Regulation 1
Citation and commencement
This Order is the Electric Vehicles Charging (Minimum Electrical Load and Charging Points) Order 2023 and comes into operation on 8 December 2023.
/akn/sg/act/sub_leg/2022/EVCA-S788-2023
The full official text, structured for quick navigation. Copy any provision or jump straight to a section.
Quick answer
Electric Vehicles Charging (Minimum Electrical Load and Charging Points) Order 2023 is Singapore Subsidiary Legislation, cited as Subsidiary Legislation EVCA-S788-2023 2022, currently marked in force and first recorded in 2022.
Citation and commencement
This Order is the Electric Vehicles Charging (Minimum Electrical Load and Charging Points) Order 2023 and comes into operation on 8 December 2023.
Definitions
In this Order, “building works”, “development”, “electrical work”, “parking lot” and “parking place” have the meanings given by section 60 of the Act.
Minimum electrical load and charging points for development with building works
For the purpose of section 64(1)(a) of the Act, the minimum electrical load in respect of a development on which building works are carried out is determined in accordance with the formula 1.3 kVA × TPL, where TPL is the total number of parking lots in the parking places of the development.
For the purpose of section 64(1)(b) of the Act, the minimum number of charging points in the parking places of the development is the number of charging points (called N) that draws the aggregate amount of electrical load (as measured in kilowatts) determined in accordance with the formula prescribed by sub‑paragraph (3) and, if N is not a whole number, rounding that number to the next higher whole number.
In sub‑paragraph (2), the formula to determine the aggregate amount of electrical load (as measured in kilowatts) is 0.2 × (MEL × PF), where —
MEL is the minimum electrical load prescribed by sub‑paragraph (1); and
PF is the power factor of 0.85.
Minimum electrical load and charging points for development with electrical work
For the purpose of section 65(1)(a) of the Act, the minimum electrical load in respect of a development on which electrical work is carried out is determined in accordance with the formula 1.3 kVA × TPL, where TPL is the total number of parking lots in the parking places of the development.
For the purpose of section 65(1)(b) of the Act, the minimum number of charging points in the parking places of the development is the number of charging points (called N) that draws the aggregate amount of electrical load (as measured in kilowatts) determined in accordance with the formula prescribed by sub‑paragraph (3) and, if N is not a whole number, rounding that number to the next higher whole number.
In sub‑paragraph (2), the formula to determine the aggregate amount of electrical load (as measured in kilowatts) is 0.2 × (MEL × PF), where —
MEL is the minimum electrical load prescribed by sub‑paragraph (1); and
PF is the power factor of 0.85.