Singapore legislation
Regulation 2
of Electricity (Taser Power Pte. Ltd. — Exemption from Section 6(1)) Order 2022
Regulation 2
Exemption
Subregulation 1
Section 6(1)(b) of the Act does not apply to Taser Power Pte. Ltd. (called in this paragraph TPP) in respect of its transmission of electricity under the following conditions:
the electricity is generated by TPP’s generating unit in Lot 5160V in Mukim No. 7 at 92 Tuas South Avenue 3, Singapore 637368; (b)the electricity is transmitted to and consumed by the cooling water pumps 1 and 2 on the premises of the Public Utilities Board in Lot 5159T in Mukim No. 7 at 92 Tuas South Avenue 3, Singapore 637368;
the cooling water pumps 1 and 2 convey sea water to TPP’s generating unit mentioned in sub‑paragraph (a) for the purpose of cooling the generating unit;
TPP is a generation licensee;
TPP complies with any direction given by the Authority under section 17 of the Act in respect of the transmission of electricity.
Subregulation 2
In this paragraph, “Public Utilities Board” means the Public Utilities Board continued under section 3 of the Public Utilities Act 2001.