Singapore legislation
Regulation 5A
of Street Works (Street Works by Private Persons) Regulations
Regulation 5A
Lodgment of street plan submissions for approval
Subregulation 1
Subject to paragraph (2), any qualified professional engineer engaged for the purposes of any street plan and street works shall, in relation to a proposed development on land to be developed or on such place as the Authority may permit, submit an application to the Authority for the approval of the street plan and street works.
Subregulation 2
The qualified professional engineer supervising the works shall, upon obtaining the approval of the competent authority, lodge the relevant street works proposals and plans with the Authority, accompanied by such declaration made by the qualified professional engineer in such form as the Authority may require where street works (excluding street works referred to in paragraph (3)) are to be carried out for any of the following developments:
residential;
industrial;
educational institution;
place of worship;
health and medical care establishment;
sports and recreation centre;
civic and community institution; or
building designated for conservation under the Planning Act 1998.
Subregulation 3
The excluded street works referred to in paragraph (2) are those relating to —
the construction of a new street;
the continuation of an existing street;
the adaptation of a street made for foot traffic only for carriage traffic;
the introduction or modification of any road related facility; or
the introduction or relocation of any covered linkway.