(1)
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Published on 30 June 2026
The full official text, structured for quick navigation. Copy any provision or jump straight to a section.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore is Singapore COMMENTARY, cited as COMMENTARY 2026-07-06-sal-prac-drafting-lessons-from-recent-consortium-and-joint-venture-construction-arbitrations-in-singapore 2026, and first recorded in 2026.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Published on 30 June 2026
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Drafting Lessons from Recent Consortium and Joint Venture Construction Arbitrations in Singapore
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
[2026] SAL Prac 19
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
This article discusses the recent decisions of the court and highlights the issues and lessons relating to construction contracts that involve consortiums and/or joint ventures. The lack of clear and unambiguous drafting may lead to real, and sometimes surprising, consequences in arbitration or arbitration related proceedings, and this article seeks to highlight the key takeaways and practical drafting lessons from DRO v DRP [2026] 3 SLR 1012 and DQR v DQT [2026] SGHC 23.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Kirindeep Singh
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
LLB (Hons) (University of Leeds), BCL (University of Oxford);Senior Accredited Specialist (Building and Construction), Singapore Academy of Law; Senior Partner, Dentons Rodyk & Davidson LLP.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
TOO Fang Yi
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
LLB (Hons) (National University of Singapore);Partner, Dentons Rodyk & Davidson LLP.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
I. Introduction
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
1 This article analyses the recent decisions of Singapore’s General Division of the High Court (“General Division”), DRO v DRP1 (“DRO v DRP”) and DQR v DQT2 (“DQR v DQT”). Both decisions concerned construction contracts involving unincorporated joint ventures/consortiums. They yielded two key lessons on drafting:
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Where a consortium is not a separate legal person, the contract must state with clarity:
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
whether the consortium acts as a single contractual counterparty;
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
which member(s) may invoke the arbitration agreement; and
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
where a member is so entitled and commences arbitration, whether that member may retain any resulting proceeds, or whether such proceeds are to be held on account for the consortium or joint venture.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Absent precision, parties risk outcomes that may be commercially unexpected, such as a single consortium/joint venture member commencing arbitral proceedings without the consortium/joint venture leader or other member(s).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Parties should clearly articulate their intentions in relation to pre-conditions to arbitration. In particular, parties need to clearly state whether compliance with the preconditions is intended to operate as a condition precedent to the tribunal’s jurisdiction or is merely a matter that goes to the issue of admissibility. A failure to specify will likely lead to the matter being treated as one of admissibility. This would impact the options for jurisdictional challenges and curial intervention.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
2 This article summarises the facts, issues and holdings in DRO v DRP. It then considers the decision in DQR v DQT and compares Singapore’s approach with three Indian decisions addressing similar questions as to who may invoke an arbitration agreement on behalf of an unincorporated consortium. Finally, the article canvases the recent developments in Singapore law concerning the jurisdiction–admissibility dichotomy in respect of preconditions to arbitration.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
II. DRO v DRP
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
3 In DRO v DRP, the respondent (ie, the claimant in the arbitration) commenced arbitration against the applicant (ie, the respondent in the arbitration). The applicant raised a jurisdictional challenge in the arbitration, which was dismissed. The applicant then applied to the General Division for: (a) a declaration that the tribunal lacked jurisdiction; and (b) in the alternative, an order setting aside the tribunal’s jurisdictional ruling.3
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
4 The applicant entered into a contract (“Contract”) with an unincorporated consortium (“Consortium”) comprising Co A (the Consortium leader) and the respondent for the delivery of a project. The Consortium was not a separate legal entity.4
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
5 Following issues arising in the project, the applicant asserted, inter alia, a claim for liquidated damages under the Contract. The applicant and Co A subsequently entered into a settlement agreement (“Settlement Agreement”) which stated that the applicant and Co A agreed to finally settle the issues and all related matters in respect of the project.5
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
6 The respondent then commenced arbitration against the applicant for payment of two final milestone invoices and for additional works. Before the tribunal, the applicant advanced three jurisdictional objections:
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
that in light of the Settlement Agreement, there was no dispute for determination (“Settlement Agreement Ground”);
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
that the respondent lacked locus standi to commence arbitration without joining Co A (the Consortium leader) as claimant (“Locus Standi Ground”); and
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
that the respondent had not complied with the pre-arbitration procedure (“Pre-Arbitration Ground”).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
7 The tribunal dismissed the jurisdictional objections, holding that:
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
the Settlement Agreement Ground raised a question of admissibility rather than jurisdiction, and hence, whether the Settlement Agreement precluded the respondent from commencing arbitration would be determined after the substantive hearing of the arbitration;
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
the arbitration clause did not require all three parties (the applicant, Co A and the respondent) to be parties to the arbitration; and
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
the pre-arbitration steps were not conditions precedent to the commencement of arbitration.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
8 Before the Singapore High Court, the applicant pursued two of the three grounds mentioned above:
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
The respondent had no locus standi to commence arbitration without joining Co A (ie, the Locus Standi Ground).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
The respondent had not complied with the pre-arbitration procedure (ie, the Pre-Arbitration Ground).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
9 On the Locus Standi Ground, the court held that the Contract did not require Co A and the respondent to act jointly in all respects, including in commencing arbitration regardless of the nature of the dispute.6 Although several provisions reflected Co A’s role as the leader of the Consortium, the decisive question was whether the parties intended the arbitration clause to be invocable only by Co A and the respondent acting jointly.7
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
10 In answering that question, the court began by examining the Contract’s structure, which contemplated circumstances in which Co A and the respondent could act jointly as well as individually.8 This structural point informed the court’s interpretation of the arbitration clause and related provisions.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
11 The arbitration clause provided that all disputes “shall be finally settled by arbitration”.9 The parties accepted that the clause could be invoked by either “PARTY”, referring to the “OWNER” or the “CONTRACTOR”. The interpretive issue therefore turned on whether the “CONTRACTOR” was necessarily the Consortium acting jointly, or whether it could include an individual consortium member.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
As “Party” included the “Contractor”, the scope of the right to invoke arbitration depended on the definition of “Contractor”.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
The Contract defined “Contractor” as Co A and the respondent “jointly and severally” [emphasis in original].10 The court treated the words “and severally” as indicating that “Contractor” could, in an appropriate context, refer to the respondent acting alone.11
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
12 The court also relied on cl 25.3 of the Contract, which contemplated “one [arbitrator] to be nominated by each of the PARTIES in dispute”.12 The reference to “PARTIES in dispute” was taken as recognition that disputes might arise between the applicant and (a) Co A and the respondent jointly; (b) Co A alone; or (c) the respondent alone.13 On the facts, the dispute concerned the applicant’s non-payment of the respondent’s invoices, such that the “PARTIES in dispute” were the applicant and the respondent.14 The court therefore held that the respondent could invoke the arbitration agreement in its own name.15
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
13 On the Pre-Arbitration Ground, the court considered whether cl 25.7 imposed a mandatory, tiered dispute resolution process as a condition precedent to arbitration. Clause 25.7 provided:16
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
25.7 Notwithstanding the above, any dispute between the PARTIES shall, in first instance, be submitted by the PARTIES to their respective project management level for resolution, failing which the dispute shall then be referred to their respective senior management level.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
14 The reference to “the above” was construed as referring to cll 25.1 to 25.6, which dealt with arbitration and governing law.17
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
15 As a matter of Singapore law, the court held that compliance with tiered dispute resolution mechanisms (including preconditions to arbitration) was generally an issue of admissibility rather than jurisdiction.18 The court also observed that this approach aligns Singapore law with the prevailing view in international arbitration.19
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
16 In doing so, the court considered the case of International Research Corp PLC v Lufthansa Systems20 (“Lufthansa”), where the Court of Appeal appeared to hold that the non-fulfilment of preconditions to arbitration was a matter that went to the jurisdiction of the tribunal. However, the court in DRO v DRP found that the issue of the jurisdiction/admissibility dichotomy for preconditions to arbitration had not been argued before the Court of Appeal in Lufthansa. Accordingly, the court held that Lufthansa’s treatment of conditions precedent as matters going to jurisdiction was obiter and not binding.21 Further, after considering the parties’ arguments, the court found that preconditions to arbitration were matters that went to admissibility as opposed to jurisdiction, as this was consistent with the principles relating to the distinction between jurisdiction and admissibility and was in line with the general consensus in international arbitration. Additionally, the court in DRO v DRP also observed that this approach had been approved by the Court of Appeal in obiter in BTN v BTP.22
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
17 On the wording of cl 25.7 itself, the court held that it did not contain sufficiently clear language to create a condition precedent to the commencement of arbitration; the phrase “notwithstanding the above” was, at best, equivocal.23
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
18 However, the court accepted the applicant’s contention that cl 25.7 envisaged a structure of escalation, whereby disputes were to be progressively referred to representatives of increasing seniority within each party’s organisation. On this basis, the court found that the requirement had not been complied with as the same representatives had attended the relevant meetings without any escalation to higher levels of management.24
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
19 The applicant also raised that cl 25.7 of the Contract required that the dispute must first be submitted to the respective management levels of the applicant, respondent and Co A for resolution. The applicant’s position was that since the designated project managers for both the applicant and the respondent did not attend the alleged project management meeting, there was no compliance. The court disagreed with this as the Contract did not define “project management level”, and thus it was for the applicant and respondent to decide who to send to the meeting.25
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
20 Lastly, the respondent argued that, on the facts of the case, the applicant had waived strict compliance with cl 25.7.26 The court agreed with this submission as the applicant had agreed to the respondent’s request for a senior management level meeting under cl 25.7 and did not reject the request on the ground that no project management level meeting had been held. Hence, the court found that the applicant had waived its right to strict compliance of cl 25.7.27
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
21 Accordingly, the court dismissed the application on both the Locus Standi Ground and the Pre-Arbitration Ground. The decision in DRO v DRP was shortly followed by another High Court decision that dealt with unincorporated associations in DQR v DQT.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
III. Developments in Singapore following DRO v DRP
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
22 The General Division’s decision in DQR v DQT reinforced the theme in DRO v DRP: Where an unincorporated joint venture is involved, careful drafting is required to ensure that the contractual architecture (and any associated payment mechanics) operates coherently in arbitration.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
23 In DQR v DQT, the claimants sought to set aside an award made in favour of the defendant. The court referred to the jurisdiction as “Ruritania” to preserve arbitral confidentiality.28 The claimants shared a common holding company and were treated as related corporations.29
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
24 The dispute arose out of the parties’ co-operation in tendering for, and executing, a major infrastructure project in Ruritania.30
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
25 To document the parties’ co-operation, a suite of contracts was executed.31 First, the defendant and the second claimant entered into the “Tender Teaming Agreement (Unincorporated JV)”.32
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
26 The second contract, the “Design and Construct Deed”, was entered into by the defendant and the second claimant with the employer in early December 2014.33
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
27 Third, the defendant and the second claimant entered into the “Joint Venture Deed” (“JV Deed”) in August 2015, establishing an unincorporated joint venture (“JV”).34 The JV Deed included a trust-and-payment mechanism for sums received “in connection with” the JV, requiring payment into designated project account(s), including the account nominated for any “surplus funds in respect of any arbitral award”35 (“JV Account”).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
28 Fourth, all three parties entered into the “Services Contract” (“Services Contract”), which was governed by Ruritanian law. It provided for arbitration in Singapore for disputes arising out of or in connection with the Services Contract.36
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
29 The JV delivered the project to the employer more than 14 months late and incurred substantial losses, including $2.1m in liquidated damages that was deducted from the final account for the project under a commercial settlement.37
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
30 This led to a dispute between the parties as to who had caused the loss. The defendant blamed the first claimant and sought compensation for the losses from the first claimant. In turn, the first claimant blamed the JV and denied any liability to compensate the defendant for any loss.38 The second claimant refused to join the defendant in its claim against the first claimant despite it being a joint promisee (with the defendant) with respect to the contractual duties that the first claimant owed to the JV under the Services Contract. This was ostensibly because the claimants were related corporations.39
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
31 In the arbitration, the tribunal accepted substantial parts of the defendant’s case on liability, including its findings of breaches of certain duties under the Services Contract and ordered the first claimant to pay $12m in damages (with interest and costs) to the defendant.40
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
32 The claimants sought to set aside this award on the ground that it dealt with a dispute beyond the scope of the submission to arbitration.41 The claimants’ case was that the tribunal made two key findings in the award that necessarily required a consideration of the terms of the JV Deed, and was therefore in excess of its jurisdiction.42 The findings made by the tribunal and relied on by the claimants were as follows:43
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
The loss suffered were personal to the defendant as long as they fell outside the JV Account.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Therefore, the sums awarded in the arbitration should be paid to the defendant directly and not to the JV Account.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
33 The Singapore General Division found that the tribunal did not exceed its jurisdiction. This was because the tribunal had only made a finding that the damages it awarded were personal to the defendant, based on the evidence presented in the arbitration.44 It did not allocate blame as between the defendant and the second claimant, nor did it award the loss jointly to the defendant and the second claimant, since no evidence or claim was adduced by the second claimant.45
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
34 Ultimately, the court found it clear that the tribunal had recognised that (a) whether the second claimant was entitled to any part of the damages; and (b) whether the defendant was obliged to account to the JV for the damages or (to pay damages into the project account), were disputes under the JV Deed.46
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
35 The court found that the tribunal had only ordered the first claimant to pay the damages directly to the defendant because this was the usual form of award in an arbitration where only one claimant sought damages.47 The court therefore dismissed the claimants’ application.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
36 From a drafting perspective, DQR v DQT illustrates the risks of a fragmented, multi-contract structure where the consequences of an arbitral award (including payment destination and accounting obligations) are dealt with in one instrument (ie, the JV Deed) but the arbitration proceeds are dealt with in another (ie, the Services Contract). Where those instruments do not speak to one another, a tribunal may revert to the “usual form” of award,48 even if it does not reflect the parties’ commercial allocation of funds.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
37 To mitigate these risks, parties should ensure that the rights and obligations of members of a joint venture/consortium are recorded consistently across all project contracts, including express provisions on (a) authority to commence arbitration; and (b) the treatment of proceeds of any award or amicable settlement.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
IV. Case law in India on consortium agreements relevant to DRO v DRP
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
38 The court’s approach in DRO v DRP may be contrasted with three Indian decisions addressing similar questions: Raster Images Pvt Ltd Tamil Nadu v State of UP49 (“Raster”), Geo Miller & Co Pvt Ltd v Bihar Urban Infrastructure Development Corp Ltd50 (“Geo Miller”) and Consulting Engineers Group Ltd v National Highways Authority of India51 (“Consulting Engineers”).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
39 In these cases, the courts considered contracts between an unincorporated consortium and a third party where a dispute arose involving an individual consortium member. The issue was whether that member could invoke the arbitration clause independently of the consortium.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
40 The courts held that an individual consortium member could not invoke the arbitration agreement independently.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
41 In Consulting Engineers, the court held that the arbitration clause could only be invoked by the consortium, as an individual member was not a party to the arbitration agreement in its personal capacity. This was, inter alia, because the agreement between the consortium members did not vest any authority in a non-leader member to pursue contractual matters, including the invocation of the dispute resolution clause.52
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
42 In Raster, the court reasoned that the arbitration clause envisaged a two-party regime and prescribed a three-member tribunal: an arbitrator appointed by the consortium, an arbitrator appointed by the other contracting party, and a presiding arbitrator appointed by the two party-appointed arbitrators.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
43 A reading that the arbitration clause was intended to refer every dispute between consortium members inter se to arbitration would do violence to the language of the clause.53
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
44 In a situation where that reading is adopted, each member of the consortium would have a right to appoint its own arbitrator. Where there are three consortium members, this would result in three arbitrators being appointed on behalf of the members, one more arbitrator being appointed by the other contracting party, and a presiding arbitrator appointed by the four arbitrators. The tribunal would thus comprise five arbitrators, notwithstanding that the arbitration clause envisaged a three-member tribunal.54
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
45 Additionally, the court specifically noted that the disputes raised by the claimant “gave a flavour of disputes between the Consortium members inter-se and not so much between the Consortium on one hand and the respondent-Authority on the other”.55 The court was careful to scrutinise the true nature of the dispute, particularly in determining whether it was one that properly engaged the main contract (eg, a dispute between the owner and the consortium) as opposed to the consortium agreement (eg, a dispute between the consortium members themselves).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
46 In Geo Miller, the court had emphasised that the agreement was between the consortium and the owner of the project, and the consortium was to be represented through its leader; correspondingly, the arbitration agreement was not intended to be invoked by a single member acting alone.56
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
47 Against that background, the General Division in DRO v DRP distinguished Raster and Geo Miller on the basis of drafting differences. In particular, the court noted that those cases lacked:57
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
a definition of the consortium members as “jointly and severally” liable; and
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
contractual rights that were conferred on individual members to the exclusion of others.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
48 Taken together, DRO v DRP demonstrates that small drafting choices – particularly defined terms and internal consistency – can determine the outcome in disputes involving unincorporated consortia. Inconsistent use of language across the Contract fuelled uncertainty as to whether the parties intended a two-party or three-party regime; that uncertainty, in turn, framed the court’s analysis of who was entitled to invoke the arbitration clause.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
49 The broader point is that agreements involving unincorporated consortia/joint ventures should be drafted with disciplined use of defined terms and a coherent allocation of authority and risk, so as to reduce the scope for an outcome that departs from the parties’ negotiated position.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
V. Developments in Singapore relating to jurisdiction–admissibility dichotomy in respect of preconditions to arbitration
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
50 As set out above, DRO v DRP set out a new path by dealing with the contentious issue of whether non-compliance with preconditions to arbitration ought to be a matter of admissibility or jurisdiction.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
51 Prior to DRO v DRP, the Singapore courts had not directly addressed this issue, and it had been understood, on the basis of Lufthansa, that this was a matter going to the jurisdiction of the tribunal. However, recent case law shows that Singapore is moving away from this position, towards the position that preconditions to arbitration are generally matters going to admissibility instead.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
52 In Lufthansa, the appellant challenged the arbitral tribunal’s jurisdiction on the grounds that, amongst other things, the respondent had not fulfilled the preconditions to arbitration.58 The Court of Appeal held that the tribunal did not have jurisdiction as a result of the non-compliance.59 Lufthansa was subsequently cited in the seminal textbook Arbitration in Singapore: A Practical Guide60 for the proposition that a tribunal’s jurisdiction can be challenged where there is non-compliance with condition precedents for proceeding to arbitration.61
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
53 However, the position ostensibly set out in Lufthansa was called into question by a subsequent Court of Appeal decision, BTN v BTP. In this case, the court had to decide whether a tribunal’s decision on the res judicata effect of a prior decision was a matter going to admissibility or jurisdiction.62 In coming to its decision, the Court of Appeal, in obiter, cited the learned author Jan Paulsson’s view that preconditions to arbitration are matters of admissibility, not jurisdiction.63
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
54 Subsequently, in DRO v DRP, as discussed above, the General Division found that a precondition to arbitration was a matter that went to admissibility, and not jurisdiction, for three reasons:64
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
First, in principle, this was consistent with the distinction between jurisdiction (ie, the power of the tribunal to hear a case) and admissibility (ie, whether it was appropriate for the tribunal to hear it).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Second, the Court of Appeal in BTN v BTP had approved of this view, albeit in obiter.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
Third, this would be in line with the general consensus in international arbitration that preconditions to arbitration should be treated as matters of admissibility rather than jurisdiction.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
55 This position appears to be further cemented in the recent High Court decision of DSQ v DSR65 (“DSQ v DSR”), in which the General Division followed the position in DRO v DRP. In particular, DSQ v DSR agreed that Lufthansa was not a binding authority on the issue, and that a precondition to arbitration is generally a matter of admissibility and not jurisdiction.66
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
56 However, DSQ v DSR emphasised that this general proposition could be displaced, eg, where there is “unequivocally clear language” demonstrating that the parties intended the preconditions to arbitration to constitute part of their consent to the tribunal’s authority to arbitrate, the issue would properly be characterised as one of jurisdiction.67
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
57 In light of the above, the key takeaway is that the characterisation of pre-arbitration steps, ie, whether they are matters of admissibility or jurisdiction, ultimately turns on how the parties express their intention in the contractual documents. If the parties intend such preconditions to be mandatory and intend for them to impact their consent to arbitration (ie, conditions going to the tribunal’s authority and jurisdiction), this must be articulated in clear and unequivocal terms. In this regard, the clause should expressly state that the parties’ consent is conditional, and that the tribunal shall have no jurisdiction unless and until the specified and precisely defined steps have been satisfied.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
58 Absent such clarity, Singapore courts are likely to treat non-compliance with preconditions to arbitration as an issue of admissibility, leaving the tribunal to decide on the matter, thereby limiting the scope for curial intervention.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
VI. Conclusion
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
59 The decisions in DRO v DRP and DQR v DQT illustrate that where a joint venture/consortium is not a separate legal entity, drafting is not merely formal: It determines who may invoke the arbitration agreement and how the arbitral process interacts with the parties’ wider commercial arrangements.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
60 Parties, as well as drafters of agreements involving consortiums or joint ventures, should carefully consider which disputes ought to be adjudicated under the contract between the consortium/joint venture and the third party and which should fall under the consortium or joint venture agreement, eg, whether the apportionment of liquidated damages should be resolved between the owner, the consortium and its members, or whether this should be an issue resolved solely between consortium members, and whether all consortium members must be involved in the dispute resolution mechanisms.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
61 Corresponding provisions should then be made to reflect this understanding, which must be consistent across both contracts. This is to avoid speculation from the parties’ counsel and the court if and when disputes arise.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
62 Practitioners should therefore ensure that a contract’s defined terms are precise, applied consistently, and aligned across related contract(s) within the project structure. Where authority to commence arbitration, joinder requirements, and payment mechanics for award proceeds are left implicit (or are addressed only in a separate instrument), the resulting ambiguity may be resolved by a court or tribunal in a manner that the parties may not have anticipated.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
63 In the same vein, if parties intend pre-arbitration steps to operate as true conditions precedent going to the tribunal’s jurisdiction, this must be expressed in unequivocally clear language; otherwise, such requirements are likely to be treated as matters of admissibility within the tribunal’s remit, thereby limiting opportunities for jurisdictional challenge and curial intervention.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
1 [2026] 3 SLR 1012.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
2 [2026] SGHC 23.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
3 DRO v DRP [2026] 3 SLR 1012 at [1].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
4 DRO v DRP [2026] 3 SLR 1012 at [3]–[5].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
5 DRO v DRP [2026] 3 SLR 1012 at [10].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
6 DRO v DRP [2026] 3 SLR 1012 at [25].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
7 DRO v DRP [2026] 3 SLR 1012 at [24].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
8 DRO v DRP [2026] 3 SLR 1012 at [26].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
9 DRO v DRP [2026] 3 SLR 1012 at [29].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
10 DRO v DRP [2026] 3 SLR 1012 at [26] and [29].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
11 DRO v DRP [2026] 3 SLR 1012 at [26].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
12 DRO v DRP [2026] 3 SLR 1012 at [31].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
13 DRO v DRP [2026] 3 SLR 1012 at [31].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
14 DRO v DRP [2026] 3 SLR 1012 at [33].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
15 DRO v DRP [2026] 3 SLR 1012 at [39].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
16 DRO v DRP [2026] 3 SLR 1012 at [55].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
17 DRO v DRP [2026] 3 SLR 1012 at [55].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
18 DRO v DRP [2026] 3 SLR 1012 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
19 DRO v DRP [2026] 3 SLR 1012 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
20 [2014] 1 SLR 130.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
21 DRO v DRP [2026] 3 SLR 1012 at [59] and [64].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
22 [2021] 1 SLR 276. DRO v DRP [2026] 3 SLR 1012 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
23 DRO v DRP [2026] 3 SLR 1012 at [71]–[72].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
24 DRO v DRP [2026] 3 SLR 1012 at [90].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
25 DRO v DRP [2026] 3 SLR 1012 at [85].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
26 DRO v DRP [2026] 3 SLR 1012 at [92].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
27 DRO v DRP [2026] 3 SLR 1012 at [95]–[96].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
28 DQR v DQT [2026] SGHC 23 at [1].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
29 DQR v DQT [2026] SGHC 23 at [3].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
30 DQR v DQT [2026] SGHC 23 at [4].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
31 DQR v DQT [2026] SGHC 23 at [9].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
32 DQR v DQT [2026] SGHC 23 at [10]–[11].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
33 DQR v DQT [2026] SGHC 23 at [13]–[14].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
34 DQR v DQT [2026] SGHC 23 at [17]–[18].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
35 DQR v DQT [2026] SGHC 23 at [24].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
36 DQR v DQT [2026] SGHC 23 at [30] and [34].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
37 DQR v DQT [2026] SGHC 23 at [37].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
38 DQR v DQT [2026] SGHC 23 at [38].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
39 DQR v DQT [2026] SGHC 23 at [40].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
40 DQR v DQT [2026] SGHC 23 at [71].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
41 DQR v DQT [2026] SGHC 23 at [81].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
42 DQR v DQT [2026] SGHC 23 at [85].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
43 DQR v DQT [2026] SGHC 23 at [85].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
44 DQR v DQT [2026] SGHC 23 at [87].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
45 DQR v DQT [2026] SGHC 23 at [88].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
46 DQR v DQT [2026] SGHC 23 at [92].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
47 DQR v DQT [2026] SGHC 23 at [92].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
48 DQR v DQT [2026] SGHC 23 at [78].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
49 (2023) 9 ILRA 1099; 2023 STPL (Web) 126 Allahabad.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
50 (2017) 1 ArbiLR 245.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
51 OMP (I) (COMM) 244/2022.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
52 Consulting Engineers Group Ltd v National Highways Authority of India OMP (I) (COMM) 244/2022.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
53 Raster Images Pvt Ltd Tamil Nadu v State of UP (2023) 9 ILRA 1099; 2023 STPL (Web) 126 Allahabad (“Raster”) at [53].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
54 Raster at [54].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
55 Raster at [23].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
56 Geo Miller & Co Pvt Ltd v Bihar Urban Infrastructure Development Corp Ltd (2017) 1 ArbiLR 245 at [19]-[20].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
57 DRO v DRP [2026] 3 SLR 1012 at [53].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
58 International Research Corp PLC v Lufthansa Systems Asia Pacific Pte Ltd [2014] 1 SLR 130 at [8].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
59 International Research Corp PLC v Lufthansa Systems Asia Pacific Pte Ltd [2014] 1 SLR 130 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
60 (Sundaresh Menon ed-in-chief) (Sweet & Maxwell, 2nd Ed, 2018).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
61 Arbitration in Singapore: A Practical Guide (Sundaresh Menon ed-in-chief) (Sweet & Maxwell, 2nd Ed, 2018) at para 10.067, fn 65.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
62 BTN v BTP [2021] 1 SLR 276 at [68] and [71].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
63 BTN v BTP [2021] 1 SLR 276 at [70]–[71]; Jan Paulsson, “Jurisdiction and Admissibility” (2005) in Global Reflections On International Law, Commerce and Dispute Resolution (Gerald Aksen et al eds) (ICC Publishing, 2005) at p 616.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
64 DRO v DRP [2026] 3 SLR 1012 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
65 [2026] SGHC 67.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
66 DSQ v DSR [2026] SGHC 67 at [87].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
67 DSQ v DSR [2026] SGHC 67 at [87]–[90].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
© 2026 Contributor(s) and Singapore Academy of Law.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
No part of this document may be reproduced without permission from the copyright holders.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
1 [2026] 3 SLR 1012.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
2 [2026] SGHC 23.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
3 DRO v DRP [2026] 3 SLR 1012 at [1].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
4 DRO v DRP [2026] 3 SLR 1012 at [3]–[5].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
5 DRO v DRP [2026] 3 SLR 1012 at [10].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
6 DRO v DRP [2026] 3 SLR 1012 at [25].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
7 DRO v DRP [2026] 3 SLR 1012 at [24].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
8 DRO v DRP [2026] 3 SLR 1012 at [26].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
9 DRO v DRP [2026] 3 SLR 1012 at [29].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
10 DRO v DRP [2026] 3 SLR 1012 at [26] and [29].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
11 DRO v DRP [2026] 3 SLR 1012 at [26].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
12 DRO v DRP [2026] 3 SLR 1012 at [31].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
13 DRO v DRP [2026] 3 SLR 1012 at [31].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
14 DRO v DRP [2026] 3 SLR 1012 at [33].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
15 DRO v DRP [2026] 3 SLR 1012 at [39].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
16 DRO v DRP [2026] 3 SLR 1012 at [55].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
17 DRO v DRP [2026] 3 SLR 1012 at [55].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
18 DRO v DRP [2026] 3 SLR 1012 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
19 DRO v DRP [2026] 3 SLR 1012 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
20 [2014] 1 SLR 130.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
21 DRO v DRP [2026] 3 SLR 1012 at [59] and [64].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
22 [2021] 1 SLR 276. DRO v DRP [2026] 3 SLR 1012 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
23 DRO v DRP [2026] 3 SLR 1012 at [71]–[72].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
24 DRO v DRP [2026] 3 SLR 1012 at [90].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
25 DRO v DRP [2026] 3 SLR 1012 at [85].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
26 DRO v DRP [2026] 3 SLR 1012 at [92].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
27 DRO v DRP [2026] 3 SLR 1012 at [95]–[96].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
28 DQR v DQT [2026] SGHC 23 at [1].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
29 DQR v DQT [2026] SGHC 23 at [3].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
30 DQR v DQT [2026] SGHC 23 at [4].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
31 DQR v DQT [2026] SGHC 23 at [9].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
32 DQR v DQT [2026] SGHC 23 at [10]–[11].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
33 DQR v DQT [2026] SGHC 23 at [13]–[14].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
34 DQR v DQT [2026] SGHC 23 at [17]–[18].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
35 DQR v DQT [2026] SGHC 23 at [24].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
36 DQR v DQT [2026] SGHC 23 at [30] and [34].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
37 DQR v DQT [2026] SGHC 23 at [37].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
38 DQR v DQT [2026] SGHC 23 at [38].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
39 DQR v DQT [2026] SGHC 23 at [40].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
40 DQR v DQT [2026] SGHC 23 at [71].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
41 DQR v DQT [2026] SGHC 23 at [81].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
42 DQR v DQT [2026] SGHC 23 at [85].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
43 DQR v DQT [2026] SGHC 23 at [85].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
44 DQR v DQT [2026] SGHC 23 at [87].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
45 DQR v DQT [2026] SGHC 23 at [88].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
46 DQR v DQT [2026] SGHC 23 at [92].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
47 DQR v DQT [2026] SGHC 23 at [92].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
48 DQR v DQT [2026] SGHC 23 at [78].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
49 (2023) 9 ILRA 1099; 2023 STPL (Web) 126 Allahabad.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
50 (2017) 1 ArbiLR 245.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
51 OMP (I) (COMM) 244/2022.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
52 Consulting Engineers Group Ltd v National Highways Authority of India OMP (I) (COMM) 244/2022.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
53 Raster Images Pvt Ltd Tamil Nadu v State of UP (2023) 9 ILRA 1099; 2023 STPL (Web) 126 Allahabad (“Raster”) at [53].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
54 Raster at [54].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
55 Raster at [23].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
56 Geo Miller & Co Pvt Ltd v Bihar Urban Infrastructure Development Corp Ltd (2017) 1 ArbiLR 245 at [19]-[20].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
57 DRO v DRP [2026] 3 SLR 1012 at [53].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
58 International Research Corp PLC v Lufthansa Systems Asia Pacific Pte Ltd [2014] 1 SLR 130 at [8].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
59 International Research Corp PLC v Lufthansa Systems Asia Pacific Pte Ltd [2014] 1 SLR 130 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
60 (Sundaresh Menon ed-in-chief) (Sweet & Maxwell, 2nd Ed, 2018).
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
61 Arbitration in Singapore: A Practical Guide (Sundaresh Menon ed-in-chief) (Sweet & Maxwell, 2nd Ed, 2018) at para 10.067, fn 65.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
62 BTN v BTP [2021] 1 SLR 276 at [68] and [71].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
63 BTN v BTP [2021] 1 SLR 276 at [70]–[71]; Jan Paulsson, “Jurisdiction and Admissibility” (2005) in Global Reflections On International Law, Commerce and Dispute Resolution (Gerald Aksen et al eds) (ICC Publishing, 2005) at p 616.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
64 DRO v DRP [2026] 3 SLR 1012 at [63].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
65 [2026] SGHC 67.
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
66 DSQ v DSR [2026] SGHC 67 at [87].
[SAL Prac]: Drafting lessons from recent consortium and joint venture construction arbitrations in Singapore
67 DSQ v DSR [2026] SGHC 67 at [87]–[90].
If one provision's text doesn't match the official source, use Suggest a fix beside that provision — it opens an editor next to the source document. For anything else — a missing amendment, a broken link, out-of-date content, or a removal request — report it here.