Authority may execute street works or cause street works to be properly carried out

(1)

If street works are not commenced or executed to the satisfaction of the Authority in any case where a deposit has been made under section 20(6), the Authority may, at any time after the service of a notice in writing, execute the street works or cause the street works to be properly carried out.

(2)

The costs and expenses incurred by the Authority in the execution of the street works or in causing the street works to be properly carried out shall be recovered from the deposit made under section 20(6).