Singapore legislation
Regulation 3
of Building Control (Buildability and Productivity) Regulations 2011
Regulation 3
Application
Subregulation 1
Subject to paragraphs (2) and (5) —
regulations 4, 6, 7, 11 and 13 (except insofar as they relate to an alternative solution) apply to any building works in respect of which an application for planning permission is submitted to the competent authority under the Planning Act 1998 on or after 15 July 2011 but before 15 December 2019 and which involve a gross floor area of 2,000 square metres or more; and
regulations 4, 6, 7, 11 and 13 apply to any building works in respect of which an application for planning permission is submitted to the competent authority under the Planning Act 1998 on or after 15 December 2019 and which involve a gross floor area of 5,000 square metres or more.
Subregulation 1A
Regulation 4, except for regulation 4(3)(b), shall not apply to building works consisting of repairs, alterations or additions to an existing building.
Subregulation 2
Regulations 4(3)(b), 6, 7, 11 and 13 do not apply to building works consisting of repairs, alterations or additions to an existing building (whether carried out within or outside the existing building) unless —
the gross floor area of the existing floor to be reconstructed;
the increase in the gross floor area of the existing building that will result from the building works; or
the sum of the gross floor areas mentioned in sub‑paragraphs (a) and (b),is —
2,000 square metres or more for building works in respect of which an application for planning permission is submitted on or after 15 July 2011 but before 15 December 2019; or
5,000 square metres or more for building works in respect of which an application for planning permission is submitted on or after 15 December 2019.
Subregulation 3
Subject to paragraphs (4), (5) and (6), regulations 5, 8, 9, 10, 12 and 14 shall apply to any building works in respect of which an application for planning permission is submitted on or after 15th July 2011 and which involve a gross floor area of 5,000 square metres or more.
Subregulation 4
Regulations 5, 8, 9, 10, 12 and 14 shall not apply to building works consisting of repairs, alterations or additions to an existing building (whether carried out within or outside the existing building) in respect of which an application for planning permission is submitted on or after 15th July 2011 unless —
the gross floor area of the existing floor to be reconstructed;
the increase in the gross floor area of the existing building that will result from the building works; or
the sum of sub-paragraphs (a) and (b),is 5,000 square metres or more.
Subregulation 4A
Subject to paragraphs (5) and (6), regulations 4A and 4B shall apply to any building works (other than repairs, alterations or additions to an existing building) in respect of which an application for planning permission is submitted on or after 1 November 2014.
Subregulation 5
These Regulations shall also not apply to any building works relating to —
any culvert, bridge, underpass, tunnel, earth retaining or stabilising structure, slipway, dock, wharf or jetty;
any theme park;
any place of worship;
any power station; or
any waste processing or treatment plant.
Subregulation 6
Regulations 4A, 5, 5A, 7, 8, 12 and 14 do not apply where the plans of the relevant building works contain any alternative solution.