Singapore legislation
Regulation 5
Regulation 5
Deployment of specified EV chargers for approved trial
Subregulation 1
The specified person may only install, deploy, operate and maintain any specified EV charger within the specified area during and for the purposes of the approved trial.
Subregulation 2
In carrying out any of the activities described in paragraph (1) in respect of any specified EV charger, the specified person must ensure that —
(a)
the specified EV charger does not pose any hazard to, or endanger, any person or property; and
(b)
appropriate measures are taken to abate or minimise any nuisance or inconvenience caused by the installation, deployment, operation or maintenance of any specified EV charger.