in support of VO2 were not part of the bundle of documents submitted by the first defendant as part of PC 12 submitted on 16 March 2017. Drawings A are in fact as-built drawings that have been marked up by the first defendant after the plaintiff disclosed them in this action on 3 October 2017. The markings on the drawings were made by Mr Ram along with his site supervisors and were initially done in red on pieces of paper before being transcribed onto the as-built drawings. Yet, none of these sketches, red markings or the documents that the first defendant’s on-site supervisors allegedly had on site to mark-up were disclosed in this action.
- [111]
[111] Second, in respect of Drawings B, it is not even clear in the first place that the second defendant prepared these drawings. There is even doubt as to the significance of Drawings B. Indeed, in his cross-examination, the second defendant disavowed them. He testified instead that the drawings were prepared by the first defendant’s on-site supervisors and stated unequivocally that the handwriting on the drawings was not his:
- [113]
[113] I also observe that the first defendant could have called its site supervisors to give evidence at trial to testify that it was the second defendant who prepared these drawings and that they considered these drawings to be written instructions from the plaintiff to carry out VO2. However, the first defendant chose not to do so and offered no explanation for failing to do so.
- [115]
[115] That Drawings B are unlikely to be evidence of a written instruction from the plaintiff to the first defendant is also bolstered by Ms Lew’s testimony that it was unclear whether these drawings relate to the Works or to VO2. The sketches were of a short piece of ductwork and it was difficult to identify where it belonged.
- [116]
[116] Moreover, Mr Ram also candidly testified that VO2 was not supported by documentation similar to that which supported VO1 even though it was within the power of the first defendant to issue a quotation for the VO2 works:
- [117]
[117] I therefore accept the plaintiff’s submission that none of the three categories of documents relied upon by the first defendant is a written instruction within the meaning of cl 11.1 of the Comfort Contract.
Waiver
- [118]
[118] This is however not the end of the matter. In Comfort v OGSP (CA), the Court of Appeal cited Law and Practice of Construction Contracts with approval and highlighted that there may be situations where non-compliance with the express terms of a contract might not bar a claim (at [89]):
- [119]
[119] In the absence of a written instruction for VO2, the first defendant bears the risk of not being able to recover under it (Comfort v OGSP (CA) at [90]). In this respect, the first defendant argues that the plaintiff by its actions waived the condition precedent of a written instruction for a variation because the parties invariably carried out, certified and paid for variations without written instructions. The usual sequence of events was that Lead would orally instruct the plaintiff to carry out a variation. The plaintiff, through the second defendant, would then orally instruct the first defendant to carry out the variation. After carrying out the variation, the first defendant would mark the variation on the drawings and the second defendant would verify the variation with Lead. Evaluation and certification would follow.
- [120]
[120] The Court of Appeal in Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317 made clear that a waiver by election requires a party to a contract making a clear and unequivocal choice between two inconsistent rights (at [54]):
(b) Additional Ducting Works: These works were carried out pursuant to a Field Instruction (“FI”) issued by Lead to the plaintiff dated 29 October 2014. However, the plaintiff issued a quotation for the works to Lead only on 17 March 2015, almost five months after the FI.
(c) Additional Fire Rated Board and Plenum Boxes: These works were carried out pursuant to an FI dated 21 November 2014. However, the plaintiff issued a quotation for the works to Lead only on 17 March 2015, almost five months after the FI.
(d) CVO4: Part of these works, amounting in value to $43,702.83, were carried out pursuant to FIs issued by representatives of Lead between 8 October 2014 and 15 January 2015 and were completed before quotations were issued on 17 March 2015 to regularise them.
- [122]
[122] Further, in cross-examination by the first defendant, the second defendant was referred to the plaintiff’s email dated 13 September 2014 to Lead seeking approval for “all additional works” as “we had carry [sic] out additional works and most of the additional works already completed”. The second defendant agreed that this meant that, although Lead had not yet given formal approval, the first defendant had carried out the variation works. In other words, this was a case in which the first defendant carried out variation works before its quotation was approved.
- [125]
[125] At trial, the second defendant was adamant that he did not give any oral instructions to the first defendant to carry out variation works and that he did not consider himself to have any authority to instruct the first defendant to carry out variation works.
- [126]
[126] I do not accept that the plaintiff waived the condition precedent of an instruction in writing before its liability to pay the first defendant for a variation under cl 11.1 is engaged. While there is some evidence of a high degree of informality in how the parties dealt with variations in performing both parties’ obligations under the Comfort Contract, there is no evidence that in respect of VO2 specifically, the plaintiff waived the condition precedent of a written instruction, much less in clear and unequivocal terms. That finding is sufficient to dispose of the first defendant’s contractual claim on VO2.
Quantum meruit
- [127]
[127] My rejection of the first defendant’s contractual claim for VO2 does not leave the first defendant without recourse. As the learned author of Law and Practice of Construction Contracts states at para 5.019:
The first defendant thus alternatively relies on a quantum meruit claim for an award of a reasonable sum for VO2.
- [128]
[128] In Eng Chiet Shoong and others v Cheong Soh Chin and others and another appeal [2016] 4 SLR 728, the Court of Appeal summarised the alternative approaches towards the award of a reasonable sum for work done by a claimant (at [41]):
- [129]
[129] Although the first defendant did not expound upon the basis for its quantum meruit claim, it is apparent that it cannot be premised on a contractual ground. This is because the express terms of the Comfort Contract (by incorporating the Lead Contract’s terms) stipulate writing as a condition precedent for the first defendant’s right to claim payment for a variation. It is not therefore possible to imply a term into the Comfort Contract entitling the first defendant to reasonable remuneration for variation work carried out without satisfying the condition precedent. That would run contrary to the express terms of the Comfort Contract and would not satisfy the traditional “business efficacy” and “officious bystander” tests (see Sembcorp Marine Ltd v PPL Holdings Pte Ltd and another and another appeal [2013] 4 SLR 193). The first defendant’s claim can thus only be premised on a restitutionary ground.
- [130]
[130] I accept that the first defendant did carry out at least part of VO2 before it withdrew from the site on 9 October 2014. The benefit of those works on and from 9 October 2014 accrued to the plaintiff, as it has been paid by Lead for those works. I have found that the first defendant is not contractually entitled to recover payment for VO2, either under the express terms of cl 11.1 or by reason of the plaintiff’s waiver of the condition precedent for recovery under that clause. I am therefore satisfied that the conditions for the first defendant to recover a quantum meruit have been made out. It then falls to me to decide the value of the first defendant’s work under VO2.
Value of works
- [131]
[131] I proceed to consider the scope and value of VO2 and how much of these variations the first defendant completed. Unfortunately, because both parties presented all-or-nothing cases, the evidence on this is not entirely satisfactory.
- [132]
[132] The first defendant argues that VO2 was completed sometime in September 2014 and that it is entitled to be paid the full $621,828.73. Its position is that CVO3 and CVO4 certified by Lead in fact reflect and contain the VO2 works. This was confirmed by Mr Ram at trial:
- [133]
[133] The plaintiff argues that the first defendant has failed to adduce sufficient evidence to show that the value of VO2 was in fact $621,828.73. The plaintiff points to the inconsistent positions taken by the first defendant on VO2, as well as the fact that the works alleged by Mr Ram in his affidavit of evidence in chief as falling within the scope of VO2 are not consistent with the list of works under CVO3 and CVO4. Additionally, some of the works contained in CVO4 include works done pursuant to FIs that were issued only after the first defendant had withdrawn on 9 October 2014 and several quotations were issued for these works after 9 October 2014.
- [134]
[134] There are several difficulties with the first defendant’s assertion that CVO3 and CVO4 which Lead issued to the plaintiff actually represent the VO2 works carried out by the first defendant. This is in addition to the fact that as a matter of law, CVO3 and CVO4 relate to a separate contract, ie the Lead Contract. They thus do not automatically prove that the first defendant is entitled to recover for a variation under the Comfort Contract. I elaborate.
- [135]
[135] First, the total amount paid by Lead to the plaintiff on CVO3 and CVO4 amounts to $560,000. I need not consider further the $100,000 paid under CVO1 and CVO2 as there is no suggestion that VO2 relates to CVO1. In any case, the second defendant adduced clear evidence that parts of CVO1 and CVO2 were in fact carried out by other subcontractors and not by the first defendant.
- [136]
[136] It is also undisputed that CVO3 comprises the works that the first defendant carried out for the plaintiff pursuant to VO1, for which the plaintiff agreed to pay the first defendant $130,000.
- [137]
[137] In the AD, the first defendant quantified its claim on VO1 and VO2 at $737,528.73, as stated in PC 12. The first defendant now claims the sum of $621,828.73 on VO2 alone. It is clear that, even excluding VO1, the first defendant’s claim for VO2 exceeds Lead’s payments to the plaintiff under CVO3 and CVO4 ie, $560,000. This discrepancy is even starker when VO1 is included. The first defendant’s argument that including the lump sum discounts of $86,606.41 brings the claimed amount closer to $560,000 under CVO3 and CVO3 still fails to take into account the payments for VO1.
- [139]
[139] Second, the list of works cited by Mr Ram in support of the first defendant’s claim on VO2, as stated in para 14 of his affidavit of evidence in chief does not correspond clearly with the valuation particulars for CVO3 and CVO4. In cross-examination, Mr Ram’s evidence was that only paras 14.1, 14.2 and parts of 14.4 and 14.5 related to VO1. By a process of elimination, paras 14.3, parts of paras 14.4 and 14.5 and paras 14.6 to 14.28 would fall within CVO3 and CVO4.
- [140]
[140] While items number 1 to 19 in the valuation particulars for CVO4 are reflected in paras 14.6 to 14.23 of Mr Ram’s affidavit of evidence in chief, the remainder of the valuation particulars are unaccounted for. Moreover, the spreadsheet that Mr Ram along with his site supervisors prepared that lists all the alleged VO2 works does not correspond to the works listed in his own affidavit of evidence in chief.
- [141]
[141] For example, para 14.3 of Mr Ram’s affidavit of evidence in chief stating “Additional installation of secondary Condensate Water Trays for Air Handling Units for ACMV and CBK, Levels 1, 2 & 3” was not wholly reflected in the spreadsheet. Additionally, a plain reading of the items contained in paras 14.17, 14.19, 14.20 and 14.24 refers to works done at the bus interchange. This is contrary to Mr Ram’s own evidence that VO2 related only to the Commercial Block. I note that this was not challenged by the first defendant in its reply closing submissions.
- [142]
[142] Third, I do not think that Drawings B are of much assistance to the first defendant’s case. As stated at [111]–[114] above, there is doubt as to whether the second defendant was even the author of these drawings. Some of the sketches are illegible. Only a few of them give locations or refer to contract drawings or subcontract drawings.
- [143]
[143] I also accept Mr McGeoch’s observations that some of the drawings refer to areas that are not part of the VO2 claim in the first place ie, the Commercial Block.
- [144]
[144] Fourth, in the valuation particulars of CVO4 issued by Lead comprising 29 items, the cross-referenced quotations for items 1 to 19 reveal that Lead gave FIs for works to be carried out on 8 October 2014 by a letter to the plaintiff of the same date. This is only a day before the first defendant withdrew from the site on 9 October 2014. It is therefore highly unlikely that these variation works were carried out or even completed by the first defendant by 9 October 2014.
The judgment continues past this page. Read the rest at eLitigation.