Regulation 20

of Building Control (Licensing of Builders) Regulations 2008

Regulation 20

Manpower programme

Amended byS 786/2014 wef 01/01/2015S 786/2014 wef 01/01/2015S 786/2014 wef 01/01/2015S 115/2013 wef 01/04/2013S 115/2013 wef 01/04/2013S 115/2013 wef 01/04/2013S 786/2014 wef 01/01/2015S 115/2013 wef 01/04/2013S 786/2014 wef 01/01/2015S 115/2013 wef 01/04/2013S 786/2014 wef 01/01/2015S 115/2013 wef 01/04/2013S 115/2013 wef 01/04/2013S 200/2011 wef 15/10/2011S 115/2013 wef 01/04/2013S 786/2014 wef 01/01/2015

Subregulation 1

Amended byS 786/2014 wef 01/01/2015

For the purposes of section 29H(2) of the Act, the manpower programme for each significant general building work project in Singapore shall provide for registered construction personnel —

(a)

of such class as specified in paragraphs (3), (4) and (6); and

(b)

of such number necessary to carry out the man-years of work computed in accordance with the formula specified in paragraph (2), rounded off to a maximum of 2 decimal points,to be employed by or on behalf of the licensed general builder or engaged in connection with the significant general building work project.

Subregulation 2

Amended byS 786/2014 wef 01/01/2015S 786/2014 wef 01/01/2015

For the purposes of this regulation —

(a)

in the case where the value of a significant building work project does not exceed $100 million, the formula referred to in paragraph (1)(b) shall be —where Ais the manpower factor specified in paragraphs (3), (4) and (6);Bis the value of the significant building work project; andCis the value of $10 million; and

(b)

in the case where the value of a significant building work project exceeds $100 million, the formula referred to in paragraph (1)(b) shall be —where Ais the manpower factor specified in paragraphs (3), (4) and (6);Bis the value of the significant building work project; andDis the value of $20 million.

Subregulation 3

Amended byS 115/2013 wef 01/04/2013S 115/2013 wef 01/04/2013S 115/2013 wef 01/04/2013S 786/2014 wef 01/01/2015

Where the significant general building work project involves addition, alteration or repair works to an existing building not described in paragraph (4) —

(a)

in the case of any class of work specified in Part I of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 1;

(b)

in the case of any class of work specified in Part II or III of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 1;

(c)

[Deleted by S 786/2014 wef 01/01/2015](d)[Deleted by S 786/2014 wef 01/01/2015](e)in the case of the class of work specified in Part V of the Third Schedule, the number of construction supervisors shall be determined using the manpower factor of 0.25; and

(f)

in the case of any class of work specified in Part VI of the Third Schedule or any combination thereof, the number of construction supervisors in any such class or classes of work shall be determined using the manpower factor of 0.25.

Subregulation 4

Amended byS 115/2013 wef 01/04/2013S 786/2014 wef 01/01/2015S 115/2013 wef 01/04/2013S 786/2014 wef 01/01/2015

Where the significant general building work project involves erecting, or any addition, alteration or repair works to, any flyover, bridge, tunnel or other structure similar thereto and is not a significant general building work project involving the construction of a station or depot of a rapid transit system —

(a)

in the case of any class of work specified in Part I of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 0.75; and (b)[Deleted by S 786/2014 wef 01/01/2015](c)in the case of the class of work specified in Part V of the Third Schedule, the number of construction supervisors shall be determined using the manpower factor of 0.25.

Subregulation 5

[Deleted by S 786/2014 wef 01/01/2015]

Subregulation 6

Amended byS 115/2013 wef 01/04/2013S 115/2013 wef 01/04/2013S 200/2011 wef 15/10/2011S 115/2013 wef 01/04/2013S 786/2014 wef 01/01/2015

In the case of any other significant general building work project not specified in paragraph (3) or (4) —

(a)

in the case of any class of work specified in Part I of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 1;

(b)

in the case of any class of work specified in Part II or III of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 1;

(c)

[Deleted by S 786/2014 wef 01/01/2015](d)[Deleted by S 786/2014 wef 01/01/2015](e)[Deleted by S 786/2014 wef 01/01/2015](f)in the case of the class of work specified in Part V of the Third Schedule, the number of construction supervisors shall be determined using the manpower factor of 0.25; and

(g)

in the case of any class of work specified in Part VI of the Third Schedule or any combination thereof, the number of construction supervisors in any such class or classes of work shall be determined using the manpower factor of 0.25.