para
Introduction
[2021] SGHC(I) 17
Singapore International Commercial Court24 Dec 2021Originating Summons No 10 of 2021
Published judgment text with court metadata, source links, and stable paragraph anchors.
What the court ordered
Citations and treatment detected automatically from later judgments and the authorities this decision relies on.
Later cases and laws citing this decision
Not yet cited by a later decision.
Earlier cases and laws this decision relies on
“former chief justices of the Bombay High Court, and the third appointed by the two appointed arbitrators. The provisions of the Arbitration and Conciliation Act 1996 (Act No 26 of 1996) (India) (“the AC Act”) were to apply, and the arbitration proceedings were to take place in Mumbai.”
“disputes were not arbitrable because the rights and liabilities in contention arose out of a breach of the FEMA and the regulations thereunder, as well as a breach of s 67 of the Companies Act 2013 (Act No 18 of 2013) (India) (“the CA”), and also because the FEMA and the CA were codes with their own tribunals for deali”
“g retired High Court justices or former chief justices of the Bombay High Court, and the third appointed by the two appointed arbitrators. The provisions of the Arbitration and Conciliation Act 1996 (Act No 26 of 1996) (India) (“the AC Act”) were to apply, and the arbitration proceedings were to take place in Mumbai.”
“(a) that the SPAs and the First Letter Agreement were void under Indian law because their object was unlawful, being a violation of the Foreign Exchange Management Act 1999 (Act No 42 of 1999) (India) (“the FEMA”) and the regulations thereunder; and”
“(a) the disputes were not arbitrable because the rights and liabilities in contention arose out of a breach of the FEMA and the regulations thereunder, as well as a breach of s 67 of the Companies Act 2013 (Act No 18 of 2013) (India) (“the CA”), and also because the FEMA and the CA were codes with their own tribunals f”
“he Promoters, both being retired High Court justices or former chief justices of the Bombay High Court, and the third appointed by the two appointed arbitrators. The provisions of the Arbitration and Conciliation Act 1996 (Act No 26 of 1996) (India) (“the AC Act”) were to apply, and the arbitration proceedings were to”
“(a) that the SPAs and the First Letter Agreement were void under Indian law because their object was unlawful, being a violation of the Foreign Exchange Management Act 1999 (Act No 42 of 1999) (India) (“the FEMA”) and the regulations thereunder; and”
“beyond the scope of the submission to arbitration, within the meaning of Article 34(2)(a)(iii) of the UNCITRAL Model Law on International Commercial Arbitration (“the Model Law”) read with s 3 of the International Arbitration Act (Cap 143A, 2002 Rev Ed) (“the IAA”);”
Auto-detected from judgment text; not a substitute for a citator check.
para
Introduction
1
The plaintiffs applied to set aside, in whole or in part, the final award made on 7 January 2021 (“the Award”) in consolidated arbitrations conducted under the rules of the Singapore International Arbitration Centre (“SIAC”). In the Originating Summons, they applied on the grounds:
para
(a) that the Award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or contains decisions on matters beyond the scope of the submission to arbitration, within the meaning of Article 34(2)(a)(iii) of the UNCITRAL Model Law on International Commercial Arbitration (“the Model Law”) read with s 3 of the International Arbitration Act (Cap 143A, 2002 Rev Ed) (“the IAA”);
para
(b) that the composition of the arbitral tribunal and/or the arbitral procedure was not in accordance with the agreement of the parties, within the meaning of Article 34(2)(a)(iv) of the Model Law read with s 3 of the IAA;
para
(c) that they were not given proper notice of the arbitral proceedings and/or were otherwise unable to present their case, within the meaning of Article 34(2)(a)(ii) of the Model Law read with s 3 of the IAA;
para
(d) that there was a breach of the rules of natural justice in connection with the making of the Award by which their rights were prejudiced, within the meaning of s 24(b) of the IAA; and
para
(e) that the Award is in conflict with the public policy of Singapore, within the meaning of Article 34(2)(b)(ii) of the Model Law read with s 3 of the IAA.
para
Background
para
Events leading to the arbitration
2
The plaintiffs are companies registered in India. The first plaintiff (“Twarit”) provides management consultancy and technical management services in India and abroad. The second plaintiff (“SEPC”) is a publicly listed company providing multi-disciplinary engineering, procurement and construction services in a number of infrastructure sectors for governmental and private clients in India and abroad.
3
The first and second defendants (“GPE India” and “GPE JV1” respectively) are companies incorporated in Mauritius; the third defendant (“Gaja”) is a company incorporated in India. Each of the defendants conducts a private equity investment business.
4
In 2010–2011 the defendants subscribed to shares in Haldia Coke and Chemicals Private Ltd (“Haldia”), a company in the business of manufacturing, processing, trading, supplying and distributing coke (carbon) coal. GPE India and GPE JV1 subscribed by way of one of two Share Subscription and Shareholders Agreements dated 31 May 2010, as amended by amending agreements dated 1 July 2010, 2 July 2010 and 15 November 2011 (“the SSHAs”); Gaja subscribed by way of the other of the SSHAs. In total, between them, the defendants subscribed for (in Indian numeration) 10,84,36,850 Compulsory Convertible Preference Shares and 1,65,61,950 Optional Convertible Preference Shares, for the subscription amount of INR125,00,00,000.
5
SEPC was a party to both SSHAs as a Promoter. Twarit was not a party to either of them. There were a number of other parties, as Promoters and otherwise; it was not suggested in the submissions in the Originating Summons that they should have been joined in the arbitrations or in the Originating Summons.
6
Under the SSHAs the Promoters undertook to procure a “Listing Event” by 31 March 2014, being either an initial public offering (“IPO”) of the shares of Haldia or a merger of Haldia with its listed subsidiary Ennore Coke Limited (“Ennore”). If the Listing Event did not occur by 31 March 2014, there was provision for an “Exit Mechanism”, being an entitlement in the defendants under cl 15.2 of the SSHAs to exercise one or a combination of a number of rights. In summary, the rights were requiring an IPO (cl 15.2.1); sale of the shares (cl 15.2.2); buy back (cl 15.2.3); a put option (cl 15.2.4); a call option (cl 15.2.5); what was called securing an economic interest in certain mines (cl 15.2.6); and requiring a merger with Ennore (cl 15.2 7).
7
The rights included reference to a guaranteed return, which I will call “the 24% IRR”, which assumed significance in the arbitrations. In its final form, the first paragraph of cl 15.2.3 dealing with buy back read:
8
A Listing Event was not procured by 31 March 2014. But none of the exit mechanism rights was exercised; instead, on 28 September 2015, a series of agreements were entered into.
9
First, three Share Purchase Agreements (“the SPAs”), in materially identical terms, were entered into. The parties to each SPA were one of the defendants (one for each SPA), the plaintiffs, and some others. In each, it was agreed that the plaintiffs would purchase the majority of the shares in Haldia held by the relevant defendant, for a total price in the three SPAs of INR200,00,00,000. The plaintiffs were to purchase the shares in 14 tranches on various dates from 30 September 2015 to 30 June 2018.
10
Secondly, a so-called letter agreement (“the First Letter Agreement”) was entered into between the plaintiffs, the defendants and other parties, providing for the suspension of the exit mechanisms and setting out consequences of breach of the plaintiffs’ obligations under the SPAs. The relevant provisions were:
11
As later described, in the arbitrations, the defendants sued on the SPAs and the First Letter Agreement. Again, it was not suggested in the submissions in the Originating Summons that the other parties to these agreements should have been joined in the arbitrations or in the Originating Summons.
12
Thirdly, two further agreements were entered into. One was a Share Purchase Agreement (“the SVL SPA”) between the defendants and SVL Limited (“SVL”), a shareholder in SEPC, pursuant to which the defendants agreed to purchase certain shares in SEPC from SVL and Gaja could be required to purchase or subscribe to shares in SEPC. The other was a letter agreement (“the Second Letter Agreement”), entered into between the defendants amongst others and SVL, pursuant to which GPE India and GPE JV1 were to purchase shares in SEPC from SVL following completion of events under the SPAs.
13
The plaintiffs paid for and acquired shares in respect of the first tranche under the SPAs, a total payment of INR5,00,00,000. They paid nothing thereafter.
14
On 11 July 2017, Haldia was admitted into a voluntary corporate insolvency resolution process under Indian law. This brought a moratorium (“the moratorium”), as to which see later in these reasons (at [87] below).
Costs
On 14 December 2017, the defendants commenced the SIAC arbitral proceedings by filing a Notice of Arbitration in respect of the three SPAs and the First Letter Agreement. In the Notice of Arbitration, the defendants alleged that the plaintiffs had evinced an intention not to perform their contractual obligations under the SPAs and the First Letter Agreement, and sought damages to be assessed, interest, compensation and legal costs. Under the SIAC rules, four arbitrations were deemed to have been commenced, with the Notice of Arbitration also serving as an application to consolidate all four arbitrations.
para
The arbitration clauses
16
There were dispute resolution clauses in all of the SSHAs, the SPAs and the First Letter Agreement.
17
Each of the SSHAs included an arbitration clause providing for referral of disputes to three arbitrators: one appointed by the relevant defendant and one appointed by the Promoters, both being retired High Court justices or former chief justices of the Bombay High Court, and the third appointed by the two appointed arbitrators. The provisions of the Arbitration and Conciliation Act 1996 (Act No 26 of 1996) (India) (“the AC Act”) were to apply, and the arbitration proceedings were to take place in Mumbai.
18
The subject-matter of the arbitration clauses was expressed:
19
Each of the SPAs included an arbitration clause providing for referral of disputes to arbitration in accordance with the SIAC rules, the seat of the arbitration being Singapore.
20
The subject-matter of the arbitration clauses was expressed:
21
The First Letter Agreement included an arbitration clause in materially the same terms as that in the SPAs, including in its description of the subject-matter.
22
Under each of the SSHAs, the SPAs and the First Letter Agreement, it was to be governed by and construed in accordance with the laws of India.
para
The arbitral proceedings
para
Procedural history
23
I have referred to the Notice of Arbitration (see above at [15]). On 30 December 2017, the plaintiffs filed a document titled Common Preliminary Objections as their response to the Notice of Arbitration. Amongst a host of other matters, there were contentions which reappeared in various guises in a formal challenge to jurisdiction and under or in connection with grounds (a) and/or (b) in the Originating Summons. They were to the effect:
para
(a) that the SPAs and the First Letter Agreement were void under Indian law because their object was unlawful, being a violation of the Foreign Exchange Management Act 1999 (Act No 42 of 1999) (India) (“the FEMA”) and the regulations thereunder; and
para
(b) that the arbitrations were improperly commenced because, in the event of breach of the SPAs or the First Letter Agreement, the defendants’ rights reverted to the exit mechanisms in cl 15.2 of the SSHAs, and accordingly the agreements in respect of which there were disputes were the SSHAs.
24
After correspondence with SIAC, in which the plaintiffs confirmed that they were raising a jurisdictional objection, and further submissions by both sides, on 26 March 2018 the Registrar of the Court of Arbitration of SIAC determined that the Common Preliminary Objections would not be referred to the Court of Arbitration and that the arbitrations would proceed.
25
The plaintiffs protested and there was further correspondence, but to no avail. The four arbitrations were consolidated. In the absence of agreement on the appointment of an arbitrator, on 16 July 2018 SIAC appointed the sole arbitrator, a Singapore lawyer (“the Tribunal”).
26
On 10 August 2018 the first procedural meeting was held, and on 16 August 2018 Procedural Order No 1 (“PO 1”) was issued by the Tribunal.
27
PO 1 included procedural directions dealing with the plaintiffs’ jurisdictional challenge. In accordance with PO 1, on 6 September 2018 the plaintiffs filed a challenge to the Tribunal’s jurisdiction. It included similar contentions to those described above in the Common Preliminary Objections, to the effect (in a summary of a document of some obscurity):
para
(a) the disputes were not arbitrable because the rights and liabilities in contention arose out of a breach of the FEMA and the regulations thereunder, as well as a breach of s 67 of the Companies Act 2013 (Act No 18 of 2013) (India) (“the CA”), and also because the FEMA and the CA were codes with their own tribunals for dealing with breaches;
para
(b) the SPAs and the First Letter Agreement were illegal, and so the arbitration agreements in them were illegal, void and unenforceable, because:
para
(i) the SSHAs were contrary to the provisions of the FEMA and the regulations thereunder and the SPAs and the First Letter Agreement were “derived from Clause 15.2 of the SSHAs”; and
para
(ii) the Second Letter Agreement and the SVL SPA contravened s 67 of the CA and the SPAs and the First Letter Agreement were part of the same commercial transaction; and
para
(c) the parties’ dispute was outside the scope of the arbitration agreements in the SPAs and the First Letter Agreement, because it was a dispute “in relation to the SSHA”.
28
Extensive submissions were filed, and a hearing was held. On 14 February 2019, the Tribunal issued a detailed decision dismissing the jurisdictional challenge. The Tribunal held, in short, that:
para
(a) arbitrability was determined under Singapore law, and that the disputes were arbitrable under that law (and were also arbitrable under Indian law);
para
(b) there was no illegality under FEMA or for contravention of s 67 of the CA; and
para
(c) the disputes were within the arbitration agreements in the SPAs and the First Letter Agreement because the claim was made under them.
29
The plaintiffs did not seek to appeal or apply to the Singapore High Court, pursuant to s 10 of the IAA and/or Article 16(3) of the Model Law, to set aside the Tribunal’s decision on jurisdiction.
30
A procession of pleadings followed:
para
(a) the defendants filed a Statement of Claim on 28 March 2019;
para
(b) the plaintiffs filed a Statement of Defence on 9 May 2019;
para
(c) the defendants filed a Reply on 6 June 2019; and
para
(d) the plaintiffs filed a Rejoinder on 4 July 2019.
para
The parties submitted their respective lists of issues on 18 July 2019. The defendants requested the production of documents, and production was completed by early October 2019. The plaintiffs did not request the production of documents. On 13 November 2019, the Tribunal issued Procedural Order No 2 (“PO 2”), and pursuant to the timetable therein, as subsequently amended, witness statements were submitted. The evidentiary hearing was fixed for 2–5 March 2020.
31
On 4 February 2020, the plaintiffs applied for an adjournment of the evidentiary hearing. The application was opposed, and was dismissed on 6 February 2020; after more correspondence, the dismissal was confirmed on 10 February 2020. On 25 February 2020, the plaintiffs applied to exclude the evidence of the defendants’ Indian law expert. The Tribunal received written submissions, and on 29 February 2020 dismissed the application. The Tribunal’s dismissal of the plaintiffs’ adjournment application and application to exclude the defendants’ expert evidence are the factual basis of grounds (c) and (d) in the Originating Summons.
32
The evidentiary hearing took place over 2–4 March 2020. Written closing submissions were provided, and there was a hearing for oral closing submissions on 8 May 2020. Additional submissions on interest were thereafter provided at the Tribunal’s request.
Costs
As noted above (at [1]), the Award was issued on 7 January 2021. The Award obliged the plaintiffs to pay to the defendants INR195,00,00,000 plus simple interest at 7.25% per annum from 21 July 2017 to the date of payment, and gave the defendants party-and-party costs and the costs of the arbitration.
para
The claim and the defence
34
I do not go into or comment on the merits of the contentions in the claim and the defence thereto. The merits were and are a matter for the Tribunal. But some understanding of the pleadings is necessary for a consideration of the grounds in the Originating Summons.
35
The Statement of Claim began with an “Introduction”, which described the claim as a dispute arising out of the three SPAs by which the plaintiffs agreed to purchase the Haldia shares and the First Letter Agreement which “provide[d] the consequences of default on the part of the [plaintiffs] in making payments to [the defendants] as per the terms of all the three SPAs”. It was said that the plaintiffs were obliged to purchase the shares in 14 tranches for an aggregate consideration of INR200,00,00,000 but had only paid for the first tranche of INR5,00,00,000, and that “[t]he [plaintiffs] ha[d] evinced an intention not to perform their obligations under the SPAs and the First Letter Agreement on erroneous and untenable grounds resulting, inter alia, in loss/ damage to the [defendants]”.
36
There was then set out a “Statement of Facts Supporting the Claim”, which included references to the exit mechanisms in cl 15.2 of the SPAs, the 24% IRR and reinstatement of rights under the SSHAs pursuant to cl 3 of the First Letter Agreement. It was alleged that “on breach by the [plaintiffs] to make payments under the SPAs”, the defendants were entitled to exercise their rights under cl 15.2 of the SSHAs to receive payment from the plaintiffs in accordance with the formulae in cl 3 of the First Letter Agreement, and to “any other contractual remedies available under Indian law, including… damages…”. After an account of the plaintiffs’ failure to pay, the Statement of Facts concluded with the assertions that the plaintiffs had “evinced an intention not to perform their obligations under the SPAs and [First] Letter Agreement”, and that the defendants had commenced the arbitration proceedings “in view of the [plaintiffs’] repudiatory breaches of the SPAs”.
37
The next section of the Statement of Claim, under the heading “Legal Grounds or Arguments Supporting the Claim”, was largely a refutation of the plaintiffs’ assertion of illegality, but concluding with a further assertion of breach of the SPAs.
38
Then came a section headed “The Relief Claimed”. The relief was described in the alternative. First, it was said that the plaintiffs were liable to pay the defendants in accordance with the formula in cl 3(c) of the First Letter Agreement, as explained being INR401,00,00,000 calculated as the 24% IRR less the amount paid under the SPAs. Secondly, it was said:
39
The final expression of the claims was, as the first alternative, “[d]amages amounting to INR 401,00,00,000… as per clause 3(c) of the [First] Letter Agreement…” and, as the second alternative, “damages amounting to INR 195,00,00,000… or such sum as to be assessed by the Tribunal”.
40
Less detail is required of the Statement of Defence. In summary, it was contended that the “entire scheme of the transaction”, reading all the documents executed on 28 September 2015 together, was unlawful and the SPAs were therefore void and unenforceable. The unlawfulness was because of infringement of the FEMA and of s 67 of the CA. The reliance on cl 3 of the First Letter Agreement for an entitlement to damages was untenable because it incorporated by reference provisions in the unlawful cl 15.2 of the SPAs. As well, by reason of a circular issued by the Reserve Bank of India, the buy back in cl 15.2 of the SSHAs was not permitted and the SSHAs were void for that reason. As to the claims for damages, the defendants had not suffered a loss because the market value of the shares exceeded the sale consideration under the SPAs. As to the damages of INR195,00,00,000, the defendants were in truth seeking specific performance rather than damages, without pleading or proving the necessary ingredients, and the grant of the relief would result in unjust enrichment to the defendants as they would have the shares in addition to the money. Finally, the defendants had failed to mitigate their loss.
41
It should be said that in the Rejoinder, it was added that the SPAs and the First Letter Agreement were voidable because they were executed under coercion.
para
The Award
42
I will refer to the Award in more detail when and as necessary in considering the grounds in the Originating Summons. In summary, and so far as relevant in this application, the Tribunal held as follows:
para
(a) Noting that the plaintiffs’ argument had evolved over the course of the arbitral proceedings, the Tribunal did not accept their contention that the SPAs, or the SSHAs, were void or unenforceable. The Tribunal held that cl 15.2 did not contravene the FEMA regime and that the SPAs were “demonstrably capable of being performed” consistently with that regime, and that s 67 of the CA was not contravened because the object of the agreements was not to further an illegal purpose of providing financial assistance.
para
(b) The Tribunal dismissed the claim for INR401,00,00,000. The Tribunal held that cl 3(c) of the First Letter Agreement obliged the plaintiffs to pay to the defendants the 24% IRR, but that it was a penalty; the defendants were entitled to reasonable compensation, but they had “not put forward a position on the quantum of reasonable consideration” but had fallen back on their alternative damages claim.
para
(c) The Tribunal held that the defendants were entitled on that alternative claim to INR195,00,00,000 as damages for breach of the SPAs, calculated as the outstanding consideration payable thereunder.
43
The award of damages for breach of the SPAs is raised as another complaint under ground (d) in the Originating Summons.
para
Requests for adjournments of the Originating Summons
44
The plaintiffs were granted one adjournment of the hearing of the Originating Summons, but were refused a further adjournment. I explain the circumstances, and the reasons for the refusal.
45
The Originating Summons was filed in the General Division of the High Court on 6 April 2021. On 22 July 2021, the proceedings were transferred to the Singapore International Commercial Court. At a Case Management Conference on 25 August 2021, by which date the affidavit evidence of both sides had been filed, directions were given for sequential written submissions and the hearing was fixed for 27 October 2021.
46
The plaintiffs’ submissions and the defendants’ responsive submissions, both of which were detailed, were filed. The plaintiffs’ submissions in reply were due on 22 October 2021. On 15 October 2021, the plaintiffs’ solicitors applied pursuant to Order 64 rule 5(1) of the Rules of Court (2014 Rev Ed) (“ROC”) for an order declaring that they had ceased to be the solicitor acting for the plaintiffs. The basis of the application was that, as further described below, the plaintiffs had not paid outstanding invoices and had not provided the requested deposit for fees and disbursements for the hearing. While ordinarily confidential between the solicitors and their clients, these matters became open for consideration in connection with the plaintiffs’ acknowledged financial stringency when applying for an adjournment.
47
On 19 October 2021, an order was made as requested by the plaintiffs’ solicitors (hereafter, “the former solicitors”). The Registry emailed the plaintiffs directing that they inform the Registry whether they would be appointing new solicitors for the hearing on 27 October 2021. The response, on 20 October 2021, was a written request to extend the time for the submissions in reply and to reschedule the hearing “by at least 6–8 weeks” so that the plaintiffs could make alternative arrangements for representation. The email described why the plaintiffs’ “projects and revenue streams [had been] prejudicially and grossly affected” such that they “could not honour some of the fees payments” to the former solicitors.
48
The defendants emailed the Registry on 21 October 2021, objecting to the plaintiffs’ request. The parties were informed that the hearing date of 27 October 2021 would remain, and that if the plaintiffs were not represented by solicitors, their representative would be heard on any application for an adjournment. Arrangements enabling appearance by an appointed representative were made modelled on O 1 r 9(2) of the ROC. From the decision of the Court of Appeal in Offshoreworks Global (L) Ltd v POSH Semco Pte Ltd [2021] 1 SLR 27 at [22] and [34], the plaintiffs as foreign corporations could not appear otherwise than by solicitors, but this expedient was adopted so that the plaintiffs could be heard on their request for an adjournment.
49
The plaintiffs took up the arrangements. They replied to the defendants’ email by an email on 25 October 2021. All emails were before me on 27 October 2021 when the plaintiffs each appeared by their representative.
50
It is necessary to say a little more of the failure to pay the former solicitors. The default began in late July 2021, when the plaintiffs short-paid a May invoice by a little more than S$3,600 with a promise of payment in the next invoice. The early August invoice for a little under S$7,000 was not paid, nor was the earlier outstanding amount. A September invoice for a little under S$43,000 as deposit for further work and the hearing was not paid. There were a number of promises of payment, none adhered to, until on 13 October 2021 the former solicitors advised that they would be applying to discharge themselves. From as early as mid-August 2021, and repeated thereafter, the former solicitors had told their clients that if payment was not made by the promised time, they might suspend work and apply to discharge themselves.
51
By 27 October 2021, the plaintiffs had not explored alternative representation; the representatives said that they had hoped that the former solicitors would come back on board. When asked about funding, they said at one point that the plaintiffs would find the money, and that in the six weeks they would either get the former solicitors back on board or have alternative representation. Having heard both sides, over the defendants’ objection, I extended the time for the reply submissions to 22 November 2021 and adjourned the hearing to 26 November 2021. It was emphasised to the plaintiffs’ representatives that this was a last chance to find the money to re-engage the former solicitors or engage other solicitors, and that if this was not done it could appear that there was no point in further adjournment.
52
The reply submissions were not filed. On 25 November 2021, the day before the appointed hearing, the plaintiffs’ present solicitors filed a notice of their appointment on behalf of the plaintiffs. By email to the Registry, they advised that they would be applying for an adjournment of the hearing to “a date in mid-January 2022” and an extension of the time for filing the submissions in reply to seven days prior to that date.
53
Also on 25 November 2021, the defendants emailed objecting to any such application. Both emails included submissions, and they also were before me on 26 November 2021, when Mr Joshua Chow appeared as counsel for the plaintiffs and Mr Prakash Pillai appeared as lead counsel for the defendants. Mr Chow made his application, and after hearing the parties I refused the plaintiffs’ application for a further adjournment of the hearing.
54
Having been instructed the previous day, Mr Chow said that he was not in a position to satisfactorily argue the plaintiffs’ case. He submitted that substantive justice required that the plaintiffs have adequate representation, and that adjournment until mid-January 2022 would still leave disposal of the proceedings within “case management tolerances”. He referred to his email of 25 November 2021 in which it was said that, on his clients’ instructions, the plaintiffs had not been dilatory, and between 8 and 25 November had approached five Singaporean law firms, the first four of which had declined engagement “with the reasons given for refusal including the short timelines and potential conflict(s) of interest”. In anticipation of the defendants’ submissions, which had been foreshadowed in their email of 25 November 2021, he said that it was open to the defendants to take action to enforce the Award while the challenge to it in the Originating Summons was pending, and that the adjournment application in the arbitral proceedings was quite insufficient for a contention of repeated delay on the plaintiffs’ part.
55
Mr Pillai submitted that the defendants would be prejudiced by further delay in the hearing of the Originating Summons, which “creates a cloud over” enforcement of the Award and, depending on the jurisdiction of enforcement, could restrict doing so. He submitted that the late engagement of the new solicitors and the further application for an adjournment were part of a pattern of conduct where the plaintiffs had repeatedly sought to delay, and that if the adjournment were granted there was no real likelihood that the position would not be the same in mid-January 2022.
56
Mr Chow’s submissions included that the new solicitors “do not expect our client to default on [fees]”. He said, in answer to my enquiry, that the firm had not yet been put in funds. In my view, that was a key matter in relation to adjournment, giving weight to Mr Pillai’s submission last mentioned.
57
The amount outstanding to the former solicitors was not large, less than S$54,000, in comparison with the amount at stake being an award of INR195,00,00,000 (which is approximately S$35m) plus interest. Money was not found, despite promises, over a number of months prior to 27 October 2021. Effectively nothing was done to have representation from 13 October 2021, when the plaintiffs could not have been in doubt that they would lose the former solicitors, to 27 October 2021 – the asserted hope that the former solicitors would come back on board being shown to be hollow and not credible when even on 26 November 2021 no money was at hand.
58
Even if an uplift be added for the new solicitors, a similarly relatively small amount had not been provided. That the plaintiffs had not put the new solicitors in funds, particularly when under the pressure of the hearing date of 26 November 2021 and the warning of a last chance on 27 October 2021, indicated that they were unwilling, but even if willing unable, to do so. Further, from the instructions as noted in the new solicitors’ letter of 25 November 2021, the plaintiffs had done nothing to approach Singaporean law firms in the period from 27 October 2021 to 8 November 2021; the letter refers to the Diwali public holiday in India in the week of 1 November 2021, but that was not a reason, in the circumstances, to fail to act in Singapore where (as Mr Pillai pointed out) the Diwali holiday occupied but a day.
59
I accepted Mr Pillai’s submission of deliberate delay, but alternatively considered that no reason had been shown why the prolonged inability to raise the relatively small amount involved, if genuine, would not continue. For one or the other reason, I was not satisfied that there was point in an adjournment because I was not satisfied that there would be representation by the new solicitors, or other legal representation, for the hearing in mid-January 2022.
60
While the plaintiffs submitted that in justice they should have adequate representation in pursuing their challenge to the Award, the defendants were entitled to have the challenge brought on for due hearing. I accepted that the pendency of the Originating Summons in practice impeded them from enforcing the Award, and they should not have to abide by the plaintiffs’ willingness or ability to fund their representation. Balancing the matters put to me, I considered that the plaintiffs had sufficient accommodation by the adjournment from 27 October 2021, and that a case for further adjournment had not been made out.
61
After I refused the application, Mr Chow asked for and was given a short adjournment in order to take instructions. Upon resumption, as his submissions on the plaintiffs’ behalves he adopted the written submissions earlier filed by the former solicitors. Mr Pillai then made his oral submissions speaking to the defendants’ written submissions earlier filed.
62
Mr Chow asked that a day to be appointed at which he could make oral submissions on behalf of the plaintiffs. This I refused, as it would amount to a de facto adjournment when an adjournment had been refused. However, I gave leave to the plaintiffs to file within two weeks a written submission, being a submission in reply to the defendants’ written submissions earlier filed and to Mr Pillai’s oral submissions, with a page limit.
63
The written submission was provided on 10 December 2021 (“the reply submissions”). It exceeded the page limit (but see below at [64]). Mr Pillai had expressed concern that the submissions would “raise something new”, and that concern was realised in that a great deal of the reply submissions was a re-statement and in some respects expansion of the plaintiffs’ arguments in the earlier written submissions plus, egregiously, an entirely new public policy argument resurrecting ground (e) in the Originating Summons, which had been expressly abandoned in those earlier submissions. On 15 December 2021, the defendants wrote to the Registry noting the page excess and objecting to the public policy argument.
64
There was some confusion over the page limit: it was 20 pages, but the transcript erroneously recorded 30 pages (which the reply submissions were within), and in the circumstances I overlook the page excess. As to the submissions not being in reply, rather than exclude them entirely, or permit more delay requiring amended submissions, I accepted their filing. I did not think that the re-statement of the arguments in the earlier written submissions required a response from the defendants, but I do not permit the resurrection of ground (e) as that would be contrary to the refusal of the adjournment.
para
Ground (a): Article 34(2)(a)(iii) – Exceeding the Scope of Submission to Arbitration
para
Preliminary matters
65
The plaintiffs made two submissions under this ground, accompanied by a third submission on arbitrability not correctly within it. I will deal with the submissions in turn, in the order in the written submissions; but first, some discussion of Article 34(2)(a)(iii) of the Model Law.
66
The Article relevantly provides:
67
The question is whether the tribunal has determined a dispute not submitted to it, or an issue within a dispute which issue was not submitted to it. In keeping with the consensual basis of an arbitration, as the tribunal has no authority to determine a dispute or an issue not submitted to it, such a determination will not be binding on the parties, and it may be set aside.
68
The dispute or issue submitted to arbitration can be distinguished from the subject-matter of the arbitration agreement itself. As the Court of Appeal said in PT Prima International Development v Kempinski Hotels SA and other appeals [2012] 4 SLR 98 (“PT Prima”) at [32]:
69
As described below, the plaintiffs’ submissions on jurisdiction (in which I do not include their submission on arbitrability) were not concerned with what disputes, or what issues within a dispute, had been submitted to arbitration. They challenged the applicability of the agreement to submit disputes to arbitration, contending that the defendants’ claims in the arbitrations were within the ambit of the arbitration agreements in the SSHAs rather than those in the SPAs and the First Letter Agreement. The defendants submitted that this jurisdictional challenge was not one which could be mounted under Article 34(2)(a)(iii) of the Model Law, because the ground was concerned only with the scope of the submission to arbitration.
70
That is not correct, and PT Prima does not have that effect. In Swissbourgh Diamond Mines (Pty) Ltd and others v Kingdom of Lesotho [2019] 1 SLR 263, the Kingdom sought to set aside an award made in an investor-state arbitration pursuant to Article 34(2)(a)(iii) on the ground that preconditions to a submission to arbitration had not been satisfied, so that the tribunal had no jurisdiction at all in respect of the dispute (at [55] and [59]). Swissbourgh submitted that the court had no jurisdiction to set the award aside, because the ground was confined to decision of matters not submitted to the tribunal (at [57] and [66]). It was held that the phrase “submission to arbitration” in Article 34(2)(a)(iii) of the Model Law was not limited to the submission in the particular arbitral proceeding, and extended to where the tribunal did not have jurisdiction over the dispute under the arbitration agreement. After a detailed consideration, the Court said (at [79]):
71
The defendants’ submission in this respect, therefore, cannot be accepted. Noting that the plaintiffs’ jurisdictional challenge was dismissed by the Tribunal but not taken on appeal or application pursuant to s 10 of the IAA and/or Article 16(3) of the Model Law, there may be a different question whether the plaintiffs are precluded from taking up the challenge in a setting-aside application: see Rakna Arakshaka Lanka Ltd v Avant Garde Maritime Services (Pte) Ltd [2019] 2 SLR 131 at [75] and PT First Media TBK (formerly known as PT Broadband Multimedia TBK) v Astro Nusantara International BV and others and another appeal [2014] 1 SLR 372 especially at [132]. However, the defendants did not so submit, and accordingly I say no more of the matter.
para
First submission: the defendants’ claims were not within the arbitration clauses in the SPAs or First Letter Agreement
72
The plaintiffs submitted that the dispute was “within the ambit of” the SSHAs, as opposed to the SPAs and the First Letter Agreement. Their submission was not clearly expressed, but the plaintiffs meant that the governing arbitration clauses were therefore those in the SSHAs, providing for a three-member tribunal, which includes two retired judges, and for arbitration in Mumbai under the AC Act (see above at [17]), and not those in the SPAs and the First Letter Agreement providing for the SIAC arbitrations (see above at [19]–[21]). As such, the Tribunal had no authority to determine the dispute.
73
The plaintiffs’ argument can be summarised as follows.
para
(a) The SSHAs provided for the exit mechanisms in the event that a Listing Event did not occur, including the 24% IRR. The exit mechanisms were not exercised; instead, the parties entered into the SPAs and other agreements on 28 September 2015.
para
(b) But the First Letter Agreement provided that the rights of the defendants under the SSHAs were only suspended, and would revive if the plaintiffs failed to pay under the SPAs. The defendants’ claims were based on that failure to pay and, via cl 3(c) of the First Letter Agreement, were primarily for the 24% IRR amount payable under the SSHAs.
para
(c) Because the claim was based upon the revival of the SSHA rights and the relief claimed flowed “substantively” from the SSHAs, the arbitration clauses in the SSHAs should apply, not the arbitration clauses in the SPAs and the First Letter Agreement.
74
I will call this “the Revival Argument”. It was submitted that “a holistic reading” of the collection of agreements should be adopted, indeed that Indian law required that they be read as a single agreement, and that any other result “would be to collapse the agreements unto one another, and defy the clearly distinct arbitration agreements agreed to between the parties in respect of the SSHAs and the SPAs”. It was said that the result was supported by the facts that the defendants’ claims in the arbitrations included the claim to the 24% IRR amount and that the defendants “continue to hold on to the shares which were the subject of the SPAs”, and that there were (otherwise) no sums payable under the SSHAs at the time.
75
The argument cannot be accepted. To begin with, it ignores that Twarit is a party to and promisor under the SPAs and the First Letter Agreement, but not a party to the SSHAs, and it ignores that there was a clear claim to relief in the alternative to the 24% IRR amount (see above at [39]). Even as to the 24% IRR amount, the defendants were not claiming in the exercise of a revived right found in the SSHAs: although cl 3(a) of the First Letter Agreement allowed them to exercise the rights under the SSHAs, they did not do so, but claimed the separately conferred entitlement under cl 3(c) of the First Letter Agreement for which the 24% IRR was part of the calculation (see above at [38]). More fundamentally, the essence of the argument is that the dispute falls within the arbitration clauses in the SSHAs; it does not, for the above reasons, but that answers the wrong question. The claim was for damages for breach of the SPAs triggering the cl 3(c) entitlement or entitlement to damages on the alternative basis. The question is whether there is a “Dispute” within that term in the arbitration clauses in the SPAs and the First Letter Agreement. There plainly is, as a disputed claim (rightly or wrongly made) between the defendants and the plaintiffs as parties thereto (including Twarit), a claim for damages for breach of and so in connection with or arising out of those agreements.
para
Second submission: the defendants’ claims were not arbitrable
76
The plaintiffs submitted in the written submissions that “the underlying transaction” under the SPAs and the First Letter Agreement was illegal and/or void under Indian law, because it violated the FEMA and the regulations thereunder and also violated s 67 of the CA. This, they submitted, rendered the dispute non-arbitrable because it falls within the class of “disputes which are of a public character and disputes whose outcome will affect the interests of persons beyond the immediate disputants”, citing BTY v BUA and other matters [2019] 3 SLR 786 (“BTY”) and Tomolugen Holdings Ltd and another v Silica Investors Ltd and other appeals [2016] 1 SLR 373 (“Tomolugen”). It was in that class, they said, because the legality or otherwise of the transaction would have an impact not only on the other parties to the SSHAs and the SPAs, in particular Haldia, but also on “the regulators and other stakeholders with an interest in [Haldia’s] insolvency proceedings”.
77
There is an initial difficulty. That a dispute is not arbitrable is a different ground for setting aside an award from those in the Originating Summons. Article 34(2)(b)(i) of the Model Law provides:
78
In their written submissions, the plaintiffs listed the “relevant prescribed grounds for setting aside an award” on which they relied, being the grounds in the Originating Summons except ground (e). They did not apply to or purport to extend the grounds, leaving Article 34(2)(a)(iii) as the only possible candidate; but it is not the vehicle for the submission. The defendants took the point, and even in the reply submissions the plaintiffs did not seek to apply to rely on the further ground or otherwise respond to the point.
79
The defendants nonetheless addressed the submission, and I will do the same. There is no merit in it.
80
In Tomolugen, the Court of Appeal said (at [71]):
81
The court noted (at [75]) that the concept of arbitrability finds legislative expression in s 11 of the IAA. It provides that any dispute which the parties have agreed to submit to arbitration under an arbitration agreement may be determined by arbitration unless it is contrary to public policy to do so, and the Court continued:
82
It is important to remember that the public policy here in play is not the public policy in play under Article 34(2)(b)(ii) of the Model Law. It is the public policy concerning whether a dispute can be arbitrated, not the public policy concerning whether an award should be set aside, which is a different matter.
83
Examples of non-arbitrability given by the court in Tomolugen at [77]–[78] included a claim under the bankruptcy avoidance provisions (referring to Larsen Oil and Gas Pte Ltd v Petroprod Ltd (in official liquidation in the Cayman Islands and in compulsory liquidation in Singapore) [2011] 3 SLR 414 (“Larsen Oil”), a case which will feature more in the analysis below), and a claim to have an insolvent company wound up; but it was held at [88] and [97] that a claim of minority oppression was arbitrable even though the tribunal could not grant some of the relief which might be sought.
84
The discussion of arbitrability in BTY was obiter. The Judge postulated, but did not decide, that a claim to have accounts lodged with the Accounting and Regulatory Authority (“ACRA”) expunged from ACRA’s records was not arbitrable, because the outcome could affect a public register and therefore could affect third parties who may have acted in reliance on the accuracy of the register (at [158]–[160]). That is remote from the present case. In the sentence on which the plaintiffs relied, the Judge paraphrased Tomolugen as saying that at the core of the class of disputes not capable of settlement by arbitration “are disputes which are of a public character and disputes whose outcome will affect the interests of persons beyond the immediate disputants”. That is apposite on the facts of BTY. However, it remains necessary to consider whether in the particular case the presumption of arbitrability has been rebutted.
85
More instructive in relation to the present case, in which the plaintiffs invoked Haldia’s insolvency proceedings, is the Judge’s consideration (at [150]–[153]) of Larsen Oil. A company’s liquidators claimed to avoid payments made under a management agreement. The refusal of a stay in favour of arbitration under an arbitration clause in the management agreement was upheld by the Court of Appeal, on the ground that the claim was not arbitrable amongst other reasons. His Honour pointed to the distinction drawn in Larsen Oil between a dispute arising only upon insolvency and by reason only of the insolvency regime, and a dispute arising from the insolvent company’s pre-insolvency rights and obligations. The former was held to be not arbitrable; the latter was considered to be arbitrable, at least where the substantive rights of the creditors were not affected. Bearing these in mind, simply referring to Haldia’s insolvency proceedings will not do. The dispute must be examined to see whether it arises from or its determination is subject to the insolvency regime.
86
The plaintiffs’ written submissions did not expand upon the bald assertion that the legality or otherwise of the transaction had an impact on the regulators and other stakeholders with an interest in Haldia’s insolvency proceedings; they did, however, expressly abandon the contention that Indian law provides for a particular dispute resolution mechanism to cover the defendants’ claims in the arbitrations. The reply submissions added the equally bald assertion that the outcome of the dispute would have “an impact of a public nature considering that [SEPC] is a public limited company”. That SEPC is a public company in no way makes a dispute to which it is a party non-arbitrable, and if that was seriously meant it was an absurd proposition.
87
I doubt that the written submissions included that Haldia’s insolvency proceedings meant that, as a process, the dispute was not arbitrable. The plaintiffs’ assertion was of an impact on various entities, not on process, and it abandoned any assertion that a particular (other) dispute resolution mechanism was necessary. However, the moratorium was referred to in the defendants’ submissions, and the reply submissions ventured into process by relying on it. The moratorium was declared on 11 July 2017, as part of the insolvency proceedings, by the National Company Law Tribunal at Chennai. The plaintiffs submitted that the Tribunal erred in dealing with the dispute despite the Chennai tribunal’s direction, which the plaintiffs stated as the direction that “no Court or arbitration proceedings could be commenced in respect of, or involving, Haldia (including any share transfers)”.
88
For a number of reasons, the submission is misconceived. First, that was not the direction given, and it is difficult to see how the submission could have been made. The moratorium prevented the commencement or continuation of proceedings against Haldia, dealing with its assets, enforcement of security given by it and recovery of property in its possession. It did not impede the commencement or continuation of the arbitrations, to which Haldia was not a party, nor was it submitted to the Tribunal in the non-arbitrability part of the jurisdictional challenge that it did. Secondly, even if the direction had been as stated by the plaintiffs, I do not see why that would have rendered the dispute non-arbitrable. The question in rebutting the presumption of arbitrability is whether the dispute is of a kind that must be resolved by a process other than arbitration. That question is not answered by an embargo on any process of resolution at all; the embargo may mean that the arbitrations were irregularly commenced or continued, but that is a different matter. Thirdly, the order admitting Haldia into the insolvency proceedings and the moratorium were set aside by the Appellate Tribunal on 19 July 2018 – as was pointed out in the defendants’ written submissions and referred to in a separate segment of the plaintiffs’ reply submissions.
89
The reply submissions asserted another matter, a moratorium imposed in 2018 in insolvency proceedings concerning SEPC with the same prevention of the commencement or continuation of proceedings against SEPC. This was a new matter to which the defendants have not had the opportunity to respond, and it should not be permitted. In any event, as stated above, I do not see why that would have rendered the dispute non-arbitrable.
90
Returning to Tomolugen at [76] and the assertion of an impact on various entities, the dispute did not arise from Haldia’s rights and obligations at all, whether pre-insolvency process or post-insolvency process. It was not a party to the arbitrations and no relief was sought against it. The submission had to be to the effect that the dispute was not arbitrable because it required a decision of whether the transaction was legal or illegal, and permitting that decision to be made by the Tribunal would offend public policy because of the impact on the other parties, on Haldia, and on the unidentified regulators and other stakeholders.
91
The plaintiffs’ written submissions included argument for the contention that the “underlying transaction” was illegal and/or void because of violation of the FEMA and the regulations thereunder and of s 67 of the CA. The Tribunal has held otherwise in response to illegality arguments, once in dismissing the jurisdictional challenge and definitively in the Award. I do not think that the merits of the contention arises in my considering arbitrability, because the question is whether the dispute, relevantly that part of it in which the illegality or otherwise of the transaction is in issue, can be resolved by arbitration, and that question is not answered by deciding the issue by saying whether there is or is not illegality. In any event, while I see no reason to disagree with the Tribunal’s rejection of the contention, there is no substance in the submission that the dispute is not arbitrable because it requires a decision on illegality.
92
To repeat, Haldia is not a party to the arbitrations and not bound by a decision on illegality. Nor are any of the other parties to the various agreements apart from the plaintiffs and the defendants. There may or may not be an economic effect on them of the outcome in the arbitrations, or of the decision on illegality, but that does not make the dispute non-arbitrable. Disputes over the illegality of a transaction are not uncommon in arbitral proceedings, and there is no reason why they cannot be decided by an arbitrator instead of a judge. The regulators or other stakeholders, whatever that may mean, are no more or less affected by an arbitrator’s decision than by a judge’s decision.
93
The presumption of arbitrability is not rebutted. The second submission fails.
para
Third submission: the Tribunal’s decision was outside the submission to arbitration
94
The plaintiffs’ submission was in the terms that the hearing of the defendants’ claims in the arbitrations constituted a decision beyond the scope of the submission to arbitration. The hearing of the claims was not a decision, and Article 34(2)(a)(iii) of the Model Law speaks of the award and of the decisions contained in it. The submission must be understood as a submission that the Award, or the decision of the dispute in the arbitrations contained in the Award, was beyond the scope of the submission to arbitration.
95
The argument in support of the submission was by incorporation of the Revival Argument put forward in support of the first submission. It was said that the only practical or sensible way to understand the defendants’ claim was as a claim “for a breach of the SSHAs, or at least arising out of the SSHAs”, and that “it is the arbitration agreements in the SSHAs that governs [sic] the dispute, not that in the SPAs and the Letter Agreements”.
96
It is sufficient to repeat the rejection of the Revival Argument.
para
Ground (b): Article 34(2)(a)(iv) – composition of the Tribunal and arbitral procedure not as agreed
97
The Article relevantly provides:
98
The plaintiffs’ complaint was as to the composition of the Tribunal. It was the sole SIAC arbitrator, not the panel of three arbitrators, two of whom are to be retired judges, required by the arbitration clauses in the SSHAs. The plaintiffs submitted that because the arbitrations should have been pursuant to the arbitration agreements in the arbitration clauses in the SSHAs, the arbitral tribunal was improperly constituted. Again, the argument in support of the submission was by incorporation of the Revival Argument, with the contention that the defendants should have commenced the arbitrations pursuant to the arbitration agreements contained in the SSHAs.
99
It is sufficient again to repeat the rejection of the Revival Argument.
para
Grounds (c) and(d): Article 34(2)(a)(ii) and s 24(b) – lack of proper notice, inability to present case and breach of the rules of natural justice
para
Preliminary matters
100
These grounds are conveniently dealt with together. The plaintiffs relied on two matters for both ground (c) and ground (d), being the refusal of an adjournment of the evidentiary hearing and the refusal to exclude the evidence of the defendants’ Indian law expert (see at [31] above), and on a third matter for ground (d) alone, being the Tribunal’s award of a total of INR195,00,00,000 as damages (see at [33] above).
101
Article 34(2)(a)(ii) of the Model Law relevantly provides:
102
Section 24(b) of the IAA relevantly provides:
103
The plaintiffs’ complaint in relation to the first two matters was as to their inability to present their case and, as the breach of the rules of natural justice, a denial of their right to be heard. The denial of the right to be heard was also the complaint in relation to the third matter.
104
The inability to present one’s case and a denial of one’s right to be heard are closely related. In the full discussion by the Court of Appeal in China Machine New Energy Corp v Jaguar Energy Guatemala LLC and another [2020] 1 SLR 695 (“China Machine”) at [88]–[89], it is said that the expression of the right to be heard in Article 18 of the Model Law, providing that each party “shall be given a full opportunity of presenting his case”, finds teeth in Article 34(2)(a)(ii) of the Model Law and s 24(b) of the IAA, and the requirements of Article 18 are described at [90] as embodying basic notions of fairness and fair process. The court’s summary of the applicable principles, at [104], is:
105
More generally as to setting aside an arbitral award for breach of natural justice under s 24(b) of the IAA, the party must establish (a) which rule of natural justice was breached; (b) how it was breached; (c) in what way the breach was connected to the making of the award; and (d) how the breach could or did prejudice the party’s rights: Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd [2007] 3 SLR(R) 86 (“Soh Beng Tee”) at [29]; China Machine at [86]. In China Machine at [87], citing Soh Beng Tee, it is said succinctly that the authorities make clear “that the threshold for a finding of breach of natural justice is a high one, and that it is only in exceptional cases that a court will find that threshold crossed”.
para
First matter: refusal of an adjournment of the evidentiary hearing
106
The plaintiffs said that on 31 January and 1 February 2020, they informed the Tribunal that they were in the process of engaging alternative external counsel, and indicated that they would seek consequential modifications to the procedural timetable once they had done so. Late on 4 February 2020, they said, their newly appointed counsel Mr Vishnu Mohan informed the Tribunal that they were “still in the midst of” engaging Senior Counsel, and requested that the evidentiary hearing (then fixed for 2–5 March 2020) be adjourned to 11–15 May 2020, because there was less than a month for the yet to be appointed Senior Counsel to “get up on the case” and prepare for the hearing. As earlier explained, the request was denied. The plaintiffs submitted that the right to be heard included the right to choose their representation, citing CGS v CGT [2021] 3 SLR 672 at [12], and that the refusal of the adjournment impeded their ability to present their case and their right to be heard.
107
More should be said of the circumstances of the refusal of the adjournment.
108
The plaintiffs had initially been represented by in-house lawyer(s). By August 2018, external lawyers were on record as their counsel. PO 1 had been issued on 10 August 2018, the hearing dates had been fixed by October 2019, and all evidentiary materials had been submitted by 7 January 2020. In the adjournment application on 4 February 2020, it was said that the then counsel had “withdrawn”, and that the new lawyers had not yet received the papers. The defendants objected, saying that the pleadings were not voluminous and detailed submissions had already been provided, and that so far as the plaintiffs said that Senior Counsel was to be engaged, they had had adequate time to engage Senior Counsel earlier on.
109
The Tribunal emailed on 6 February 2020, dismissing the request for an adjournment. The Tribunal referred to the fixing of the hearing dates long ago, and said that so far as the plaintiffs wished to appoint Senior Counsel, they had had adequate time to do so. He noted that the plaintiffs’ “previous legal team did not include a Senior Counsel”. He said that the plaintiffs had “provided few details on the circumstances of the withdrawal of their previous counsel, including the reasons for the same and the date they became aware of their counsel’s intention to withdraw”. He continued:
110
Mr Mohan wrote again on 8 February 2020, repeating the request and canvassing the reasons given by the Tribunal. The defendants responded. On 10 February 2020 the Tribunal confirmed the dismissal of the request, having considered the additional matters put to him and saying that he was satisfied that the plaintiffs’ counsel had sufficient time to prepare, for the reasons set out in his earlier emails.
111
Returning to the plaintiffs’ complaint in the present case, it was said that the Tribunal’s conduct was not what a reasonable and fair-minded arbitrator might have done, and that the plaintiffs’ ability to present their case and their right to be heard had been prejudiced. The prejudice was simply asserted, on the basis that the newly appointed counsel had less than a month to get up on the case and prepare for the hearing.
112
I do not accept the plaintiffs’ complaint. In fact, the plaintiffs had a team of counsel at the hearing, including Mr Mohan. Their counsel filed opening submissions, conducted the hearing including cross-examination, filed closing submissions, and requested and participated in a hearing of oral closing submissions. No protest was made that counsel was prejudiced by dismissal of the application to adjourn the evidentiary hearing. The refusal of the adjournment was well within the Tribunal’s discretion and consistent with fair conduct of the arbitral proceedings, and in the circumstances neither an unfair or unreasonable impediment to the presentation of the plaintiffs’ case nor a prejudicial denial of the right to be heard. The Tribunal was in a position to assess the adequacy of the time available to incoming counsel, and other than by assertion no reason has been shown for the assessment being wrong or unreasonable or resulting in prejudice – on the contrary, counsel appear to have been able fully to fulfil their role.
113
It may be noted that in the reply submissions, responding to the defendants’ submission that there was no more than a bare allegation of prejudice because the newly appointed counsel had less than a month to get up on the case and prepare for the hearing, the plaintiffs simply again asserted that they were “in fact unable to present its [sic] case properly”, without any attempt to support that equally bare allegation.
para
Second matter: refusal to exclude the evidence of the Indian Law expert
114
The plaintiffs submitted that there was an agreed and contemplated procedure for the parties to present legal arguments by way of submissions, but that the defendants tendered as evidence the expert report of Mr Vikram Nankani on Indian law. This, they said, caught them by surprise, and led to their application to exclude the report. In their written submissions, they were pleased to describe it as an ambush on them. The Tribunal refused the application, and their counsel thereafter cross-examined Mr Nankani. In the plaintiffs’ submission, the refusal also impeded their ability to present their case and their right to be heard.
115
As with the first matter, some more should be said of these circumstances. In particular, the plaintiffs’ claim that there was the “agreed and contemplated procedure” cannot be accepted.
116
PO 1, issued on 16 August 2018, included that “[t]he Parties may offer the testimony of expert witnesses, which shall be subject to the directions set out above for fact witnesses, mutatis mutandis”. Mr Nankani’s report was filed on 6 December 2019. On 8 January 2020, the plaintiffs’ lawyers sent a brief email to the Tribunal, saying that the plaintiffs “do not wish to submit a responsive witness statement in the above captioned arbitration proceedings”. On 15 February 2020, as part of an email in anticipation of a pre-hearing conference on 25 February 2020, they wrote:
117
On 25 February 2020, however, the plaintiffs requested that the Tribunal “may kindly consider not receiving the statement of Mr Nankani in evidence as it, in its entirety, does not relate to a question of fact but instead pertains to the legal issues which are to be adjudicated by the Arbitral Tribunal”. The reason given was:
118
It will be noted that the reason given was not that the report of Mr Nankani had been provided contrary to an “agreed and contemplated procedure”. On the contrary, PO 1 clearly contemplated that there could be expert evidence by witness statement, in context being or including expert evidence of Indian law, and there was no protest of departure from an agreed and contemplated procedure when Mr Nankani’s report was filed, when video conferencing was raised, or as a reason in support of the request to decline to receive it in evidence.
Costs
Written submissions were exchanged in accordance with the Tribunal’s directions, and on 29 February 2020 the Tribunal dismissed the request to exclude Mr Nankani’s report. From the Tribunal’s reasons, the plaintiffs’ submissions had now included a procedural complaint. In the reasons, the Tribunal summarised the plaintiffs’ “objections” as that PO 1 did not contemplate the admission of expert evidence on questions of law; that the expert evidence mechanism was not suited to dealing with questions of law; that the Tribunal should not delegate the determination of Indian law or the application of Indian law to an expert witness; and that consideration of costs and time warranted the exclusion of Mr Nankani’s report. At this point still, it was not said by the plaintiffs that receiving the report would be contrary to the positive of an agreed and contemplated procedure: the complaint was the negative, ie, that its receipt was not contemplated.
Costs
The Tribunal said that PO 1 did not preclude the submission of expert evidence on questions of Indian law, referring to the paragraph stating that the parties may offer the testimony of expert witnesses. For reasons he gave, he said he was not persuaded that he could conclude that there was no utility in receiving Mr Nankani’s evidence or hearing cross-examination on the same. He said that Mr Nankani’s appearance at the hearing did not mean that his evidence would be accepted without question and that the plaintiffs, if they so desired, would be given a fair opportunity to confront Mr Nankani in cross-examination and make submissions on his evidence as well as put their own position on Indian law: there would not be a delegation of the application of Indian law to the facts to Mr Nankani. As to costs and time, he was not satisfied that Mr Nankani’s evidence would be of limited utility, and costs were not the only concern: the Tribunal had an obligation to ensure a fair, expeditious, economical and final resolution of the dispute, and in that regard the plaintiffs had not previously objected to Mr Nankani’s evidence and it would be unfair to the defendants to exclude it on an application made less than one week before the hearing. The fairest way forward was to allow Mr Nankani to appear at the hearing and for the parties to submit on the relevance, materiality and admissibility of his evidence in closing submissions.
121
As earlier noted, the plaintiffs did cross-examine Mr Nankani. They were represented throughout the arbitrations by a team of counsel qualified in Indian law. The Tribunal made clear that he expected full submissions on Indian law from the plaintiffs’ counsel, and extensive submissions on Indian law were made. At no time was there complaint that the plaintiffs or their counsel were prejudiced through themselves not adducing expert evidence on Indian law.
122
It was well open to the Tribunal to rule as he did, carefully and explaining his reasons. It could not be said that his ruling was outside what a reasonable and fair-minded tribunal might have done, nor does it appear that there was any prejudice to the plaintiffs in the conduct of their case. In the reply submissions, responding to the defendants’ description of the second matter as an afterthought, it is said that the plaintiffs were denied the opportunity to adequately address and/or respond to the points on Indian law raised at the evidential hearing, but again this is only an assertion without any attempt to support it. I do not accept the plaintiffs’ complaint in the second matter either.
para
Third matter: the award of damages
123
I have described above at [33] the Tribunal’s award of INR195,00,00,000 as damages. The plaintiffs submitted that the award was made in breach of the rules of natural justice, specifically in breach of their right to be heard, because the defendants had not submitted in the arbitrations that they should be awarded damages for breach of the SPAs and it “ignored the fact that this resulted in a windfall to [the defendants]”.
124
The submission was presented by the plaintiffs as a complaint that the Tribunal had gone beyond the defendants’ case as presented in the arbitration, not that the Tribunal had gone beyond the defendants’ case as pleaded. The case as pleaded, however, cannot be ignored in considering the complaint. While it could not be called a model pleading, in the Statement of Claim the defendants clearly claimed damages for breach of the SPAs and the First Letter Agreement, with the alternative claim to relief a clear claim to damages of INR195,00,00,000 as an amount equivalent to the amount due under the outstanding thirteen tranches in the SPAs. A demonstration that this was not maintained in the defendants’ conduct of the arbitrations was necessary.
125
No such demonstration was attempted by the plaintiffs. They alleged that “it was the Arbitrator who unilaterally reframed the claim as arising from a breach of the SPAs in the Award”, without giving them the opportunity to present their arguments on the issue, and that they were thereby prejudiced because had the Tribunal heard arguments from them, he could reasonably have arrived at a different result. But no reference was made by the plaintiffs to the transcript of the hearing, to the written opening or closing submissions, to the Award, or to anything else to support the allegation. While the plaintiffs’ argument rested on a negative (that the defendants had not submitted that they should be awarded damages for breach of the SPAs), the beginning of establishing the negative was what the defendants had submitted during the arbitral proceedings.
126
In fact, the defendants did maintain the pleaded alternative claim, and the plaintiffs had full opportunity to respond to it.
para
(a) The defendants’ written opening submissions were largely directed to the claim calculated as the 24% IRR less the amount paid under the SPAs, but included a proleptic answer to a contention by the plaintiffs that, for reasons stated, the defendants were not entitled to damages calculated as the unpaid consideration amount less the value of the shares. The submission was made that even if the damages were computed in that manner “which is denied”, the defendants’ claim was “fully sustainable and ought to be granted”. In context, the “which is denied” was an expression that the primary claim was to damages calculated as the 24% IRR less the amount paid under the SPAs.
para
(b) The plaintiffs’ written opening submissions explicitly recognised that the defendants “seek damages of INR195,00,00,000/- being an amount equivalent to the sums due under the SPAs, or such amount to be determined by the Tribunal”.
para
(c) The defendants’ written closing submissions included:
para
(d) The plaintiffs’ written closing submissions, which were filed contemporaneously with the defendants’ written closing submissions, included the contention that the only damages claimable for breach of a contract for sale or purchase of shares was an amount being the difference between the price of the shares and the market price on the date of breach – apparently, as an answer to the claim to damages calculated as the 24% IRR amount less the amount paid under the SPAs – and made submissions against damages so arrived at.
para
(e) The defendants’ written reply submissions took the contention as such an answer, and responded to it.
127
In the Award, the Tribunal’s summary of the defendants’ arguments on the alternative claim to damages included taking up the language of para 62 set out at [126(c)] above as the basis of the claim. It is not correct that the Tribunal unilaterally re-framed the claim without the plaintiffs having the opportunity to present their arguments. The Tribunal considered and determined the claim as presented to him. Whether or not he was correct in his determination is not a matter for debate in the Originating Summons. The complaint of denial of natural justice cannot be accepted.
128
I record that the plaintiffs referred to authorities for denial of natural justice if the tribunal decides the case on a point that he invents for himself, or fails to consider an important issue in the case. Nothing of that kind has been shown, and it is not necessary to go into the authorities. I record also that at one point in the written submissions concerning the award of damages the plaintiffs also said that the Tribunal “[impeded] the Applicants’ ability to present its case”. For the reasons above, he did not.
129
The relevance to denial of natural justice of the assertion that there was a windfall to the defendants is not clear, and was not explained. If there was a windfall, that would go to the merits of the Tribunal’s calculation of the damages as the amount outstanding under the SPAs; the plaintiffs’ submissions before the Tribunal raised the point, and the merits are not for debate in the Originating Summons. As the defendants pointed out, their case for the damages in the arbitrations included that the shares were of no value.
para
Ground (e): Article 34(2)(b)(ii) – conflict with the public policy of Singapore
130
No submissions were made in support of this ground in the plaintiffs’ written submissions. It was not in the listing in those submissions of the “relevant prescribed grounds for setting aside an award” on which the plaintiffs relied, and it was said expressly in those submissions that the plaintiffs “will no longer be pursuing their case on breach of public policy (pursuant to Article 34(2)(b)(ii))”. The ground was abandoned. As earlier noted, in the reply submissions it was resurrected, but I do not permit the resurrection.
para
Conclusion
Costs
The Originating Summons is dismissed. The plaintiffs should pay the defendants’ costs, but with liberty to the parties to apply if they wish to contend for an additional or different order. The parties should file and exchange written submissions on the amount of costs, limited to five pages, within 21 days; any application pursuant to the liberty to apply is to be included in the written submissions, with an additional page limit of five pages. Unless a party requests an opportunity for oral submissions, costs will be determined on the papers.
Wrong text, a broken link, out-of-date content, or a removal request — tell us and we'll check it against the official source.