General Division of the High Court · Decided 4 October 2017
OGSP Engineering Pte Ltd v Comfort Management Pte Ltd
[2017] SGHC 247 · Case no. Originating Summons No 478 of 2017 (Summons Nos 2425 and 3856 of 2017) · 43 paragraphs
✱ What happened, in plain English
There is no plain-English summary of this judgment yet.
Ask about this judgment →Grounds of decision
Official text from eLitigation
Introduction
- [1]
[1] OGSP Engineering Pte Ltd (“OGSP”) was hired by Comfort Management Pte Ltd (“Comfort”) as a sub-contractor for its project. A dispute arose between OGSP and Comfort, as a consequence of which OGSP lodged a payment claim titled Payment Claim No 12 (“PC12”) against Comfort for certain work done. Comfort did not file a payment response. Although Comfort eventually filed an adjudication response during the adjudication proceedings, the adjudication response was invalid as it was out of time. Hence, OGSP obtained an adjudication determination dated 21 April 2017 in its favour (“the AD”).
- [2]
[2] OGSP filed Originating Summons No 478 of 2017 (“OS 478”) to enforce the AD as a judgment debt. In response, Comfort filed Summons No 2425 of 2017 (“SUM 2425”) to set aside the AD. Having heard the parties’ submissions, I gave brief reasons to explain why I dismissed Comfort’s application to set aside the AD. I now explain my reasons in further detail.
Background
- [3]
[3] Both Comfort and OGSP are Singapore-incorporated companies with the principal business of general construction and building works. In October 2013, Comfort engaged OGSP under a sub-contract where OGSP was to supply and install a ventilation and ducting system for a warehouse in Joo Koon Circle for a fixed sum of $1.25m (excluding GST) (“the Contract”).
- [4]
[4] On 16 March 2017, OGSP issued PC12 to Comfort for work done between October 2013 and October 2014. The amount claimed was $890,262.23 (including GST). On 30 March 2017, Comfort’s lawyers sent an email to OGSP stating that the invoices in PC12 had already been paid and asked for additional supporting documents. Notwithstanding that letter, OGSP served its Notice of Intention to Apply for Adjudication on Comfort on 4 April 2017. On 6 April 2017, OGSP served its adjudication application on the Singapore Mediation Centre (“SMC”) and filed its submissions for the adjudication application. SMC served a copy of the adjudication application on Comfort on 7 April 2017. Comfort filed its adjudication response and its submissions with the SMC on 17 April 2017. OGSP objected to the adjudication response on the ground that it was out of time.
- [5]
[5] On 21 April 2017, the adjudicator issued his AD and held, among other things, that the sum of $890,262.23 was payable by Comfort to OGSP within seven days after the service of the AD on Comfort. OGSP filed OS 478 on 3 May 2017 seeking to enforce the AD as a judgment debt and Comfort sought to set aside the AD in SUM 2425.
Parties’ submissions
Comfort’s submissions
- [6]
[6] Comfort accepted the adjudicator’s finding that there was no valid payment response and adjudication response within the meaning of the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (the “SOPA”). Hence, Comfort also accepted that, under s 15(3) of the SOPA, the adjudicator could not consider any matter that had not been raised in the payment response. However, it submitted that the court should still set aside the AD on two grounds.
- [8]
[8] In relation to the contract sum and the retention money, Comfort alleged that OGSP had provided “absolutely no supporting documents” evincing that the work claimed for had been done. The supporting documents related to 92% of the work which had already been completed but not the remaining 8% which was part of the claim in PC12. The adjudicator made a leap of logic by concluding at para 68.1 of the AD that there were “no materials or information… to suggest that the Works were not completed or that the Retention Money [was] not due for release”. Instead, the adjudicator should have required OGSP to provide evidence of its claims.
- [9]
[9] In relation to OGSP’s claims for variation works, Comfort submitted that the only paragraph which dealt with this in the AD – para 68.2 – did not make any mention of the relevant contractual provisions such as cl 11 of the Contract. If the adjudicator had applied his mind to the contractual provisions, it would have been “readily apparent” that OGSP provided no evidence of the variation works, as required under the Contract. In addition, OGSP did not set out the sums it claimed in the adjudication application or in PC12, but rather only did so subsequently in its submissions in the adjudication application.
- [11]
[11] Comfort’s second ground for setting aside the AD was that there was a fraudulent conspiracy involving OGSP, RSP Engineering Pte Ltd (formerly known as SS Mechanical and Electrical Engineering Pte Ltd) (“SS Mechanical”), and Pintu Kumar Sarker (“Pintu”) who was Comfort’s project manager and SS Mechanical’s initial sole director and shareholder. The alleged conspiracy was that OGSP would present inflated invoices for work done when no such work had in fact been done by that time, and that Pintu would facilitate the invoices. Ultimately, the aim was to obtain frontloaded payments from Comfort for work not yet done, to benefit the conspirators.
OGSP’s submissions
- [13]
[13] OGSP submitted that neither of Comfort’s two grounds was sufficient for the court to set aside the AD.
- [14]
[14] In relation to Comfort’s first ground to set aside the AD which was that the adjudicator had failed to consider patent errors, OGSP made two arguments. First, OGSP submitted that the adjudicator had correctly dismissed Comfort’s arguments that there were patent errors in OGSP’s claim. OGSP said that Comfort was “abusing” the setting-aside application to ask the court to infer that the adjudicator had merely “rubber-stamped” the adjudication application when he had not. OGSP relied on para 65 of the AD, where the adjudicator expressly noted that “even in the absence of a payment response or an adjudication response, [he] must not merely rubber stamp a claim”. OGSP also argued that by failing to raise the alleged patent errors at the payment response stage, Comfort had waived its right to raise this objection before the adjudicator and in court.
- [15]
[15] Second, OGSP said that in any event there were no patent errors in its claim. For the contract sum and the retention money, OGSP submitted that it was Comfort who continually refused to verify the work done despite multiple email chasers. OGSP relied on the fact that the registered inspector’s inspection and the Temporary Occupation Permit (“TOP”) inspection had been completed. These indicated that the work concerned had been completed. OGSP acknowledged Comfort’s allegations that no invoices were attached to PC12 for 8% of the work, but said that the Contract was still substantially completed since Comfort had certified that the remaining 92% was complete and because the warehouse itself had already gone into operation and was accessible to the public.
- [16]
[16] For the variation works, OGSP said that Comfort could not object to OGSP’s claims as it took a “hands off” approach and left the issue of the variation works to OGSP. When OGSP asked Comfort for clear written instructions, Comfort’s representatives refused to provide any.
- [18]
[18] In relation to Comfort’s second ground to set aside the AD which was that there was a conspiracy of front loading the invoices, OGSP submitted that apart from SS Mechanical’s invoices, no documents linked Pintu to OGSP. Even SS Mechanical’s invoices presented were nothing out of the ordinary. In fact, it was Comfort who told OGSP that the latter should contact Pintu as he was the project manager. Finally, OGSP highlighted that Comfort did not raise the allegation of conspiracy in the adjudication response and this was only raised for the first time in the affidavit of one Lew Sien Yen Wenda (“Wenda Lew”) dated 26 May 2017. Therefore, this showed that the allegation of conspiracy was nothing more than an afterthought.
The court’s decision
Issues
- [19]
[19] There were two issues before the court:
(a) whether the adjudicator failed to consider any patent error in OGSP’s claim such that the AD should be set aside; and
(b) whether there was a fraudulent conspiracy between OGSP, SS Mechanical and Pintu to present inflated invoices to Comfort such that the AD should be set aside.
The adjudicator’s alleged failure to consider patent errors
- [20]
[20] Comfort’s failure to lodge a payment response and its late adjudication response put it at a great disadvantage during its application to set aside the AD. Section 15(3) of the SOPA prohibits the adjudicator from considering matters not raised in the payment response:
Therefore, the adjudicator was correct not to have considered Comfort’s explanation for not honouring PC12. Comfort could not set aside the AD based on the adjudicator’s failure to consider anything within its payment response and adjudication response, which Comfort rightly conceded.
- [21]
[21] However, even if the respondent failed to file a payment response (which would prevent the adjudicator from considering the arguments raised in the payment response under s 15(3) of the SOPA), the adjudicator would still need to consider patent errors in the adjudication application. The Court of Appeal in W Y Steel Construction Pte Ltd v Osko Pte Ltd [2013] 3 SLR 380 (“W Y Steel”) expressed the respondent’s right to have patent errors considered even though it did not file a payment response in the following terms (at [50]–[52]):
- [22]
[22] Nevertheless, it must be emphasised that the court “should not review the merits of an adjudicator’s decision” (Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal [2013] 1 SLR 401 at [66]). Thus, my focus was confined to the issue of whether the adjudicator had failed to consider and spot patent errors in the adjudication application.
- [23]
[23] As to what is meant by patent errors, the Court of Appeal in W Y Steel intimated that this would refer to “errors manifest from the material that was properly before the [a]djudicator” (at [54]). This was similarly stated by Lee Seiu Kin J in Aik Heng Contracts and Services Pte Ltd v Deshin Engineering & Construction Pte Ltd [2015] SGHC 293 where he noted that patent errors were those that were “on the face of that material” [emphasis omitted] (at [30]). In Kingsford Construction Pte Ltd v A Deli Construction Pte Ltd [2017] SGHC 174, I provided an illustration of a patent error at [35] as follows:
In the present case, I adopted these statements of the law and found that the search for patent errors must be limited to the face of the relevant documents.
- [24]
[24] With these principles in mind, I turn now to explain why I found that the adjudicator did not fail to consider any alleged patent errors in this case.
- [25]
[25] The adjudicator was aware that he had to scrutinise OGSP’s adjudication application for patent errors. This was clear from para 65 of the AD, where the adjudicator noted that “even in the absence of a payment response or an adjudication response, I must not merely rubber stamp a claim. I must consider the material properly before me and consider if there are patent errors”. Having set out this general approach, the adjudicator went on to examine the documents properly before him at paras 67 to 69 and concluded that “[h]aving gone through this AA, I am of the view that there are no reasons for me to suspect that there are any patent errors and so I hold”. Hence, this was not a case where the adjudicator did not know that he had the duty to consider patent errors and hence failed to do so.
- [27]
[27] Comfort additionally submitted that the adjudicator had failed to spot a patent error as he did not consider the contractual provisions before him, particularly cl 11, as required by s 17(3)(b) of the SOPA. Section 17(3)(b) provides that:
- [28]
[28] In my view, s 17(3) does not prescribe what the adjudicator must consider. Rather, it sets out the outer limits of what the adjudicator can consider, ie, the adjudicator cannot consider anything outside what is stated in s 17(3). When a case falls within the outer limits set by s 17(3), the relevant provision is s 15(3), which provides that where the respondent does not file a payment response, the adjudicator cannot consider the respondent’s “reason[s] for withholding any amount”. Hence, I did not accept Comfort’s submissions that the adjudicator in this case was obliged to look at the contractual provisions by virtue of s 17(3) of the SOPA. Instead, the adjudicator would have been wrong to consider the reasons that Comfort provided unless these were reasons that were already on the face of the record, ie, patent errors.
- [30]
[30] It was very unfortunate that Comfort took a condescending approach when it replied to OGSP’s PC12 on 30 March 2017. Comfort took the view that it did not need to file a payment response and it must live with the consequences of its decision. If Comfort was so determined to dispute PC12, as its solicitors have done so vigorously in these proceedings, then it should have lodged a payment response with all the reasons that it had canvassed before the court. The adjudicator would then be obliged to consider those reasons subject to the limits in s 17(3) of the SOPA. Comfort refused to take this golden opportunity and it could not use this court as a forum to ventilate its arguments as to the merits, having chosen to sit on its hands when it could have lodged a payment response. The Court of Appeal in W Y Steel faced a similar application and it had this to say (at [54]):
- [31]
[31] The Court of Appeal’s comments in W Y Steel were also apposite in this case. I rejected Comfort’s attempt to introduce its arguments on the merits of its case by the back door.
- [32]
[32] Accordingly, I was satisfied that the adjudicator did look out for patent errors and found there were none before he delivered the AD. But even assuming that the adjudicator did overlook some patent errors, whether the court would set aside the AD would depend on the seriousness and the extent of the patent errors. If the patent errors were minor and had a marginal or insignificant impact on the adjudication sum, then logically these would be insufficient to set aside the AD. The court would not readily set aside an adjudication determination for the slightest reasons. This approach is also in line with the overall purpose and objective of the SOPA, which is to provide quick justice for the building and construction industry that has cashflow as its lifeblood. I noted these concerns in the recent case of AES Façade Pte Ltd v WYSE Pte Ltd [2017] SGHC 171 (“AES Façade”) at [23] as follows:
A court that readily sets aside adjudication determinations would not be acting in line with the purpose of the SOPA. This is because it would allow unsatisfied respondents to set aside adjudication determinations based on inconsequential failures to consider patent errors, thereby delaying the quick justice envisaged by the SOPA.
- [33]
[33] However, this was not the case here as I found that the adjudicator had not been in breach of his duty to consider patent errors on the face of the materials before him. Thus, there was no need to deal with the issue of whether the errors were sufficiently material to warrant a setting aside. Accordingly, I rejected Comfort’s submissions that the AD should be set aside on this ground.
Allegations of OGSP’s conspiracy to defraud Comfort
- [34]
[34] It was not entirely clear whether the statutory scheme under the SOPA provides for the challenge of adjudication determinations on the ground that it had been obtained by fraud. However, some decided cases appear to have made comments to that effect. In Mansource Interior Pte Ltd v Citiwall Safety Glass Pte Ltd [2014] 3 SLR 264, I noted that “[a]lthough there have been no cases that have held that fraud should be a ground for setting aside an adjudication determination, I am of the opinion that it is a valid ground for setting aside” (at [31]). I did not, however, ultimately make a finding of fraud on the facts. This case went on appeal but the finding on fraud was irrelevant for the purposes of the appeal (see Citiwall Safety Glass Pte Ltd v Mansource Interior Pte Ltd [2015] 5 SLR 482 at [8]).
- [35]
[35] A similar sentiment was expressed by Lee Seiu Kin J in W Y Steel Construction Pte Ltd v Osko Pte Ltd [2012] SGHC 194 at [7], where Lee J concluded that the adjudication determination in that case was valid “except for the possible exception of a clear case of fraud”. Again, this finding was not referenced on appeal.
- [36]
[36] In the Supreme Court of New South Wales case of QC Communications NSW Pty Ltd v CivComm Pty Ltd [2016] NSWSC 1095 (“CivComm”), the New South Wales Supreme Court interpreted the provisions of the Building and Construction Industry Security of Payment Act (Act 46 of 1999), which is in pari materia with the SOPA. The court concluded at [31]–[32] that where an adjudication determination was obtained by fraud in which the adjudicator was not involved, the adjudication determination may be set aside by court proceedings akin to the situation where a judgment was obtained by fraud. The court went on to explain that this may occur where the application is based on facts discovered after the judgment which are material, and it is reasonably clear that the fresh evidence would have provided an opposite verdict.
- [38]
[38] However, I did not find any evidence of fraud on the facts of this case. Comfort alleged that OGSP had entered into a conspiracy with SS Mechanical and Pintu to defraud it. According to Comfort, under the conspiracy OGSP would claim inflated sums to be collected from Comfort. Pintu and SS Mechanical would assist in this process as Pintu was the point of contact between Comfort and OGSP as the project manager. Hence, Pintu would have known of any ‘frontloading’ (ie, inflated claims) that had taken place. To support its claim, Comfort produced an audio transcript of its meeting with Pintu. It asserted that the transcript was evidence of the “frontloading” by OGSP, in that Pintu had admitted to the frontloading during the course of the interview with one Lim Fatt Seng (“Lim”) and Wenda Lew.
- [39]
[39] I had carefully perused the transcript provided and found nothing to suggest that Pintu had admitted that there was frontloading. On the contrary, when Lim pointedly asked him whether he had frontloaded the payment claims, Pintu expressly denied it. The relevant parts of the transcript provided as follows:
- [40]
[40] Contrary to Comfort’s submissions, this passage did not assist its case that Pintu had admitted to frontloading. Instead, Pintu had not only denied the allegation but had also explained that there were back-to-back contracts between OGSP and Comfort, and between Comfort and Lead Management Engineering & Construction Pte Ltd (“Lead”). Under these contracts, OGSP would complete work for Comfort which would in turn complete work for Lead. Hence, the process of certifying work done was managed by Lead and not by Comfort or Pintu himself. Therefore, Pintu could not have facilitated the process of making inflated claims nor could he have been part of any conspiracy with OGSP to submit inflated claims. Pintu’s position was consistent with cl 4 of the Contract, which provides that the payment from Comfort to OGSP would only be due 30 days after Comfort received the payment from Lead. It made sense that Lead (and not Pintu) would have been the one verifying the claims because Comfort would only make payments to OGSP after Lead had certified and made payments to Comfort.
- [41]
[41] In addition to the fact that the audio transcript did not show that Pintu had admitted to frontloading, I also noted that the meeting with Pintu was only conducted very recently – on 22 May 2017. The setting aside application was filed four days later on 26 May 2017. It was clear to me that the meeting with Pintu was conducted in preparation to boost Comfort’s chances in these proceedings. Despite Comfort’s best efforts, the transcript alone was simply insufficient to establish a conspiracy to defraud.
- [43]
[43] I did not accept Comfort’s submissions that Wenda Lew’s third affidavit, along with its attached documents like the audit compliance emails, showed that OGSP did not genuinely believe in the sums that it claimed in PC12. Michelle Kuah (“Kuah”), who was OGSP’s financial controller, deposed on an affidavit that the sums in the audit compliance forms were low because of accounting uncertainties. According to Kuah, the audit compliance forms had been prepared in accordance with the Singapore Financial Reporting Standards. These standards provided that a company’s revenue could only be recognised where “it is probable that the economic benefits associated with the transaction will flow to the entity” and that OGSP’s auditors were hence “reluctant” to allow such sums to be included when there was not enough information about them. She further explained that this lack of information was due to Comfort’s own refusal to provide OGSP with information. Moreover, at this time the adjudication application had yet to be filed.
- [44]
[44] Comfort did not file any affidavit to contradict Kuah’s evidence even though it had the chance to do so, having filed the first affidavit of one Ong Siow Ping, Comfort’s accountant, just three days later. Instead, Comfort’s solicitors sought to question the veracity of her findings during their submissions. Without further evidence provided by Comfort, I found that the reduced claim was more likely to have been an issue with OGSP’s accounting practices or requirements, than to constitute evidence of fraud.
- [45]
[45] Accordingly, I found that Comfort did not establish that there had been a conspiracy amongst OGSP, SS Mechanical and Pintu to defraud Comfort. The audio transcript and Wenda Lew’s third affidavit, whether taken separately or together, were insufficient to establish the requisite fraudulent intention.
Stay of enforcement pending appeal
- [46]
[46] After I dismissed Comfort’s application to set aside the AD in SUM 2425, Comfort took out Summons No 3856 of 2017 (“SUM 3856”) to apply for a stay of enforcement of the AD pending Comfort’s appeal. In essence, Comfort submitted that if the stay were not granted, then Comfort would not be able to recover its monies even if the dispute were ultimately resolved in its favour.
- [47]
[47] Comfort did not submit that OGSP was insolvent as Comfort had no basis to do so. However, Comfort alleged that OGSP had a history of declaring dividends for its shareholders even if this resulted in it having much lesser accumulated profits. In this case, Comfort submitted that OGSP would declare dividends in favour of Rotating Offshore Solutions Ltd (“ROS”), OGSP’s majority shareholder, to reduce the losses that ROS had suffered for the financial year ending 31 March 2016.
The court also noted that the party asking for a stay must satisfy the “high threshold” of demonstrating that a stay is required because it “will not readily be granted having regard to the overall purpose of the [SOPA], which is precisely to avoid and guard against pushing building and construction companies over the financial precipice” [emphasis omitted] (at [71]).
- [50]
[50] Comfort did not meet this high threshold. OGSP is perfectly entitled to declare dividends for its shareholders as long as it did not put its company in the red. Even the evidence that Comfort cited to the court did not show that OGSP was insolvent or was about to be insolvent. Hence, Comfort could not rely on this ground for its stay application.
- [51]
[51] In W Y Steel, W Y Steel argued for a stay because there were 11 lawsuits that had been filed against Osko and the latter would have to pay off the default judgments granted against it in two of the 11 lawsuits. Further, Osko was currently in a net current liability position and had lent money to one of its directors despite its financial difficulties (at [57]). Notwithstanding these liabilities, the Court of Appeal refused to grant the stay, noting that W Y Steel’s evidence was offset by Osko’s evidence that it was solvent even though its paid-up capital was admittedly just $25,000 (W Y Steel at [58] and [72]). The same conclusion applied in the present case. OGSP’s financial controller, Kuah, deposed on an affidavit that OGSP declared its dividends based on previous retained profits and that OGSP did not invariably declare dividends without thinking. For instance, in the financial year ending 31 March 2016, OGSP did not declare dividends in favour of ROS even though it made profits in that financial year. I was unable to agree with Comfort that there was sufficient evidence that OGSP would declare dividends to such an extent that it would be unable to return the adjudicated sum should Comfort succeed on appeal.
- [52]
[52] Furthermore, even if OGSP’s financial statements indicated that it had been in some financial difficulty, Comfort would have known of this at the time it engaged OGSP as a sub-contractor. The Court of Appeal in W Y Steel noted at [70] that it was relevant “whether the claimant’s financial distress was, to a significant degree, caused by the respondent’s failure to pay the adjudicated amount and, also, whether the claimant was already in a similar state of financial strength or weakness (as the case may be) at the time the parties entered into their contract”. In this case, even if OGSP could be considered financially weak, this had already been its financial position in October 2013 according to Comfort’s own evidence and Comfort must be taken to have engaged OGSP as its sub-contractor with that knowledge. The Court of Appeal in W Y Steel made a similar finding at [72]:
The court concluded that W Y Steel could not rely on Osko’s financial distress because it had already known of Osko’s situation at the time it engaged the latter. For the same reasons, I rejected Comfort’s submissions that the court should exercise its discretion to stay enforcement of the AD pending appeal.
Conclusion
- [53]
[53] In summary, I was satisfied that the adjudicator found no patent errors before he made the AD. There was also no evidence to suggest that there was fraud in PC12. Accordingly, I dismissed Comfort’s application to set aside the AD in SUM 2425. In the meantime, Comfort had taken out Suit No 509 of 2017 against OGSP, Pintu and SS Mechanical for loss and damage arising from OGSP’s alleged breaches of the Contract and the purported conspiracy between OGSP, Pintu and SS Mechanical.