About this subsidiary legislation

Building Control (Environmental Sustainability) Regulations 2008 is Singapore Subsidiary Legislation, cited as Subsidiary Legislation BCA-S199-2008 1989, currently marked in force and first recorded in 1989.

Regulation 1

Citation and commencement

Open as pageSuggest a correction

These Regulations may be cited as the Building Control (Environmental Sustainability) Regulations 2008 and shall come into operation on 15th April 2008.

Regulation 2

Definitions

Open as pageSuggest a correction
Amended byS 579/2022 wef 31/12/2021S 592/2025 wef 30/09/2025S 542/2014 wef 01/09/2014S 256/2010 wef 05/05/2010S 579/2022 wef 01/08/2022S 542/2014 wef 01/09/2014S 542/2014 wef 01/09/2014S 579/2022 wef 31/12/2021S 592/2025 wef 30/09/2025

In these Regulations —“appropriate practitioner”, in relation to any building works, means —

(a)

the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act to prepare the plans of those building works in accordance with the Act; (b)any other qualified person appointed under the Act in respect of those building works; or

(c)

a professional engineer registered under the Professional Engineers Act 1991 in the branch of mechanical engineering or electrical engineering,who is, under the Code, recognised as competent to assess the building works and, using the scoring methodology specified in the Code, to express by a numerical score the degree of compliance of those building works with the Code;“building envelope” means the elements of a building which enclose air-conditioned spaces through which thermal energy may be transferred from the exterior;“building plans”, in relation to any building works, means the building plans referred to in regulation 4(1)(a)(i) of the Building Control Regulations 2003 (G.N. No. S 666/2003) relating to those building works;“building services” means any part of, or any controls associated with —

(a)

the air-conditioning system or any assembly of components for the treatment of air, controlling its temperature, humidity, cleanliness and distribution within an air-conditioned space; and

(b)

the mechanical ventilation system for the purposes of supplying or removing air to or from a building or part thereof by mechanical means or devices; “Code” means the Code for Environmental Sustainability of Buildings issued by the Building and Construction Authority;“environmental sustainability score” or “ES score” has the meaning given by section 22FA of the Act;“existing building” means any building in respect of which a certificate of statutory completion or a temporary occupation permit has been issued;“Government Land Sales Programme” means a programme under which State land is sold by or on behalf of the Government for development and through a public selection process;“Green Mark Certification” means certification under the BCA Green Mark Certification Standard for New Buildings approved by the Commissioner of Building Control and issued by the Building and Construction Authority;“gross floor area” has the same meaning as “floor area” in the Planning (Development) Rules 2008 (G.N. No. S 113/2008);“mixed-use building” means a non-residential building part of which is constructed or used, or is to be constructed or used, solely as a residence or private dwelling;“non-residential building” means a building other than a residential building;“residential building” means a building that is constructed or used, or is to be constructed or used, solely as a residence or private dwelling;“State land” has the same meaning as in section 2 of the Singapore Land Authority Act 2001.

Definition

“appropriate practitioner”, in relation to any building works, means —

(a)

the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act to prepare the plans of those building works in accordance with the Act; (b)any other qualified person appointed under the Act in respect of those building works; or

(c)

a professional engineer registered under the Professional Engineers Act 1991 in the branch of mechanical engineering or electrical engineering,who is, under the Code, recognised as competent to assess the building works and, using the scoring methodology specified in the Code, to express by a numerical score the degree of compliance of those building works with the Code;

Amended byS 579/2022 wef 31/12/2021
Suggest a correction

Definition

“building envelope” means the elements of a building which enclose air-conditioned spaces through which thermal energy may be transferred from the exterior;

Suggest a correction

Definition

“building plans”, in relation to any building works, means the building plans referred to in regulation 4(1)(a)(i) of the Building Control Regulations 2003 (G.N. No. S 666/2003) relating to those building works;

Suggest a correction

Definition

“building services” means any part of, or any controls associated with —

(a)

the air-conditioning system or any assembly of components for the treatment of air, controlling its temperature, humidity, cleanliness and distribution within an air-conditioned space; and

(b)

the mechanical ventilation system for the purposes of supplying or removing air to or from a building or part thereof by mechanical means or devices;

Suggest a correction

Definition

“Code” means the Code for Environmental Sustainability of Buildings issued by the Building and Construction Authority;

Suggest a correction

Definition

“environmental sustainability score” or “ES score” has the meaning given by section 22FA of the Act;

Amended byS 592/2025 wef 30/09/2025
Suggest a correction

Definition

“existing building” means any building in respect of which a certificate of statutory completion or a temporary occupation permit has been issued;

Suggest a correction

Definition

“Government Land Sales Programme” means a programme under which State land is sold by or on behalf of the Government for development and through a public selection process;

Amended byS 542/2014 wef 01/09/2014
Suggest a correction

Definition

“Green Mark Certification” means certification under the BCA Green Mark Certification Standard for New Buildings approved by the Commissioner of Building Control and issued by the Building and Construction Authority;

Amended byS 256/2010 wef 05/05/2010
Suggest a correction

Definition

“gross floor area” has the same meaning as “floor area” in the Planning (Development) Rules 2008 (G.N. No. S 113/2008);

Amended byS 579/2022 wef 01/08/2022
Suggest a correction

Definition

“mixed-use building” means a non-residential building part of which is constructed or used, or is to be constructed or used, solely as a residence or private dwelling;

Suggest a correction

Definition

“non-residential building” means a building other than a residential building;

Suggest a correction

Definition

“residential building” means a building that is constructed or used, or is to be constructed or used, solely as a residence or private dwelling;

Amended byS 542/2014 wef 01/09/2014
Suggest a correction

Definition

“State land” has the same meaning as in section 2 of the Singapore Land Authority Act 2001.

Amended byS 542/2014 wef 01/09/2014S 579/2022 wef 31/12/2021S 592/2025 wef 30/09/2025
Suggest a correction

Regulation 3

Application

Open as pageSuggest a correction
Amended byS 631/2021 wef 01/12/2021S 631/2021 wef 01/12/2021S 631/2021 wef 01/12/2021S 579/2022 wef 31/12/2021

Subregulation 1

Suggest a correction
Amended byS 631/2021 wef 01/12/2021S 631/2021 wef 01/12/2021S 631/2021 wef 01/12/2021S 579/2022 wef 31/12/2021

Subject to paragraph (2), these Regulations shall apply only to any of the following building works in respect of which an application for planning permission is submitted to the competent authority under the Planning Act 1998 on or after 15th April 2008:

(a)

building works which involve a gross floor area of 5,000 square metres or more;

(b)

building works which involve increasing the gross floor area of an existing building by 5,000 square metres or more;

(c)

building works relating to an existing building which involve a gross floor area of 5,000 square metres or more.

Subregulation 2

Suggest a correction

Notwithstanding paragraph (1)(c), these Regulations shall not apply to any building works consisting of repairs or alterations to an existing building unless those building works involve the provision, extension or substantial alteration of the building envelope and building services in or in connection with an existing building.

Regulation 4

Minimum ES score and relevant Green Mark Certification

Open as pageSuggest a correction
Amended byS 256/2010 wef 05/05/2010S 542/2014 wef 01/09/2014S 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010S 342/2012 wef 20/07/2012S 542/2014 wef 01/09/2014S 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010S 342/2012 wef 20/07/2012S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 342/2012 wef 20/07/2012S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 505/2022 wef 30/06/2022S 256/2010 wef 05/05/2010S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 592/2025 wef 30/09/2025S 592/2025 wef 30/09/2025

Subregulation 1

Suggest a correction
Amended byS 256/2010 wef 05/05/2010S 542/2014 wef 01/09/2014S 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010S 342/2012 wef 20/07/2012S 542/2014 wef 01/09/2014S 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010S 342/2012 wef 20/07/2012S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 342/2012 wef 20/07/2012S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 505/2022 wef 30/06/2022

For the purposes of these Regulations, the minimum requirement for any building works to which these Regulations apply shall, subject to paragraphs (2), (3) and (4), be the following:

(a)

where the building works relate to a residential building not referred to in sub-paragraph (c), (d) or (e) — an ES score of 50 points calculated in accordance with the Code;

(b)

where the building works relate to a non-residential building not referred to in sub-paragraph (c), (d) or (e) — an ES score of 50 points calculated in accordance with the Code; and

(c)

where the building works relate to any building on land sold on or after 5 May 2010 but before 30 June 2022 under the Government Land Sales Programme and the building is wholly or partly within an area described in the first column of the First Schedule — the relevant Green Mark Certification indicated in the second column of the First Schedule; (d)where the building works relate to any building on land sold on or after 20 July 2012 but before 30 June 2022 under the Government Land Sales Programme and the building is wholly or partly within an area described in the first column of the Second Schedule — the Green Mark Certification indicated in the second column of the Second Schedule; (e)where the building works relate to any building on land sold on or after 1 September 2014 but before 30 June 2022 under the Government Land Sales Programme and the building is wholly or partly within an area described in the first column of the Third Schedule — the relevant Green Mark Certification indicated in the second column of the Third Schedule;

(f)

where the building works relate to any building on land sold on or after 30 June 2022 under the Government Land Sales Programme — a Green Mark Certification of Green Mark Platinum Super Low Energy.

Subregulation 2

Suggest a correction
Amended byS 256/2010 wef 05/05/2010S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 592/2025 wef 30/09/2025

Where any building works to which these Regulations apply relate —

(a)

to both residential and non-residential buildings and the respective parts of building works relating to the residential building and to the non-residential building each involve a gross floor area of 2,000 square metres or more; or

(b)

to any mixed-use building and the building works relating to each of the following parts of the building involve a gross floor area of 2,000 square metres or more:

(i)

the part of the building which is constructed or used, or is to be constructed or used, as a residence or private dwelling; and

(ii)

the remaining parts of the same building,each part of those building works shall be regarded as separate building works, and the minimum ES score or relevant Green Mark Certification in paragraph (1)(a), (b), (c), (d), (e) or (f), as the case may be, shall apply to each part as if each were separate building works.

Subregulation 3

Suggest a correction
Amended byS 256/2010 wef 05/05/2010S 542/2014 wef 01/09/2014S 505/2022 wef 30/06/2022S 592/2025 wef 30/09/2025

Where any building works to which these Regulations apply relate —

(a)

to both residential and non-residential buildings and any respective part of the building works relating to the residential building or to the non-residential building involve a gross floor area of less than 2,000 square metres; or

(b)

to any mixed-use building and the building works relating to either of the following parts of the building involve a gross floor area of less than 2,000 square metres:

(i)

the part of the building which is constructed or used, or is to be constructed or used, as a residence or private dwelling; or

(ii)

the remaining parts of the same building,the smaller part of the building works shall be disregarded and the minimum ES score or relevant Green Mark Certification in paragraph (1)(a), (b), (c), (d), (e) or (f), as the case may be, shall apply to the building works as if it comprised only the larger part.

Subregulation 4

Suggest a correction
Amended byS 592/2025 wef 30/09/2025

Where any building works to which these Regulations apply relate only to such part of a mixed-use building which is constructed or used, or is to be constructed or used, as a residence or private dwelling, the building works shall be regarded as relating to a residential building.

Regulation 5

Assignment of numerical score by appropriate practitioner

Open as pageSuggest a correction
Amended byS 256/2010 wef 05/05/2010

For the purposes of regulation 4(1)(a) or (b), it shall be the function of every appropriate practitioner who assesses any building works or any part thereof to which these Regulations apply, to express by a numerical score, using the scoring methodology specified in the Code, the degree of compliance of those building works or part thereof with the Code and assign that score accordingly.

Regulation 6

Minimum environmental sustainability standard

Open as pageSuggest a correction
Amended byS 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010

Subregulation 1

Suggest a correction
Amended byS 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010

The qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act to prepare the plans of any building works in accordance with the Act shall ensure that the building works are designed with physical features or amenities, and may be carried out using methods and materials, so that —

(a)

the total (using the scoring methodology specified in the Code) of all numerical scores assigned by every appropriate practitioner who assesses the building works or part thereof is not less than the minimum ES score applicable to those building works; or

(b)

the relevant Green Mark Certification is achievable in respect of those building works.

Subregulation 2

Suggest a correction

Paragraph (1) shall apply in addition to the requirements of Part IV of the Building Control Regulations 2003 (G.N. No. S 666/2003).

Regulation 7

Submission of scores using Code

Open as pageSuggest a correction
Amended byS 256/2010 wef 05/05/2010S 592/2025 wef 30/09/2025

In addition to the requirements of regulations 4, 5 and 6 of the Building Control Regulations 2003, the developer of any building works that is subject to a minimum ES score shall, when applying for approval of building plans under section 5 of the Act, submit to the Commissioner of Building Control —

(a)

a declaration from each appropriate practitioner who assessed the building works or any part thereof, stating the numerical score he assigned the building works or part thereof under regulation 5 and that the numerical score is correct;

(b)

a statement from the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act to prepare the plans of those building works in accordance with the Act that the total (using the scoring methodology specified in the Code) of all numerical scores assigned by every appropriate practitioner who assessed the building works or part thereof is not less than the minimum ES score applicable to those building works;

(c)

the total (using the scoring methodology specified in the Code) of all numerical scores assigned by the appropriate practitioners referred to in paragraph (a); and

(d)

such other documents as the Commissioner of Building Control may require in any particular case.

Regulation 8

Deviation from approved building plans

Open as pageSuggest a correction
Amended byS 256/2010 wef 05/05/2010S 592/2025 wef 30/09/2025

Where the plans of any building works or proposed building works that is subject to a minimum ES score have been approved by the Commissioner of Building Control under section 5(3)(a) of the Act and the developer of the building works who intends to depart or deviate from the plans approved —

(a)

the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act in respect of those building works must ensure that the building works (with such departure and deviation) are still designed with physical features or amenities, and may be carried out using methods and materials, so that the total (using the scoring methodology specified in the Code) of all numerical scores assigned by every appropriate practitioner who assesses the building works or part thereof is not less than the minimum ES score applicable to those building works; but(b)the developer need not submit to the Commissioner of Building Control the total of all numerical scores assigned by the appropriate practitioners who assessed the building works or part thereof.

Regulation 9

Submission of as-built scores

Open as pageSuggest a correction
Amended byS 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010S 592/2025 wef 30/09/2025

Subregulation 1

Suggest a correction
Amended byS 592/2025 wef 30/09/2025S 256/2010 wef 05/05/2010S 592/2025 wef 30/09/2025

Without prejudice to the requirements of regulation 43 of the Building Control Regulations 2003 (G.N. No. S 666/2003), a temporary occupation permit or, in a case where no such permit is earlier applied for, a certificate of statutory completion shall not be granted in respect of any completed building works where the application for a temporary occupation permit or certificate of statutory completion, as the case may be, is not accompanied by a Green Mark Certificate to show that the required Green Mark Certification has been achieved or where the works are subject to a minimum ES score —

(a)

a declaration from each appropriate practitioner who assessed the completed building works or any part thereof using the Code, stating the numerical score he assigned the building works or part thereof under regulation 5 and that the numerical score is correct;

(b)

a statement from the qualified person appointed under section 8(1)(a) or 11(1)(d)(i) of the Act to prepare the plans of those building works in accordance with the Act that the total (using the scoring methodology specified in the Code) of all numerical scores assigned by every appropriate practitioner who assessed the building works or part thereof is not less than the minimum ES score applicable to those building works; and

(c)

the total (using the scoring methodology specified in the Code) of all numerical scores assigned by the appropriate practitioners referred to in sub-paragraph (a).

Subregulation 2

Suggest a correction

On completion of any building works, the developer of the building works shall, when applying for a temporary occupation permit or a certificate of statutory completion, whichever is the earlier, submit to the Commissioner of Building Control —

(a)

the documents referred to in paragraph (1)(a), (b) and (c); and

(b)

such other documents as the Commissioner of Building Control may require in any particular case.

Subregulation 3

Suggest a correction

Paragraph (2) shall apply in addition to the requirements of Part V of the Building Control Regulations 2003 (G.N. No. S 666/2003).

Regulation 10

Penalty

Open as pageSuggest a correction

Subregulation 1

Suggest a correction

Any person who contravenes regulation 6(1) or 8(a) shall be guilty of an offence and shall be liable on conviction to a fine not exceeding $10,000.

Subregulation 2

Suggest a correction

In any proceedings for an offence under paragraph (1), it shall be a defence for the person charged to prove —

(a)

that the commission of the offence was due to the act or default of another appropriate practitioner or to some other cause beyond his control; and

(b)

that he took all reasonable precautions and exercised all due diligence to avoid the commission of such an offence by himself or by any person under his control.

Common questions

What is Building Control (Environmental Sustainability) Regulations 2008?
Building Control (Environmental Sustainability) Regulations 2008 is Singapore Subsidiary Legislation, cited as Subsidiary Legislation BCA-S199-2008 1989, currently marked in force and first recorded in 1989.
Is Building Control (Environmental Sustainability) Regulations 2008 still in force?
Yes — Building Control (Environmental Sustainability) Regulations 2008 is currently in force.
When did Building Control (Environmental Sustainability) Regulations 2008 take effect?
Building Control (Environmental Sustainability) Regulations 2008 was first recorded in 1989.
How many regulations does Building Control (Environmental Sustainability) Regulations 2008 have?
Building Control (Environmental Sustainability) Regulations 2008 contains 10 regulations.
Where can I read the official version of Building Control (Environmental Sustainability) Regulations 2008?
The official text of Building Control (Environmental Sustainability) Regulations 2008 is published at sso.agc.gov.sg.