para
Introduction
[2026] SGHC 67
General Division of the High Court of Singapore31 Mar 2026Originating Application No 1062 of 2025
Published judgment text with court metadata, source links, and stable paragraph anchors.
Cited in 1 later decision. No negative treatment detected.
Citations and treatment detected automatically from later judgments and the authorities this decision relies on.
Later cases and laws citing this decision
“65 [2026] SGHC 67.”
Earlier cases and laws this decision relies on
“(a) the Employer is precluded by Art 16(3) of the UNCITRAL Model Law and/or s 10 of the International Arbitration Act 1994 (“IAA”) from challenging the Tribunal’s jurisdiction in court, for it failed to apply to court for a decision on jurisdiction within the time allowed by those provisions;”
“e general rule is displaced, and a precondition to arbitration is a matter of jurisdiction rather than admissibility. This is also how the Hong Kong Court of Final Appeal expressed the point in C v D [2023] HKCFA 16 at [47]–[50].”
“The Employer cites COT v COU [2023] SGHC 69 (“COT”) for the propositions that “[a] closing submission should not generally … advance a case which falls outside the pleadings” (at [179]) and if it does then “it is open to that party to seek to”
“In DRO v DRP [2025] SGHC 255 (“DRO”), the General Division of the High Court did not, however, regard Lufthansa to be binding authority on the distinction between admissibility and jurisdiction. The court pointed out (DRO at [59”
Auto-detected from judgment text; not a substitute for a citator check.
para
Introduction
1
The parties were, respectively, Employer and Contractor under a design and build contract (the “Contract”) for certain works in relation to a railway project. Disputes arose between them, which were referred by the Contractor to arbitration (the “Arbitration”) before a three-member tribunal (the “Tribunal”) comprising Sir Antony Edwards-Stuart (presiding), Mr Edwin Glasgow CBE, QC, and Mr Harish Salve QC.
2
The Arbitration culminated in an Award dated 2 April 2025, following which the Tribunal issued a Decision and Addendum on 25 June 2025. The Award, as revised by the Decision and Addendum, awarded a sum of money to the Contractor.
3
On 25 September 2025, the Employer applied to court to set aside the Award and the Decision and Addendum on two grounds:
para
(a) the Tribunal lacked jurisdiction; and
para
(b) the Tribunal breached natural justice in relation to four aspects of the Award.
4
I address these grounds in turn.
para
Jurisdiction
para
Overview
5
Clause 20 of the General Conditions of Contract (“GCC”) – set out below at [97] – prescribes a procedure to be followed before a dispute is referred to arbitration.
6
In the Arbitration, the Employer contended that the Contractor had not followed that pre-arbitral procedure before commencing the Arbitration, and so the Tribunal had no jurisdiction.
7
The Tribunal dealt with the Employer’s jurisdictional objections as a preliminary question, and ruled in Procedural Order No 5 (“PO5”) that the pre-arbitral procedure had been complied with, thus rejecting the Employer’s jurisdictional objections.
8
The Contractor contends that the Award cannot now be set aside for lack of jurisdiction, because:
para
(a) the Employer is precluded by Art 16(3) of the UNCITRAL Model Law and/or s 10 of the International Arbitration Act 1994 (“IAA”) from challenging the Tribunal’s jurisdiction in court, for it failed to apply to court for a decision on jurisdiction within the time allowed by those provisions;
para
(b) after PO5, the Employer waived its right to challenge the Tribunal’s jurisdiction;
para
(c) the alleged non-compliance with pre-arbitral procedure is an issue of admissibility, not jurisdiction; and
para
(d) in any event, the Tribunal had correctly decided that the pre-arbitral procedure had been followed.
9
The Employer contends that:
para
(a) Art 16(3) of the Model Law and s 10(3) of the IAA do not apply, as the Tribunal did not rule “as a preliminary question that it has jurisdiction”, it was only in the Award that the Tribunal ruled on this;
para
(b) even if Art 16(3) of the Model Law and s 10(3) of the IAA apply, they do not preclude the Employer from applying to set aside the Award for the Tribunal’s lack of jurisdiction, although it had not applied to court under those provisions;
para
(c) the Employer’s jurisdictional objections go to the Tribunal’s jurisdiction, not just admissibility of the claims in the Arbitration, and so the court can review the Tribunal’s decision; and
para
(d) the Tribunal was wrong in deciding that it had jurisdiction.
10
I thus address:
para
(a) whether Art 16(3) of the Model Law and s 10(3) of the IAA apply in this case;
para
(b) whether Art 16(3) of the Model Law and s 10(3) of the IAA have general preclusive effect;
para
(c) whether the Employer waived its jurisdictional objections after PO5;
para
(d) whether the Employer’s jurisdictional objections go towards jurisdiction or admissibility; and
para
(e) in any event, whether the tribunal correctly ruled that it had jurisdiction.
para
Art 16(3) of the Model Law and s 10(3) of the IAA
11
Section 3 of the IAA provides that, subject to the IAA, the Model Law, with the exception of Chapter VIII, has the force of law in Singapore.
12
Chapter IV of the Model Law, on “Jurisdiction of Arbitral Tribunal”, contains Art 16:
13
The court referred to in Art 16(3) of the Model Law is the General Division of the Singapore High Court, as stipulated in s 8 of the IAA.
14
Sections 10(1)–(5) of the IAA provide as follows:
para
Do Art 16(3) of the Model Law and s 10(3) of the IAA apply in the present case?
15
The Employer says that Art 16(3) of the Model Law and s 10(3) of the IAA do not apply in the present case, as the Tribunal did not rule “as a preliminary question that it has jurisdiction”, the Employer says that it was only in the Award that the Tribunal ruled on this.
16
The Employer does not dispute that it had raised a “plea that the arbitral tribunal does not have jurisdiction” for the purposes of Art 16(3) of the Model Law and s 10(3) of the IAA; its point is that the Tribunal did not rule on this as a preliminary question, but only in the Award.
17
The Employer recognises that the Tribunal had made a decision on jurisdiction in PO5 but argues that that did not “finally” decide the Employer’s jurisdictional objections. This contention is, however, contrary to the record, and I reject it.
18
On 28 December 2021, the Tribunal issued Procedural Order No 2 (“PO2”), provisionally directing that there was to be a determination of the preliminary issues set out in PO2, including:
19
The Tribunal framed as preliminary issues for determination, whether it had jurisdiction to determine Disputes 1 to 4, and Disputes 5 to 6 (the six disputes before it), with various sub-issues.
20
On 14 July 2022, by Procedural Order No 4 (“PO4”), the Tribunal gave directions for written submissions, reply submissions, and brief skeleton arguments on the preliminary issues, and fixed a hearing on 1 September 2022.
21
At that hearing, the Tribunal heard oral submissions from the parties’ counsel, and on 16 September 2022 the Tribunal gave its decision on the preliminary issues by PO5, providing its answers to the preliminary issues set out in PO2, as follows:
22
By PO5, the Tribunal expressly decided that Disputes 1 to 6 were all admissible in the Arbitration and that the Tribunal had jurisdiction to determine those disputes:
para
(a) for Disputes 1 to 6, that was decided on the basis that the Contractor had complied with the pre-arbitration procedure and so was entitled to refer Disputes 1 to 4 to the Arbitration;
para
(b) for Disputes 5 to 6, that was decided on the basis of the answers in relation to Disputes 1 to 4 and the concession by the Employer’s counsel (which I discuss below at [110]).
23
There is nothing in PO5 or the Tribunal’s reasons (attached to PO5) (“PO5 Reasons”) that supports the Employer’s contention that the Tribunal’s decision that it had jurisdiction did not “finally” decide the Employer’s jurisdictional objections.
24
The Employer points to its own Amended Statement of Defence (“Amended Defence”) filed on 7 July 2023, after PO5, in which it purported to maintain its jurisdictional objections:
25
The Employer could not, however, by purporting to maintain jurisdictional objections which the Tribunal had already dismissed by PO5, change the fact that its jurisdictional objections had been dismissed.
26
The Employer also points to the Award, in which the Tribunal reiterated its dismissal of the Employer’s jurisdictional objections, but that too does not help the Employer.
27
At [68] of the Award the Tribunal set out the awards and declarations the Employer sought, per its Answer to the Request for Arbitration (which preceded PO5), including (at (a)): “That this Arbitral Tribunal lacks jurisdiction to adjudicate on the Claimant’s reference being premature and in violation of mandatory pre-arbitration procedure in the Contract”.
28
However, the Tribunal went on to say the following (at [69] and [77]):
29
The Tribunal’s primary position, as stated in [69(c)] of the Award, was that “the challenge to the jurisdiction of the Tribunal was determined and rejected by PO5”. Indeed, from the procedural history and PO5 itself, I agree that that is so.
30
The Tribunal then put forward an alternative secondary position, that if the challenge to the Tribunal’s jurisdiction had not been determined and rejected by PO5, the Tribunal “hereby dismisses it”. That was the context in which (at [77] of the Award) the Tribunal referred to PO5 and the PO5 Reasons attached to it, said that those were to be treated as forming part of the Award, and attached PO5 to the Award as Annex 2.
31
In light of the above, the Employer’s contention that, by incorporating PO5 into the Award, the Tribunal only finally determined the issue of jurisdiction in the Award, is plainly incorrect: the Tribunal expressly said at [69(c)] that it had already determined and rejected the Employer’s jurisdictional challenge by PO5, as indeed the Tribunal had.
32
The Employer also takes issue the Tribunal’s statement in [69(b)] of the Award “that no further submissions were made about the Tribunal's lack of jurisdiction” and the Tribunal’s statement in [69(c)] of the Award that after PO5, the Employer’s jurisdictional challenge was “not pursued”. The Employer points to its Amended Defence where it had maintained its jurisdictional objections, as well as its Written Closing Submissions (“WCS”) to the same effect.
33
This too does not help the Employer surmount the hurdle that the Tribunal had dismissed its jurisdictional objections by PO5. The Tribunal’s characterisation of the Employer’s purported maintaining of its jurisdictional objections thereafter cannot change the effect of PO5. In any event, at [69(a)] of the Award the Tribunal had noted that the Employer purported to maintain its jurisdictional objections after PO5. In that context, when the Tribunal said at [69(b)] of the Award that “no further submissions were made about the Tribunal's lack of jurisdiction”, that simply meant that no new submissions were put forward by the Employer, beyond those put forward up to the time of PO5. Indeed, after PO5 the Employer simply purported to maintain its jurisdictional objections, and to reiterate what it had already submitted (which the Tribunal had already considered and dismissed by PO5).
34
For completeness, in so far as the Tribunal put forward (as an alternative) a secondary position that if the Employer’s jurisdictional objections has not been determined and rejected by PO5, the Tribunal “hereby dismisses it” ( at [69(c)] of the Award), that does not revive the Employer’s right to apply to set aside the Award on jurisdictional grounds, if that right had already been lost because Art 16(3) of the Model Law and s 10(3) of the IAA have general preclusive effect (which I discuss below at [39]).
35
As I mentioned above, I agree with the Tribunal’s primary position that it had by PO5 determined and rejected the Employer’s jurisdictional objection. Accordingly, the alternative secondary position does not arise.
36
In the present case, the Tribunal dealt with the Employer’s jurisdictional objections as a preliminary question, and ruled as a preliminary question that it had jurisdiction. Accordingly, Art 16(3) of the Model Law, and s 10(3) of the IAA, apply in the present case.
para
Do Art 16(3) of the Model Law and s 10(3) of the IAA have general preclusive effect?
37
The Employer did not, however, apply to court within 30 days (or at all) to challenge the Tribunal’s decision in PO 5, by which the Tribunal had ruled as a preliminary question that it had jurisdiction. Instead, the Employer continued to participate in the arbitration until the Award was issued, and then it applied to set aside the Award on grounds including that the Tribunal had no jurisdiction.
38
The Contractor contends that Art 16(3) of the Model Law and/or s 10(3)(a) of the IAA have general preclusive effect, and in the circumstances of the present case the Employer cannot now challenge the Tribunal’s jurisdiction and so set aside the Award. The Employer contends that those provisions do not have any preclusive effect.
39
In Rakna Arkshaka Lanka Ltd v Avant Garde Maritime Services (Pte) Ltd [2019] 2 SLR 131 (“Rakna”), the appellant Rakna applied to set aside an award on the basis that the tribunal had no jurisdiction. It failed at first instance but succeeded on appeal. The Court of Appeal found that Art 16(3) of the Model Law had general preclusive effect, but not against a non-participating respondent like Rakna. Accordingly, Rakna was allowed to challenge the tribunal’s jurisdiction before the court for the purposes of its setting-aside application, and that jurisdictional challenge succeeded.
40
The Employer contends that the Court of Appeal’s decision in Rakna that Art 16(3) has general preclusive effect was merely obiter dicta as the case involved a non-participating respondent, whereas here the Employer participated in the Arbitration.
41
The same contentions – that the finding in Rakna as to the general preclusive effect of Art 16(3) was obiter, and the point should be decided differently – were put forward in Republic of Korea v Mason Capital LP [2025] 4 SLR 308 (see [80], [110]–[113] at [113] of the judgment) but the Singapore International Commercial Court found it unnecessary to decide the point, as it considered the jurisdictional objection to lack substantive merit.
42
My decision is:
para
(a) the Court of Appeal’s reasoning in Rakna that Art 16(3) of the Model Law has general preclusive effect is part of the ratio decidendi of the case, and as such is binding on me; and
para
(b) in any event, if I were not bound by Rakna, I would still, with respect, follow the reasoning of the Court of Appeal and likewise conclude that Art 16(3) of the Model Law has general preclusive effect.
43
In Rakna, the first instance judge had held as follows (as summarised in Rakna at [32]):
para
(a) the tribunal had ruled on jurisdiction as a preliminary issue (thus bringing into play Art 16(3) of the Model Law and s 10(3) of the IAA);
para
(b) Art 16(3) of the Model Law and s 10(3) of the IAA had preclusive effect, in that a party who had failed to challenge such a ruling on jurisdiction within the prescribed 30 day period could not thereafter raise the same jurisdictional challenge to set aside an award; and
para
(c) that preclusive effect applied equally to a non-participating respondent.
44
On appeal, Rakna argued against all three aspects of the first instance decision as summarised above (Rakna at [33]):
para
(a) first, that the tribunal had not made a preliminary ruling on jurisdiction, and so Art 16(3) of the Model Law and s 10(3) of the IAA did not apply;
para
(b) second, if that had been such a preliminary ruling, Art 16(3) of the Model Law and s 10(3) of the IAA did not have preclusive effect;
para
(c) third, even if preclusion applied, it would not apply to a non-participating respondent like Rakna.
45
In the event, the Court of Appeal found in Rakna’s favour only on its third argument – that a non-participating respondent who had not brought a court challenge against a tribunal’s preliminary ruling on jurisdiction, was not precluded from challenging jurisdiction so as to set aside an award: Rakna at [72]–[79].
46
The Court of Appeal did not, however, simply decide in favour of Rakan on that argument, and so not reach a decision on Rakna’s first and second arguments: instead, it reached a reasoned decision against Rakna on those arguments:
para
(a) it reviewed the nature of Rakna’s jurisdictional challenge in the arbitration, and the character of the order made by the tribunal, and held that the tribunal had ruled on jurisdiction as a preliminary issue (at [55]–[59]); and
para
(b) it analysed the effect of Article 16(3) of the Model Law and held that it had general preclusive effect (at [60]–[77], see also [47]–[54]).
47
Rakna was allowed to assert lack of jurisdiction for the purposes of its setting-aside application, because the court held that Art 16(3) of the Model Law and s 10(3) of the IAA applied, and that Art 16(3) of the Model Law and s 10(3) of the IAA had general preclusive effect, but that such preclusion did not apply to a non-participating respondent like Rakna.
48
A useful test for determining ratio decidendi is that stated in Cross & Harris, Precedent in English Law, 4th Ed (1991), p 72: “The ratio decidendi of a case is any rule of law expressly or impliedly treated by the judge as a necessary step in reaching his conclusion, having regard to the line of reasoning adopted by him.” The English Court of Appeal used that test in R (Kadhim) v Brent Housing Board [2001] 2 SLR 1674 at [16]–[17] to determine what the ratio decidendi of a previous English Court of Appeal decision was.
49
Applying this test, the Court of Appeal’s holding that Art 16(3) of the Model Law and s 10(3) of the IAA have general preclusive effect was expressly treated by the court as a necessary step in reaching its conclusion, having regard to the line of reasoning adopted by the court.
50
The Court of Appeal did not leave open the point of whether Art 16(3) of the Model Law and s 10(3) of the IAA had general preclusive effect: the court decided that those provisions did have general preclusive effect; and it further decided that, as an exception to that general position, a non-participating respondent was not precluded from applying to set aside an award for lack of jurisdiction: Rakna at [54].
51
It is also instructive to consider how the Court of Appeal in Rakna dealt with its previous decision in PT First Media TBK v Astro Nusantara International BV [2014] 1 SLR 372 (“Astro”).
52
In Astro, the court decided that Art 16(3) of the Model Law did not preclude a respondent from challenging enforcement of a Singapore award (a “passive remedy”) on jurisdictional grounds, although that respondent had not pursued the active remedies of challenging jurisdiction in court pursuant to Art 16(3) of the Model Law or applying to set aside the award. The court expressed the tentative view (at [132]) that “the position might not be the same in relation to whether such a party may raise such a ground to initiate setting aside proceedings under Art 34”, and moreover (at [130]) that the court would be “surprised if a party retained the right to bring an application to set aside a final award on the merits under Art 34 on a ground which they could have raised via other active remedies before the supervising court at an earlier stage when the arbitration process was still ongoing.”
53
In Rakna at [65] the Court of Appeal said this of Astro:
54
At [68] of Rakna, the court added:
55
Notably, the Court of Appeal in Rakna did not characterise as obiter its own decision on the general preclusive effect of Art 16(3) of the Model Law (and s 10(3) of the IAA) on setting-aside applications. Rakna sought to avoid preclusion by arguing (i) that the provisions had no preclusive effect; and (ii) that even if they had general preclusive effect, as an exception preclusion did not apply to a non-participating respondent. If either argument succeeded, Rakna would avoid preclusion. In the event, the court decided against Rakna on argument (i), but for Rakna on argument (ii).
56
The Employer contends that the reasoning in Rakna on the preclusive effect of Art 16(3) of the Model Law (and s 10(3) of the IAA) is obiter because that case concerned a non-participating respondent, whereas the Employer here participated in the arbitration. I do not agree that Rakna can be distinguished in this way: the Court of Appeal specifically decided that Art 16(3) of the Model Law (and s 10(3) of the IAA) had general preclusive effect, in rejecting Rakna’s argument that they had no preclusive effect, and this was treated by the court as a necessary step in reaching its conclusion, having regard to the line of reasoning adopted, ie, Art 16(3) of the Model Law (and s 10(3) of the IAA) had general preclusive effect, but there was an exception for non-participating respondents like Rakna.
57
I thus consider myself bound by the reasoning in Rakna that Art 16(3) of the Model Law and s 10(3) of the IAA have general preclusive effect, in that a party who had failed to challenge such a preliminary ruling on jurisdiction within the prescribed 30-day period generally cannot thereafter raise the same jurisdictional challenge to set aside an award. As the Employer participated throughout the Arbitration, the “non-participating respondent” exception which availed Rakna does not help the Employer. It follows that the Employer is precluded from seeking to set aside the Award for lack of jurisdiction.
58
In any event, if I were not bound by virtue of Rakna to hold that Art 16(3) of the Model Law and s 10(3) of the IAA have general preclusive effect, I would nevertheless, with respect, follow the Court of Appeal’s decision and reach the same conclusion.
59
The Employer contends that its position is supported by the express wording of Art 16 of the Model Law, the travaux préparatoires, and policy considerations. However, the Court of Appeal in Rakna had considered the express wording of Art 16 of the Model Law, the travaux préparatoires, and policy considerations, in arriving at the opposite conclusion.
60
The Employer points to the phrase “may request” in Art 16(3) and the lack of stipulated consequences if such a request is not made, and argues this indicates that Art 16(3) is permissive. The same point was addressed in Rakna at [68] where the court said that the permissive interpretation of Art 16(3) as only one remedy available to the parties, was explained in Astro at [119], but “no great weight is placed on the wording of the provision”, and in any event, the view expressed in Astro was that the court would be surprised if a party retained the right to apply to set aside an award on jurisdictional grounds on which it could have brought a court challenge under Art 16(3) but did not.
61
The court in Rakna went on at [69] to cite Nata Ghibradze’s article, “Preclusion of Remedies under Article 16(3) of the UNTITRAL Model Law” 27 Pace International Law Review 345 (2015). The court noted that the article undertook a wide-ranging review of the traveaux, literature, and case law relevant to Art 16(3) and its meaning, and that the author observed that “many courts and the greater part of the legal scholarship support the preclusive effect of Art 16(3)”.
62
At [70] of Rakna, the court also cited Gary Born, International Commercial Arbitration, at p 1106 for the view that “the only exception to the requirement that a party must challenge the arbitrator’s positive jurisdictional ruling under Art 16(3), ‘is where a party does not participate at all in the arbitral proceedings; in this instance, the Singaporean court would permit a challenge to a final arbitral award under Article 34 of the Model Law’”. Further, the court cited Robert Merkin and Johanna Hjalmarsson, Singapore Arbitration Legislation Annotated (Informa, 2nd Ed, 2016) at pp 148–149 for the similar view that a party “may simply refuse to have anything to do with the arbitration, in which case he has the right to await the award itself and then challenge it under Model Law, Art 34”.
63
The Employer does not directly confront the observation in Rakna at [69] that many courts and the greater part of the legal scholarship support the preclusive effect of Art 16(3); nor does the Employer directly confront the other commentaries cited in Rakna at [70]. Instead, the Employer puts forward views to the contrary, which are minority views.
64
In particular, the Employer cites Shaun Pereira, “Deferred Challenges to Jurisdiction Under the Model Law” (2018) 35(6) Journal of International Arbitration 719, an article published after Astro and the first instance decision in Rakna, but before the Court of Appeal’s decision in Rakna. Pereira suggests that one would have expected clearer and more express indications in Art 16(3) to the effect that its inclusion was intended to upend the fundamental architecture of the Model Law, a cornerstone of which is the curial court’s supervision over arbitral awards on the grounds set out in Article 34(2).
65
With respect, the court in Astro at [130] had already observed that the supervisory court exercises control at two points in time: immediate court control over pending arbitration proceedings (such as on an application under Art 16(3) of the Model Law) and delayed court control over the arbitration award. Interpreting Art 16(3) as having general preclusive effect does not deprive the supervisory court of the right to exercise court control on the issue of jurisdiction: it simply means that where Art 16(3) is triggered, the dissatisfied party must seek immediate court control, rather than simply continue participating in the arbitration only to apply to set aside the award thereafter (on the same issue of jurisdiction).
66
Pereira also argues that if Art 16(3) of the Model Law is regarded as having preclusive effect, there would be an unwarranted asymmetry in the availability of appellate review of a first instance court decision, in that Art 16(3) provides that the first instance court’s decision “shall be subject to no appeal”, whereas there is no equivalent stipulation in Art 34 in relation to setting-aside.
67
This asymmetry is evident on the face of the Model Law, but that did not move “many courts and the greater part of the legal scholarship”, or the Court of Appeal in Astro and Rakna, away from the view that Art 16(3) has general preclusive effect in relation to a later setting-aside application on the same jurisdictional ground.
Costs
There is moreover a good policy reason for the asymmetry. In the context of Art 16(3) of the Model Law, there is still a pending arbitration, indeed one that can continue while an application to court is still pending. Allowing an unrestricted right to appeal the first instance decision would mean that the arbitration might proceed for an even longer period before the issue of jurisdiction is finally determined: that would risk greater wastage of time and costs if the court were eventually to decide that the tribunal had no jurisdiction.
69
As the court in Astro observed at [130]:
70
The 30-day timeline under both Art 13(3) and 16(3) of the Model Law is stricter than the 3 months allowed in Art 34 on setting-aside, consonant with the former provisions dealing with a challenge while the arbitration is pending, whereas a setting-aside application is brought when the arbitration has culminated in an award. It is likewise consonant for there to be a restriction on rights of appeal where the court is addressing a pending arbitration, rather than an arbitral award. Indeed, Art 13(3) on challenging an arbitration has the same restriction as does Art 16(3) on jurisdictional challenges: the Model Law stipulates that the first instance court decision “shall be subject to no appeal”. Section 10(4) of the IAA has relaxed the position slightly in relation to jurisdictional challenges, in that an appeal against a first instance court decision under Art 16(3) may be brought with the permission of the appellate court: s 10(4). Even so, the Singapore legislature has still decided to place some restriction on appeal rights in the case of immediate court control in relation to a pending arbitration (under Art 16(3) or s 10) as permission from the appellate court must still be sought, as compared to delayed court control in relation to an arbitral award (under Art 34) where neither the Model Law nor the IAA places any restriction on an appeal.
71
As for policy reasons, the court in Rakna stated at [72]:
72
The court went on at [75] to consider the position of a respondent (like the one in Astro) who had failed in its jurisdiction objection then participates in the arbitration; the court said:
73
Thus, even if I were not bound by the reasoning in Rakna to hold that Art 16(3) of the Model Law and s 10(3) of the IAA have preclusive effect in relation to a setting-aside application on the same jurisdictional ground (that could have been pursued under those provisions, but was not) I would still have reached the same conclusion.
74
It follows that I consider that the Employer (who was not a non-participating respondent like Rakna) is precluded from seeking to set aside the award on its jurisdictional challenge. It ought to have brought that to court within 30 days, pursuant to Art 16(3) of the Model Law and/or s 10(3) of the IAA; not having does so, it cannot now rely on the same as a ground to set aside the Award.
para
Did the Employer waive its jurisdictional objections after PO5?
75
The Contractor argues that even if Art 16(3) of the Model Law and/or s 10(3) of the IAA did not preclude the Employer from challenging jurisdiction again, the Employer had waived its right to do so by its conduct after PO5.
76
I do not accept this. As I noted above at [24]–[33], the Employer purported to maintain its jurisdictional objections even after the Tribunal had dismissed those by way of PO5. It was futile for the Employer to continue taking the position that the Tribunal had no jurisdiction, whilst not applying for the court to determine that pursuant to Art 16(3) of the Model Law and/or s 10(3) of the IAA. Be that as it may, the Employer’s conduct in the arbitration does not amount to a waiver of its jurisdictional objections: the Employer continued to say that the Tribunal had no jurisdiction. As for the Employer’s failure to apply to court under Art 16(3) of the Model Law and/or s 10(3) of the IAA, I view that as giving rise to preclusion as discussed in the previous section, rather than as a waiver.
para
Do the Employer’s jurisdictional objections go towards jurisdiction or admissibility?
77
The Contractor says that the Employer’s jurisdictional objections (based on non-compliance with pre-arbitral procedure) go towards the admissibility of the Disputes which the Contractor referred to the Arbitration, rather than towards the jurisdiction of the Tribunal. The Employer says that its jurisdictional objections go towards the Tribunal’s jurisdiction, and not admissibility.
78
The Employer relies on International Research Corp PLC v Lufthansa Systems Asia Pacific Pte Ltd [2014] 1 SLR 130 (“Lufthansa”) at [54]–[63] as Court of Appeal authority that non-compliance with pre-arbitral procedure goes towards a tribunal’s jurisdiction.
79
In Lufthansa at [35]–[53], the court held that:
80
The court went on to say at [53], “This is sufficient to dispose of the matter in the Appellant’s favour, but we comment on the remaining issues as they are of some importance.” From that alone, one might have thought that the court’s “comments” on the remaining issues were going to be obiter. However, after discussing non-compliance with of pre-arbitral procedure at [54]–[62], the court stated its “ruling” at [63]:
81
The court’s reference to its “ruling” on non-compliance with pre-arbitral procedure as the “second ground” on which the appeal was allowed, points to that ruling being part of the ratio decidendi rather than obiter.
82
In DRO v DRP [2025] SGHC 255 (“DRO”), the General Division of the High Court did not, however, regard Lufthansa to be binding authority on the distinction between admissibility and jurisdiction. The court pointed out (DRO at [59]) that this was not argued in Lufthansa – it was not one of the issues that the court had to decide (as set out in Lufthansa at [16]), instead, the court in Lufthansa proceeded on the uncontested premise that non-compliance with pre-arbitral procedure was a matter going to jurisdiction. Thus, the court in DRO concluded at [59] that Lufthansa was not binding authority that non-compliance with pre-arbitral procedure was a matter going to jurisdiction.
83
The court went on to hold (DRO at [60]–[63]) that non-compliance with pre-arbitral procedure should be treated as a matter of admissibility rather than jurisdiction. The court cited BTN v BTP [2021] 1 SLR 276 (“BTN”), a decision of the Court of Appeal subsequent to Lufthansa. In BTN, the distinction between admissibility and jurisdiction was expressly discussed, whereas it was not in Lufthansa. The court in BTN decided that a tribunal’s decision on the res judicata effect of a prior decision is a decision on admissibility, not jurisdiction.
84
In arriving at that decision, the court at [70]–[71] approved of Jan Paulsson commentary on Jurisdiction and Admissibility:
85
However, the court in DRO stated at [61]:
para
(a) the issue in BTN concerned whether a tribunal’s decision on the res judicata effect of a prior decision went to admissibility or jurisdiction, and not preconditions to arbitration;
para
(b) the court in BTN did not have to decide whether a condition precedent to arbitration is a matter of admissibility;
para
(c) thus, the court’s approval of Jan Paulsson’s view that the fulfilment of conditions precedent / preconditions to arbitration was a matter of admissibility, was obiter.
86
The court in DRO went on to decide at [62]–[63] that a precondition to arbitration is a matter that goes to admissibility and not jurisdiction, for the reasons summarised at [63]:
para
(a) in principle, this is consistent with the distinction between jurisdiction (ie, the power of the tribunal to hear a case) and admissibility (ie, whether it is appropriate for the tribunal to hear it): see BTN at [68];
para
(b) the Court of Appeal in BTN has approved of this view, albeit obiter; and
para
(c) this would be in line with the general consensus in international arbitration that preconditions to arbitration should be treated as matters of admissibility rather than jurisdiction, and there is no reason why Singapore should adopt a contrary position.
87
I respectfully agree with the reasoning and conclusion in DRO that Lufthansa is not binding authority on (a) the distinction between admissibility and jurisdiction, or (b) that non-compliance with pre-arbitral procedure was a matter going to jurisdiction: see [82] above. I also agree that a precondition to arbitration (such as compliance with pre-arbitral procedure) is generally a matter of admissibility rather than jurisdiction: [83]–[86], save that I would couch this as a general proposition, because there may be cases where the general rule is displaced, and a precondition to arbitration is a matter of jurisdiction rather than admissibility. This is also how the Hong Kong Court of Final Appeal expressed the point in C v D [2023] HKCFA 16 at [47]–[50].
88
In C v D, Justice Ribiero stated that:
para
(a) Parties could expressly agree that compliance with a pre-arbitration condition is amenable to review by the court, and if so, that would resolve the issue of reviewability (at [47]).
para
(b) The court would only reach that conclusion if there is unequivocally clear language to that effect, for “it would be contrary to all normal expectations to find that such was the parties’ intention. They have opted to submit their disputes to an arbitral tribunal rather than a court for resolution. It would be surprising to discover that they intend to have a court involved and to undergo two rounds of decision-making to determine whether a pre-arbitration condition has been met.” (At [48].)
para
(c) Gary Born’s commentary in International Commercial Arbitration, Vol 1: International Arbitration Agreements (Wolters Kluwer, 3rd ed, 2020) at p 1000 expresses the view that pre-arbitration conditions should be regarded as presumptively non-jurisdictional (at [49]).
para
(d) “Such a presumption is consistent with the consensual basis of the tribunal’s jurisdiction: in the absence of unequivocal language to the contrary, an objection to how the tribunal has resolved an issue concerning a pre-arbitration condition does not challenge the tribunal’s authority to arbitrate conferred by the parties’ consent.” (At [50].)
89
That the distinction between jurisdiction and admissibility may vary from case to case, is also illustrated by the decision in Swissbourgh Diamond Mines (Pty) Ltd v Kingdom of Lesotho [2019] 1 SLR 263(“Swissbourgh”). In that case, the court noted at [206] that the failure to exhaust local remedies has traditionally been regarded by international courts as a matter that goes towards the admissibility of the claim, and not the jurisdiction of the tribunal. However, at [209] the court considered that the state in question had made exhaustion of local remedies a pre-condition for its consent to arbitration, and so the court found that failure to exhaust local remedies should be taken to be an issue concerning the jurisdiction of the tribunal.
90
Swissbourgh, though, concerned a state making an offer to arbitrate, which an investor could accept on the terms of the offer, thus forming an arbitration agreement. The present case is different: it is between two commercial parties, not an investor and a state; and there is already an arbitration agreement between the parties based on the FIDIC form, specifically in Clause 20 with a provision for arbitration in Sub-Clause 20.6
91
Returning to DRO, the Employer seeks to distinguish that case on the basis that the arbitration clause there did not make it clear that compliance with pre-arbitral procedure was a condition precedent to arbitration. The court in DRO did indeed find that there were no clear words creating a condition precedent to arbitration (at [69]–[76]). However, this finding was separate from and subsequent to the court’s finding at [58]–[63] that a precondition to arbitration was a matter going to admissibility and not jurisdiction. Thus, the court summed up its decision at [100] by saying at (b) that “In my view, conditions precedent to arbitration are matters going to admissibility”, followed by (c) that “In any event, cl 25.7 of the Contract is not a condition precedent.” Whether the clause was a condition precedent was thus a separate matter from the court’s reasoning and conclusion on admissibility versus jurisdiction.
92
The Employer also seeks to distinguish DRO on the basis that the pre-arbitral procedure there involved negotiation steps, whereas that in the present case involves a potentially binding adjudicative reference to a DAB. I do not agree that this difference justifies me reaching the conclusion that the pre-arbitral procedure in the present case goes towards jurisdiction rather than admissibility.
93
The pre-arbitral procedure in the present case does involve reference to a DAB, rather than just negotiation steps. However, Sub-Clause 20.4 provides that “The decision [of the DAB] shall be binding on both Parties, who shall promptly give effect to it unless and until it shall be revised in an amicable settlement or an arbitral award as described below.” [Emphasis added.] A party dissatisfied with a DAB’s decision may give notice of dissatisfaction as further provided in Sub-Clause 20.4, and after allowing for a period for parties to attempt to settle the dispute amicably, arbitration may be commenced. In other words, a DAB’s decision remains binding only if the matter is not otherwise settled between the parties, no notice of dissatisfaction is duly given, or no arbitration is duly commenced. It is arbitration, rather than reference to a DAB, that ultimately decides a dispute between the parties, if either party does not accept the DAB’s decision, and they do not settle the matter amicably. That leaves the case squarely within the general rule that pre-arbitral procedure is generally a matter going to admissibility rather than jurisdiction. As the court observed in C v D (see [88(b)] above), having agreed to submit their disputes to arbitration rather than to a court, the parties likely intended for the arbitral tribunal to resolve any dispute over compliance with pre-arbitral procedure, rather than to have a further round of decision-making before a court to resolve that dispute.
94
The Employer also cited Christopher R Seppala, Arbitration Clause in FIDIC Contracts for Major Works, The International Construction Law Review, Vol 22, Part 1, January 2005 for the proposition that if a dispute submitted to arbitration has not gone through the prescribed pre-arbitral process, the arbitrators “will be exceeding their jurisdiction”. However, that commentary does not refer to, let alone discuss, the admissibility/jurisdiction distinction; it is more than 20 years old, pre-dating the Singapore cases that have discussed this issue, such as Swissbourgh, BBA v BAZ [2020] 2 SLR 453 (“BBA”), BTN, and DRO. With respect, this commentary does not assist me on the issue.
95
I consider the general rule to apply in the present case, and thus regard the Employer’s jurisdictional challenge (based on non-compliance with pre-arbitral procedure) to go towards admissibility of the claims that the Contractor submitted to the Arbitration, rather than towards the jurisdiction of the Tribunal. Accordingly, the Tribunal’s decision on the Employer’s jurisdictional challenge was a decision on admissibility, which the court cannot review: BBA at [73]; BTN at [68]).
para
Did the Tribunal correctly decide that it had jurisdiction?
96
In any event, the jurisdictional ground of the Employer’s setting-aside application fails because I consider that the Tribunal had correctly decided that it had jurisdiction.
97
The contract, based on the FIDIC form, had a multi-tiered dispute resolution mechanism in Clause 20 of the GCC, save that Sub-Clause 20.6 was amended by the Particular Conditions of Contract:
para
(a) Sub-Clause 20.2 (Appointment of the Dispute Adjudication Board) provides that:
para
(b) Sub-Clause 20.3 (Failure to Agree Dispute Adjudication Board) addresses the possible failure to agree on a DAB, and related matters.
para
(c) Sub-Clause 20.4 (Obtaining Dispute Adjudication Board’s Decision) provides that:
para
(d) Sub-Clause 20.5 (Amicable Settlement) provides that:
para
(e) Sub-Clause 20.6 (Arbitration) – as per the Particular Conditions of Contract – provides that:
98
In the present case, a DAB was constituted and the Contractor referred a dispute (the “AEB dispute”) to it. Before the DAB gave its decision on the AEB dispute (and, as such, before the DAB’s appointment expired per Sub-Clause 20.2), the Contractor referred four other disputes to the DAB: Disputes 1 to 4, which it later referred to the Arbitration.
99
The DAB, however, declined to decide Disputes 1 to 4 on the basis that it had only been appointed for the AEB dispute. In the event, the DAB did not give its decision on Disputes 1 to 4 within 84 days of those disputes being referred to it, or at all. After 84 days had passed, the Contractor issued a notice of dissatisfaction, and a further 59 days later, the Contractor filed and served its Request for Arbitration on 18 December 2020.
100
There is no issue with the Contractor not observing the timelines in Clause 20, as such. The Employer’s objection, more fundamentally, is that the Contractor was not entitled to refer Disputes 1 to 4 to the DAB – it should have taken steps to have a new DAB appointed to decide those disputes – and so it was misconceived for the Contractor to have issued a notice of dissatisfaction in relation to the DAB not deciding Disputes 1 to 4, and thereafter to have commenced the Arbitration.
para
Disputes 1 to 4
101
The Tribunal decided that the Contractor was entitled to refer Disputes 1 to 4 to the DAB, and consequently the Contractor was entitled to have issued a Notice of Dissatisfaction when the DAB failed to give a decision on those disputes within 84 days, and the Contractor was entitled to have commenced the Arbitration when it had.
102
The Tribunal’s reasoning, which I agree with, was stated in the Tribunal’s PO5 Reasons at [25]–[30]:
103
The Employer argues that the DAB was not a standing DAB appointed for the duration of the project, but an ad hoc DAB whose appointment could expire before the end of the project; and more specifically, the DAB was appointed only to decide the AEB dispute (and so it could only decide that dispute)
104
Indeed, the DAB was not a standing DAB, it was an ad hoc DAB whose appointment could expire before the end of the project, but that does not avail the Employer. The DAB need not be a standing DAB for the Contractor to be able to refer other disputes to it: Clause 20 contemplates that other disputes may be referred to an ad hoc DAB before it has given its decision on the first dispute referred to it, and Sub-Clause 20.2 makes specific provision for the duration of the DAB’s appointment to be extended in that event (see [28] of the PO5 Reasons set out above).
105
As for the contention that the DAB was appointed only to decide the AEB dispute (and so it could only decide that dispute), the Dispute Adjudication Board Agreement does not support this. First, the fee structure in [3] is on a “per dispute” basis, “for each dispute referred”, which leaves open the possibility of further disputes being referred to the DAB. Second, clause 4(e) of the General Conditions of Dispute Adjudication Agreement (in the Appendix to the Dispute Adjudication Board Agreement) requires DAB members to “comply with the annexed procedural rules and with Sub-Clause 20.4 of the Conditions of Contract”, and rule 2 of the Procedural Rules states that “The DAB shall proceed in accordance with Sub-Clause 20.4 and these Rules.” [32] of the PO5 Reasons duly cites these provisions of the Dispute Adjudication Board Agreement.
106
If Sub-Clause 20.4 allowed the Contractor to refer other disputes to the DAB, then the DAB members were obliged to decide those other disputes, for Sub-Clause 20.4 obliged them to do so, and they had agreed to comply with it. The fact that there was only one dispute (the AEB dispute) when the DAB was appointed, and in that sense the DAB was appointed to decide that dispute, does not mean that it could only decide that dispute. Pursuant to Sub-Clause 20.4, which the DAB members agreed to comply with, other disputes could validly be referred to it (as the Tribunal decided, which I agree with).
107
Finally, the FIDIC Contracts Guide (1st Ed, 2000) supports the Tribunal’s interpretation. Commenting on the standard Sub-Clause 20.2, the Guide says at p 308:
108
The Guide says that a party wishing to refer a second dispute to an existing DAB should do two things. It then says that if that has been done, or “if the Party is reluctant to accept the delay involved in appointing another DAB”, that party is entitled to refer the second dispute to the same DAB, and the other party “cannot (under the Contract) prevent this reference to the same DAB”.
109
That is the position here: the Contractor did not wish to appoint an additional DAB (or DABs) for Disputes 1 to 4, and so it referred those disputes to the existing DAB: it was entitled to do so, as the Guide says, and as the Tribunal decided.
para
Disputes 5 to 6
110
The Contractor approached Disputes 5 to 6 differently from Disputes 1 to 4. With the DAB declining to decide Disputes 1 to 4 on the basis that it would only decide the AEB dispute (and the Employer agreeing with that), the Contractor did not refer Disputes 5 to 6 to the DAB (a referral it was entitled to make, as with Disputes 1 to 4). The Contractor simply submitted Disputes 5 to 6 to the Arbitration, along with Disputes 1 to 4.
111
The Tribunal decided that Disputes 5 to 6 were admissible in the Arbitration and that the Tribunal had jurisdiction to determine them, primarily based on a concession by the Employer’s counsel in the course of oral submissions, which the Tribunal summarised at [22] of the PO5 Reasons:
112
The transcript of the hearing bears out the concession by the Employer’s counsel:
113
The Employer’s counsel expressly conceded that if the Tribunal ruled against the Employer on Disputes 1 to 4 (such that Disputes 1 to 4 would continue in the Arbitration), then “it is sensible that 5 and 6 also goes to the Tribunal. We don’t say that it should go back to the DAB.”
114
Given the Employer’s counsel’s concession, the Employer’s jurisdictional objections to Disputes 5 to 6 would stand or fall with its jurisdictional objections to Disputes 1 to 4. With that concession, and with the Tribunal dismissing the Employer’s jurisdictional objections to Disputes 1 to 4, the Tribunal accordingly ruled as follows in relation to Disputes 5 to 6, and correctly so:
115
Although the concession by the Employer’s counsel coupled with the Tribunal’s decision on Disputes 1 to 4 was decisive of the jurisdictional objections to Disputes 5 to 6, in the PO5 Reasons the Tribunal gave further reasons for rejecting the jurisdictional objections to Disputes 5 to 6, at [33]–[40]:
116
In summary, the Tribunal decided that:
para
(a) in this case, for reasons accepted by the Employer’s counsel, the situation would become unworkable if a DAB were required to determine Disputes 5 to 6 whilst Disputes 1 to 4 were the subject of arbitration proceedings (at [34]);
para
(b) with the DAB’s wrongful refusal to accept the referral of Disputes 1 to 4, the dispute resolution machinery relating to the DAB broke down and/or became unworkable, and accordingly, the Contractor was entitled to refer not just Disputes 1 to 4, but also Disputes 5 to 6, to the Arbitration (at [35], [38]);
para
(c) in light of the DAB’s wrongful refusal to accept the referral of further disputes, the Contractor was relieved from having to refer Disputes 5 to 6 to the DAB, and could proceed to refer them to the Arbitration (at [35], [38], [39]).
117
I consider that the Tribunal was correct to reach these conclusions. I agree with the Contractor’s submission that if support were required from an express contractual provision, Clause 20.8 (Expiry of Dispute Adjudication Board’s Appointment) would supply that:
118
The phrase “there is no DAB in place, whether by reason of the expiry of the DAB’s appointment or otherwise” [emphasis added] aptly covers the situation where a DAB has wrongfully refused to accept the referral of further disputes (which were properly referred under Sub-Clause 20.4), and so (as the Tribunal found) the dispute resolution machinery relating to the DAB broke down and/or became unworkable. To require the Contractor to go through the motions of referring Disputes 5 to 6 to the DAB would be an exercise in futility; to require the Contractor to take steps to appoint another DAB would deprive the Contractor of its contractual right under Sub-Clause 20.4 to refer Disputes 5 to 6 to the DAB, for the DAB to decide. With the DAB refusing to accept referral of further disputes, “there is no DAB in place” within Sub-Clause 20.8.
119
For the above reasons, I decided that the Employer’s attempt to set aside the Award on jurisdictional grounds fails.
para
Natural Justice
120
The Employer applies to set aside the Award (or parts thereof) on the basis of alleged breaches of natural justice.
121
The Employer alleges four such breaches:
para
(a) in relation to Claim H4, the Tribunal adopted a methodology for computing the applicable cap for prolongation costs which was not pleaded by the parties, thereby depriving the Employer of a reasonable opportunity to be heard;
para
(b) the Tribunal failed to apply its mind to essential issues, having failed to consider:
para
(i) the Employer’s case on repudiatory breach under applicable legislation;
para
(ii) the Employer’s case that the Contractor could, and should, have pre-casted Location Box (“LB”) foundations, and that this caused the delay in the Works; and
para
(iii) the Employer’s evidence on whether the changes to the Auto Location Huts (“ALHs”) constituted variations for Claim H2.
122
I address these four complaints in turn.
para
First complaint: in relation to the capped amount for prolongation costs
Costs
Clause 2.1 of the GCC provided that the Contractor would get an extension of time or payment in the event that it suffered delay or incurred costs as a result of the Employer’s failure to give it right or possession to the worksite; such payment would be: “Payment of any such cost plus reasonable profit subject to a maximum of [monetary amount] per day for every Km. For length less than a kilometre pro-rata amount shall be calculated.”
124
The Employer says that the parties’ quantum experts had agreed on how the capped amount should be calculated if Clause 2.1 applied (the “Subtraction Method”), but the Tribunal – without prior notice to the parties – departed from that, applied another method (the “Overall Length Method”) and arrived at a higher cap – which meant that the Employer’s was liable for more than if the Subtraction Method had been applied.
125
The Employer recognises that the Contractor had in its written closing submissions (“WCS”) put forward the Overall Length Method, but it says that:
para
(a) the Tribunal had not decided on the Overall Length Method because it was what the Contractor sought in its WCS, but instead the Tribunal coincidentally arrived at the same method independently; and
para
(b) if the Tribunal had relied on the Contractor’s WCS, it was too late for the Contractor to have put forward the Overall Length Method in its WCS, and the Employer was deprived of a fair and reasonable opportunity to respond to it.
126
The Employer’s first submission: that the Tribunal coincidentally arrived at the same method that the Contractor had contended for, is a strange one. I cannot glean from reading the Award, that the Tribunal had arrived at the same method one of the parties had contended for, by coincidence, rather than by simply agreeing with that party’s contention. There is nothing in the Award to indicate that the Tribunal did not have in mind the Contractor’s WCS in which the Contractor contended for the Overall Length Method.
127
The Employer suggests that the Tribunal meant to apply the Subtraction Method, but it mistakenly applied the Overall Length Method instead. If that were the case, this would be a complaint about an error in the Tribunal’s reasoning (which the court cannot interfere with: “poor reasoning on the part of an arbitral tribunal is not a ground to set aside an arbitral award”: AKN v ALC [2015] 3 SLR 488 at [59]), and not a natural justice complaint.
128
The Employer sought correction of the Award in relation to the capped amount, and suggested that there was a computational error – referring to [577] of the Award which had mentioned the Subtraction Method, as described in the Contractor’s quantum expert’s rebuttal report. In response, the Contractor contended that the Tribunal had not committed itself to adopting the Subtraction Method but “expressed its understanding of the approach but then proceeded to compute the capped amount using its own methodology.”
129
In so far as the Employer says the phrase “its own methodology” in that submission by the Contractor was an admission that the Tribunal had not simply accepted the Contractor’s contention of the Overall Length Method, but coincidentally arrived at the same method independently, I do not accept that. In context, the Contractor was simply contrasting what the Tribunal did using “its own methodology” with the use of the Subtraction Method, ie, the Tribunal used the methodology which it had decided on, and not the Subtraction Method mentioned by the quantum experts.
130
The Tribunal concluded at [73] of the Decision and Addendum:
131
Notably, the Tribunal characterised what it had done as an “exercise of its judgment” – it did not agree with the Employer’s suggestion that it had meant to use one method (the Subtraction Method) but mistakenly used another (the Overall Length Method) instead.
132
The core question (which underpins the Employer’s second submission) is whether it was deprived of a fair and reasonable opportunity to respond to the Overall Length Method put forward in the Claimant’s WCS. The answer to that is: no.
133
In the Contractor’s WCS, it had put forward the Overall Length Method, with the Subtraction Method as an alternative case Both sides filed their WCS on 16 September 2024, following which there was a hearing of oral closing submissions on 3 October 2024. At that hearing, the Employer had a fair and reasonable opportunity to respond to the Overall Length Method which the Contractor was contending for, but the Employer said nothing about it. On 14 October 2024, the Employer submitted a document entitled “Supplementary Written Quantum Submissions”, but that too said nothing about the Overall Length Method.
134
In the circumstances, the Employer has not made out its complaint that there was a breach of natural justice in this regard. I am reinforced in the conclusion by the Court of Appeal’s decision in Phoenixfin Pte Ltd v Convexity Ltd [2022] 2 SLR 23 at [52]:
135
The issue in the present case was a legal one: in Clause 2.1, what does “every Km” in the phrase “subject to a maximum of [monetary amount] per day” mean? The Tribunal decided that that meant the overall length of the track, and so it used the Overall Length Method (which is what the Contractor had contended for) and calculated the capped amount by taking the overall length of the track, multiplied by the relevant period of delayed access for which the Employer alone was reasonable, multiplied by the monetary amount stated in the Clause 2.1, to produce the “capped” loss.
136
The Employer had a fair and reasonable opportunity to respond to that method, first at the hearing of oral closing submissions on 3 October 2024, and then in its “Supplementary Written Quantum Submissions”: there was no breach of natural justice.
137
The Employer contends that it is not open to parties to put forward new arguments in closing submissions – all arguments have to be pleaded from the outset, and if a new argument is raised in closing submissions (as the Contractor had done) and the Tribunal wished to consider it, then the Tribunal had to specifically seek the Employer’s response to the argument. I do not accept this. Conventionally, pleadings contain material facts not arguments; it would be too much of an interference with the arbitral process to hold that closing submissions can only contain arguments that had been pleaded from the outset, unless the tribunal specifically requests a response (despite a general right of response having been afforded).
138
The Employer cites COT v COU [2023] SGHC 69 (“COT”) for the propositions that “[a] closing submission should not generally … advance a case which falls outside the pleadings” (at [179]) and if it does then “it is open to that party to seek to amend the pleadings, and it is within the power of the tribunal to allow the application to amend, even if the opposing party withholds its consent” (at [181]).
139
In that portion of COT (from [167] to [211]), the court was not discussing breach of natural justice but rather whether the tribunal had exceeded its jurisdiction. To determine that, the court reviewed:
para
(a) the notice of arbitration (where the claimant said its claim arises from or is connected with legal obligations assumed by the respondents, which obligations are “contained in or evidenced by” a non-disclosure undertaking dated 17 March 2026 (“NDU-3”));
para
(b) the terms of reference (which tracked the notice of arbitration on the above point);
para
(c) the pleadings (where the claimant pleaded in its statement of claim that a contract on basic or essential terms was concluded by 17 March 2016 by words or conduct, and that NDU-3 was issued pursuant to that contract; and in its statement of reply that NDU-3 “evidences the contract”);
para
(d) the lists of issues, after the evidential phase (where the claimant included in its list, the following issue: “Whether a contract on full or basic/essential terms was concluded by words and conduct between [the claimant] and the Respondents (or any one or more of them) between 15 March 2016 and 18 March 2016);
para
(e) the closing submissions, where the claimant carried through its position from the list of issues (that on or by 17 March 2017, the parties “had reached an agreement on all essential terms” and the claimant “regarded a contract on full terms to have been concluded by words or conduct on or by 18 March 2016”).
140
The court noted at [205] that:
141
In the event, the court concluded (at [206]–[211]) that the tribunal had not exceeded its jurisdiction.
142
The court then turned to consider the alleged breach of natural justice – with the respondents alleging that they did not have an opportunity to respond to the alleged “new case” put forward by the claimant, ie, that a contract had been formed by words or conduct by 18 March 2016, as distinct from a contract being formed on 17 March 2026 on the terms of NDU-3.
143
The court said at [227] that “It is perhaps true that the claimant did not plead this issue”, but went on to say at [227]–[228]:
144
The court thus rejected this allegation of breach of natural justice (at [229]).
145
It is noteworthy that the decision in COT itself contradicts the Employer’s present contention that all legal arguments must be pleaded from the outset, otherwise there will be a breach of natural justice unless the tribunal specifically invites a response to new arguments. Although the court said it was “perhaps true” that the claimant had not pleaded the issue (of a contract being formed by words of conduct), as that was made patent in the list of issues (after the evidential phase) the respondents had a fair and reasonable opportunity to respond – which they did not take – and so there was no breach of natural justice.
146
Returning to the present case, the relevant issue is how Clause 2.1 should be construed. Notably, the Employer does not say that this issue was unpleaded, or otherwise not before the Tribunal. On the contrary, the Employer’s affidavit states at [121]:
147
Ironically, it was the Contractor that said that the Employer could not rely on the “cap” in Clause 2.1 because the Employer had not pleaded this, but the Tribunal did not accept that. Both parties’ quantum experts provided workings as to how the “cap” might be computed based on the Subtraction Method, and the Contract’s WCS advanced the Total Length Method as its primary contention, alternatively the Subtraction Method.
148
The Employer says that the Subtraction Method was agreed between the quantum experts, but the Contractor disputes that characterisation. The Contractor says that the Subtraction Method was first proposed by the Employer’s quantum expert, following which the Contractor instructed its quantum expert to provide calculations using the Subtraction Method with certain added assumptions. In any event, in deciding how Clause 2.1 should be construed, and in particular how the “cap” should be computed, the Tribunal was not bound to accept the Subtraction Method, and the Employer does not suggest the Tribunal was bound to do so. The Employer’s complaint is that there was a breach of natural justice in that it did not have a fair and reasonable opportunity to respond to the Contractor’s submission on the Total Length Method – but it had that opportunity, both oral and in writing – it just did not take the opportunity to do so. As in COT, in those circumstances there is no breach of natural justice.
149
This conclusion is fatal both to the Employer’s second submission (that it did not have a fair and reasonable opportunity to respond to the Contractor’s WCS which contended for the Overall Length Method) and its first submission (that the Tribunal had coincidentally arrived at the Overall Length Method without considering the Contractor’s WCS on the point). If indeed the Tribunal had coincidentally decided in the same way that the other party had contended for (which I have found not to be the case), the point remains that the Employer had a fair and reasonable opportunity to respond to that contention: there was no breach of natural justice, and in any event no prejudice caused to the Employer. The Employer’s argument that the Tribunal somehow overlooked the Contractor’s contention (but arrived at the same outcome) goes nowhere unless the Employer can say this might have made a difference to the outcome, but it would not have, since the Tribunal arrived at the same outcome that the Contractor had asked for.
150
I thus dismiss the Employer’s first natural justice complaint.
para
Second complaint: in relation to the Employer’s case on repudiatory breach under applicable legislation
151
The remaining complaints are ones that are infra petita (literally, “below what was asked”): complaints that the Tribunal did not consider material points in the Arbitration and so breached the rules of natural justice.
152
For such complaints to succeed, the Employer needs to satisfy the following four cumulative conditions (per DKT v DKU [2025] 1 SLR 806 at [8]):
para
(a) the point must have been properly brought to the Tribunal for its determination;
para
(b) the point must have been essential to the resolution of the dispute;
para
(c) the Tribunal must have completely failed to consider the point; and
para
(d) even if the Tribunal had failed to consider the point, there must have been real or actual prejudice occasioned by the breach of natural justice.
153
The second natural justice complaint relates to the termination of the Contract. When the Employer terminated the Contract, it relied on a contractual clause to do so. In the Arbitration, it also argued that the Contractor’s conduct was repudiatory, and so, under applicable local legislation, it was entitled to terminate the Contract. The Employer alleges that the Tribunal failed to consider whether it was entitled, under applicable legislation, to terminate the Contract for repudiatory breach on the part of the Contractor.
154
The Employer’s complaint is not borne out by the Award, in particular [713] and [774(4)].
155
At [713] of the Award, the Tribunal said:
156
At [774] of the Award, the Tribunal provided its answers to the issues in relation to NTCs and termination. That included (at [774(4)]):
157
The Tribunal thus dismissed the Employer’s contention that it was entitled to terminate the Contract for repudiatory breach. It appears from that, that there is no breach of natural justice: the Tribunal addressed the point.
158
The Employer complains that the Tribunal did not cite the provision of the local legislation that it was relying on, but that does not avail the Employer: the Tribunal expressly decided that the Contractor had not repudiated the Contract, and that was fatal to the Employer’s contention (whether based on local legislation, or otherwise) that it was entitled to terminate the Contract for repudiatory breach.
159
The Employer contends nevertheless that despite [713] and [774(4)] of the Award (reviewed above), a closer read of the Award will reveal that the Tribunal actually failed to deal with the issue of termination for repudiatory breach.
160
The Employer points to the Tribunal’s analysis of the Contractor’s Claim H10 (the Contractor’s claim for damages resulting from termination) at [455]–[470] of the Award. The Tribunal prefaced that by considering “The course of events in the absence of termination – Claim H10” at [446]–[449] of the Award, noting at [447] that the Contractor had made four claims arising as a consequence of the termination, including Claim H10 for lost profit and overheads on the balance of work (ie, amounts that it would have earned but for the termination). The Tribunal then discussed “Claim H10 – the background” at [450]–[458], then “Claim H10 – the likely course of events in the absence of termination” at [459]–[469].
161
At [467]–[470] of the Award, the Tribunal concluded, in relation to Claim H10:
162
The Employer contrasts the above discussion of Electrical Interlocking (“EI”) in relation to the Contractor’s Claim H10, with the discussion of the same matter of EI in relation to the Employer’s claim for repudiatory breach.
163
As the Tribunal had noted at [713], the Employer’s case was that “in relation to EI [the Contractor] was refusing to complete its scope of work, which amounted to a repudiatory breach, or that [the Contractor] did not comply with NTC 8 [which related to EI] and this ‘enabled [the Employer] to terminate the Contract…’”. The Employer makes this point: how could the Tribunal have dismissed the Employer’s contention of termination for repudiatory breach in relation to EI, when the Tribunal expressed at [467] that:
para
(a) it was doubtful whether the Contractor could have been able to overcome the problems relating to EI, and that the Tribunal could reach no firm conclusion about this; and
para
(b) the Contractor had failed to demonstrate that it could have overcome those problems?
164
The short answer is: at [713]–[774] the Tribunal was discussing the Employer’s contention that it was entitled to terminate the Contract for repudiatory breach by the Contractor in relation to EI (finding that the Employer had wrongfully terminated the Contract), whereas at [446]–[470] the Tribunal was discussing EI in relation to the Contractor’s claim for damages resulting from wrongful termination.
165
After noting at [713] the Employer’s case of termination for repudiatory breach in relation to EI, the Tribunal went on to make the following findings:
166
Thus, in relation to the Employer’s contention that it was entitled to terminate the Contract for issues relating to EI (whether for repudiatory breach or on the terms of the Contract), the Tribunal found:
para
(a) at a meeting on 6 December 2019, there was an agreement between the parties on a way forward (at [770]);
para
(b) after that meeting and agreement, the Employer elected not to terminate the Contract on the ground of a failure to comply with NTC 8 (relating to EI), and thereafter it was not open to the Employer to terminate the Contract for non-compliance with NTC8 (at [771], [774(2)]); accordingly the issue of whether the Contractor complied with NTC8 falls away (at [772]);
para
(c) thus, the Employer was not entitled to terminate the Contract for repudiatory breach (in relation to EI) (at [774(4)]), and the Contract was not validly terminated (at [774(7)]).
167
There is no inconsistency between those findings, which relate to the Employer electing not to terminate the Contract in relation to EI in light of an agreement between the parties, and the Tribunal finding (at [467]–[470], [773]) that the Contractor had not proved that it could overcome the EI issues (and so the Tribunal dismissed the Contractor’s Claim H10).
168
In any event, the issue is not whether the Tribunal’s decision was well reasoned, it is whether there was a breach of natural justice by the Tribunal failing to address the Employer’s contention that it was entitled to terminate the Contract for repudiatory breach: there was no such breach of natural justice.
169
I thus dismiss the Employer’s second natural justice complaint.
para
Third complaint: in relation to the Employer’s case on pre-casting of Location Box (“LB”) foundations
170
The Employer says that the Tribunal failed to consider the essential issue of whether the Contractor could have performed the pre-casting of LB foundations before the formation was complete.
171
The Tribunal did consider the pre-casting issue and related matters: that is evident not only from [244] of the Award which the Employer refers to, but also [323], [372], [387] and [389] (which the Contractor refers to) – all these paragraphs are set out below, together with [242]–[243] for context:
172
From the Award, in particular [372], the Tribunal found: “we do not consider that procurement or installation of LBs was on the critical path” (see also [389]). That being the case, the Employer’s natural justice complaint about the pre-casting issue leads nowhere: even if there were any breach of natural justice in relation to the pre-casting issue, the Tribunal’s finding that procurement and installation of LBs were not on the critical path meant that even if the Tribunal had found that the Contractor could have, and should have, pre-cast the LBs, the Tribunal would have found that did not contribute to the delay to the Works. Any breach of natural justice thus would not have caused the Employer any prejudice, and prejudice is an element that the Employer needs to establish to set-aside an Award (or part thereof) for breach of natural justice.
173
In any event, I do not agree with the Employer’s specific complaints in relation to this alleged breach.
174
First, the Employer points to [244] of the Award where the Tribunal observed that it was “possible” that the LB foundations could have been constructed before formation, but said that no witness had mentioned whether the pre-casting of LB foundations could have been done before the formation was complete.
175
This mischaracterises what the Tribunal said at [244]:
para
(a) The Tribunal did not merely say it was possible that the LB foundations could have been constructed before formation, it added “this might have involved constructing the formation around in situ LB foundations”.
para
(b) In context, the Tribunal’s statement that it “did not understand any witness to say that this could or should have been done” referred not merely to the possibility of pre-casting the LB foundations, but also that “this might have involved constructing the formation around in situ LB foundations” as the Tribunal had just said.
para
(c) At [244] the Tribunal had also referred to what the Contractor’s witness Mr “A” had said about installing LBs a minimum of 2.825 m from the centre line of the track, and how could that be done if the track was not there?
176
Second, the Employer says that the Tribunal did not apply its mind to the “fact” (which had been brought to its attention) that the LB could have been installed anywhere within the right of way, and did not have to be placed on the formation. This was not a “fact” as the Employer puts it, for the Contractor had disputed it: the Contractor’s evidence was that the LBs were meant to be constructed on the blanket/formation.
177
Third, the Employer says the Tribunal completely failed to consider the Employer’s evidence that the parties had arrived at an understanding that the Contractor should, and could, perform pre-casting of the LB foundations to expedite the Works. The evidence cited for this rests on the Engineer having allowed the Contractor to pre-cast the LB foundations, which the Contractor had sought permission for. It was nevertheless the Contractor’s position, as it maintained in the Arbitration, that pre-casting was not technically workable or practical since the final location and height of LBs could only be confirmed from the actual track, as was reflected in the Contractor’s Reply to Amended Defence in the Arbitration, at [82].
178
Ultimately, these criticisms of how the Tribunal dealt with the pre-casting issue do not reveal any breach of natural justice, all the more so when set against the backdrop of the Tribunal’s finding that procurement and installation of LBs was not on the critical path, and so whether or not the LBs could or should have been pre-cast did not cause the delay to the Works.
179
I thus dismiss the Employer’s third natural justice complaint.
para
Fourth complaint: in relation to the Employer’s evidence on whether the changes to the Auto Location Huts (“ALHs”) constituted variations
180
The Employer’s fourth and last natural justice complaint is that the Tribunal allowed the Contractor’s Claim H2 for additional payment due to variation works required by the Employer in relation to the ALHs).
181
The Tribunal specifically addressed Claim H2 in “Section XIII. The ALH Variation (H2)” running from [775]–[813] (on liability) and [807]–[818] (on quantum and interest) of the Award. In that section, the Tribunal did not mention the evidence of the Employer’s witness Mr K, and so the Employer says the Tribunal must have failed to consider Mr K’s evidence on Claim H2.
182
The Tribunal did however mention Mr K’s evidence on other aspects of the case. More pertinently, the Tribunal said at [312] that it had undertaken “careful consideration of [Mr K’s] evidence as a whole” and at [313] that it approached “all of his evidence with considerable reservation” [emphasis added]. Those references go against the Employer’s contention that the Tribunal had failed to consider Mr K’s evidence on Claim H2.
183
The Tribunal’s criticisms of Mr K’s evidence as a whole (at [312] – [313]) merit fuller examination.
184
At [240]–[245] of the Award, the Tribunal reviewed Mr K’s evidence on the pre-casting issue; [242]–[243] of the Award have been set out at [171] above. At [242] of the Award, the Tribunal noted that Mr K’s evidence that access to track was not necessary to establish the foundation level of the LB was in direct conflict with the Employer’s pleaded case that it was “general practice” that when LBs are cast along a track the rail level is used as a reference for the LB foundations. At [243] of the Award, the Tribunal said, “Regrettably, the Tribunal finds that it is a reflection of Mr [K’s] approach to giving his evidence to the Tribunal that he was not prepared to offer any explanation for this apparent abandonment of general engineering practice”.
185
At [306]–[311] of the Award, the Tribunal reviewed Mr K’s evidence on HDD (“horizontal direct drilling”). At [310] of the Award, the Tribunal said Mr K had made a blatant attempt to divert cross-examination by introduction, for the first time and without any advance notice, an entirely new method of construction. At [311]–[313] of the Award, the Tribunal’s criticism of Mr K’s evidence was biting:
186
At [828], the Tribunal referred to Mr K’s evidence in relation to the Contractor’s Claim H1, which concerned the change in the number and location of Level Crossing Gates. The Tribunal said, “…[the Employer] relies on the evidence of Mr [K] who expressed his view that [the Contractor’s witness] Mr [H’s] calculation of the time spent was too high.” At [831], the Tribunal said it found no reason, in light of the exchanges between the Contractor and the Engineer, to doubt the truth and reliability of the evidence given by [the Contractor’s witnesses Mr H and Mr “CG”], none of which was challenged when they gave oral evidence. The Tribunal then said at [832]:
187
That reference to Section VII in [832] of the Award would appear to be a typographical error (the correct reference being to section VI instead). Although there were references to Mr K’s evidence in Section VII (which ran at [374], [376] and [441], the Tribunal’s reference to and criticism of Mr K’s evidence “as a whole” was in [312]–[313] of the Award, which were in Section VI (running from [171]–[313]), not Section VII (running from [314]–[370]).
188
This is reinforced by the (correct) reference to section VI in the very next paragraph of the Award – [833], where the Tribunal said that Mr S’s evidence was of limited assistance to the Tribunal, for principally, three reasons as set out at [319]–[336].
189
The reasons the Tribunal referred to at [833] of the Award would be those at [319]–[333] (in Section VI) of the Award, where the Tribunal said that Mr S’s evidence was of limited assistance to the Tribunal for, principally, three reasons as set out in that part of the Award.
190
Given the various references to and criticisms of Mr K’s evidence on other aspects, the Tribunal saying that (at [312]) that it had carefully considered his “evidence as a whole”, and (at [313]) that it approached “all of his evidence” with considerable reservation, I cannot draw the inference that the Tribunal failed to consider his evidence on Claim H2 merely because the Tribunal did not specifically mention Mr K’s evidence on Claim H2 in Section XIII where that claim was discussed. For such an inference to be drawn, it would have to be clear and virtually inescapable (AKN v ALC [2015] 3 SLR 488 at [46]) – it was not.
191
In any event, given the Tribunal’s criticisms of Mr K’s evidence, and how it dealt with Claim H2, even if the Tribunal had failed to consider Mr K’s evidence in relation to that claim, I am not persuaded that Mr K’s evidence on that “could reasonably have made a difference” to the Tribunal – “it is evident that there is no prospect whatsoever that the material…would have made any difference because it wholly lacked legal or factual weight.”
192
I reach this conclusion not only because of what the Tribunal said of Mr K’s evidence (as discussed above), but also because of how the Tribunal approached Claim H2.
para
(a) The Tribunal found from the wording of a letter from the Engineer, that the Engineer had issued an instruction which constituted a variation under the Contract, to change the size of the ALH building(s) (at [798]).
para
(b) The Tribunal said if the Employer had wished to maintain its pleaded denial of the Contractor’s pleaded case, that should have been clearly put to the one witness (Mr G) who gave evidence in support of the Contractor’s case (at [797]), but it was not (at [787]) – Mr G’s evidence on this claim was not challenged in cross-examination, and so the Tribunal described his evidence as “unchallenged” (at [801], [802], [803].
para
(c) The Tribunal found the Contractor’s Mr G to be a credible witness and accepted his evidence (at [800]–[806]).
193
Mr K’s evidence could not reasonably have made a difference to these matters: it could not reasonably have changed the Tribunal’s decision (based on the wording of the Engineer’s letter) that the Engineer had issued a variation amounting to a variation to change the size of the ALH building(s), it could not have changed the failure to put the Employer’s denial of the Contractor’s pleaded case to Mr G in cross-examination, and it could not reasonably have changed the Tribunal’s view of Mr G as a credible witness.
194
In the circumstances, even if there were any breach of natural justice, that would not have caused any prejudice to the Employer.
195
I thus dismiss the Employer’s fourth natural justice complaint.
para
Conclusion
196
For the above reasons, I dismiss the Employer’s application to set aside the Final Award dated 2 April 2025 and the Decision and Addendum dated 25 June 2025.
Costs
Unless the parties can agree on costs, they are to file their costs submissions, limited to eight pages excluding any schedule of disbursements, by 17 April 2026.
Wrong text, a broken link, out-of-date content, or a removal request — tell us and we'll check it against the official source.