High Court · Decided 24 September 2008
Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd
Feedback & support[2008] SGHC 159 · Case no. OS 894/2008, SUM 3242/2008 · 94 paragraphs
✱ What happened, in plain English
There is no plain-English summary of this judgment yet.
Ask about this judgment →Grounds of decision
Official text from eLitigation
- [1]
[1] This application addresses the question of whether an adjudicator’s interpretation of a certain key provision of the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the SOP Act”) was compatible with the requirements of natural justice.
- [2]
[2] The SOP Act provides for a scheme of “adjudication” by which disputing parties in a construction contract can obtain a quick, interim decision by an impartial adjudicator on whether, and how much, one should pay the other. This regime operates alongside other lengthier forms of dispute resolution which the parties may be concurrently engaged in, such as litigation or arbitration. The summons before me sought to set aside an adjudication determination arising from this procedure.
- [3]
[3] As a prelude to the adjudication process, the claimant has to submit a payment claim to the respondent, who in turn is supposed to submit a payment response to the claimant within a statutorily mandated timeframe. Among other things, a payment response would contain the respondent’s reasons why it was entitled to withhold payment from the claimant.
- [4]
[4] In the present case, Ssangyong Engineering & Construction Co Ltd (“the Respondent”) did not serve a payment response on Chip Hup Hup Kee Construction Pte Ltd (“the Claimant”) within the stipulated time. Before the Adjudicator, Mr Goh Phai Cheng SC, the Respondent sought to raise certain reasons why it was justified in withholding payment. These reasons had been included in a payment certificate (provided to the Claimant after the time for making a payment response had passed) as well as in an adjudication response. The Adjudicator took the view that he was precluded by s 15(3) of the SOP Act from giving any consideration to such reasons as they had not been contained in any payment response made within the stipulated time. That being the case, he awarded the Claimant the full amount under its payment claim (“the Adjudication Determination”).
- [5]
[5] The Respondent asked me to set aside the Adjudication Determination on the basis that the Adjudicator wrongly interpreted s 15(3) of the SOP Act and had offended the rules of natural justice by denying the Respondent the opportunity to be heard. Having reserved judgment at the hearing, I have come to that the application should be dismissed. As the SOP Act is a relatively recent piece of legislation with little judicial explication of its provisions, I give my detailed reasons below.
The facts
- [6]
[6] The construction works in question were a part of the proposed Marina Bay Sands Integrated Resort. The Respondent is the main contractor for the construction works in relation to the hotel portion of that project, and the Claimant was appointed the sub-contractor for the reinforced concrete structural works of that portion of the project by means of a letter of acceptance dated 3 September 2007. The sub-contract sum was for $12,000,000.
- [7]
[7] Various disputes arose between the parties, boiling down to cross-allegations of contractual breaches by both parties. On 21 April 2008, the Claimant served Progress Claim No. 5 on the Respondent for the sum of $1,616,207.149. Under s 11 of the SOP Act, the deadline for the Respondent to submit its payment response was 12 May 2008 (i.e. 21 days after the service of Progress Claim No. 5). However, no payment response was served by the end of this period.
- [8]
[8] On 17 May 2008, by way of letter, the Claimant reminded the Respondent to provide its payment response. However, there was still no payment response forthcoming during the dispute settlement period mandated under s 12 of the SOP Act (i.e. the 7-day period after 12 May 2008).
- [9]
[9] On 22 May 2008, after the expiry of the dispute settlement period, the Claimant gave the Respondent a Notice of Intention to Apply for Adjudication as required by s 13(2) of the SOP Act. On the same day, the Claimant submitted its Adjudication Application for Progress Claim No. 5 (“the Adjudication Application”) under s 13(1) of the SOP Act to the Singapore Mediation Centre (“SMC”) as an authorised nominating body. The application identified the contract type as a construction contract for the provision for works and services, and that the nature of the dispute was a “failure to respond with payment response.” The claimed amount was $1,103,101.49.
- [10]
[10] The following day, 23 May 2008, the SMC served a copy of the Adjudication Application on the Respondent, as required by s 13(4) of the SOP Act, and informed the Respondent that it had to lodge its Adjudication Response within seven days.
- [11]
[11] The Respondent provided a copy of Payment Certificate No. 5 to the Claimant on the same day, which certified the value of the works done to be only $659,196.82. It further listed certain back-charges allegedly owed by the Claimant to the Respondent totalling $515,635.01. According to the Respondent, these had arisen for four reasons:
- [12]
[12] On 29 May 2008, the SMC notified the Claimant that Mr Goh had been appointed as the Adjudicator. On 30 May 2008, the Respondent submitted Adjudication Response SOP/AA22/2008, which included Payment Certificate No. 5 as a supporting document. On 4 June 2008, the Claimant’s solicitors wrote to the Adjudicator objecting to, among other things, the inclusion of Payment Certificate No. 5 and the reasons for withholding amounts stated therein. The Respondent’s solicitors wrote back on 6 June 2008, disagreeing with that position.
- [13]
[13] In the meantime, the parties were still fighting over related issues on the site. The sub-contract was terminated sometime in late May or early June 2008. The parties dispute who had repudiated the sub-contract. In other developments, on 3 June 2008, the Respondent had commenced Suit No. 379 of 2008 against the Claimant, and also applied for an interim injunction by way of Summons No. 2403 of 2008 to compel the Claimant to vacate the project site. The latter injunction was granted on 3 June 2008. The suit was discontinued on 21 July 2008.
- [14]
[14] The parties attended an Adjudication Conference on 13 June 2008 at the Adjudicator’s office. The Adjudication Determination in favour of the Claimant was issued on 25 June 2008, containing the following terms:
- [15]
[15] The Respondent did not pay any part of the adjudicated amount by the date specified, and the Claimant commenced the present originating summons pursuant to s 27 of the SOP Act on 3 July 2008 in order to obtain leave of court to enforce the Adjudication Determination in the same manner as a judgment or order of the court. This was granted. The Respondent then filed this present summons under s 27(5) of the SOP Act and paid the unpaid portion of the adjudicated amount into court as security as required by the provision. The summons prayed that:
- [16]
[16] Prayers for a stay of proceedings or a holding of security by the court pending final determination of the substantive dispute by a court or arbitration tribunal contained in the summons were not pursued at the hearing before me.
The issue stated
- [17]
[17] In the Adjudication Determination, the Adjudicator stated that there were two issues before him. These were:
- [18]
[18] The second question was answered in the affirmative. The Respondent did not make any arguments before me on that point and I will not discuss it further.
- [19]
[19] The first question is the heart of the present application. Section 15(3) of the SOP Act states:
- [20]
[20] The Adjudicator noted that it was not in dispute that Payment Certificate No. 5 was provided neither within the 21-day period stipulated under s 11 of the SOP Act nor the 7-day dispute settlement period stipulated in s 12(4) of the SOP Act. His holding can be found at [31] of the Adjudication Determination:
- [21]
[21] The Adjudicator then quoted a breakdown of the claimed amount from the Notice of Intention to Apply for Adjudication. He obtained clarification from the Claimant that the claimed amount of $1,103,101.49 was arrived at after subtracting certain payments and deductions in respect of Progress Claim Nos. 3 and 4 from the amount of $1,616,207.15 in Progress Claim No. 5. He concluded at [41] of the Adjudication Determination as follows:
- [22]
[22] Before me, the Respondent argued that the Adjudicator was wrong to interpret s 15(3) of the SOP Act to completely exclude all aspects of the Respondent’s case, and that such an interpretation constituted a failure to carry out his quasi-judicial responsibilities to ensure that justice was done; in particular, he had failed to comply with his obligations to abide by the rules of natural justice as required under s 16(3) of the SOP Act.
The SOP Act and foreign legislation
- [23]
[23] The SOP Act is based on Building and Construction Industry Security of Payment Act 1999 of New South Wales (“the NSW Act”), which in turn is based on the UK Housing Grants, Construction and Regeneration Act 1996 (“the UK Act”). The broad aims of these enactments are similar to ours and the structural similarities, in particular relation to the NSW Act, are striking. In the proceeding analysis, I will therefore make reference to cases from these jurisdictions where appropriate. Where differences are material, this will also be highlighted.
Preliminary issues: The scope of the present application
- [24]
[24] As a preliminary but important point, I wish to make two brief comments on the scope of setting aside applications under the SOP Act. My first point relates to whether the substantive merits of an adjudicator’s determination ought to be examined by a court hearing a setting aside application. The boundaries of such applications under the SOP Act are not entirely clear. Indeed, reference to setting aside in the SOP Act is only oblique. Section 27(5) of the SOP Act states:
- [25]
[25] What is clear is that the setting aside application is not an appeal. The SOP Act already provides a limited right of reviewing the substantive correctness of the adjudication determination through the adjudication review procedure under ss 18 and 19. (I say it is limited because there is only such a right for the respondent, and then only if the adjudicated amount exceeds the relevant response amount by a prescribed amount: s 18(1) of the SOP Act. The prescribed amount is presently $100,000: s 10(1) of the Building and Construction Industry Security of Payment Regulations (Cap 30B, Regulation 1) (“the SOP Regulations”). Section 18(1) of the SOP Act presupposes that there has been a payment response made and thus is also not available to respondents who fail to give a payment response.) The panel of review adjudicators may substitute their determination of the appropriate adjudication amount for the previous adjudication determination.
- [26]
[26] Given the availability of the adjudication review procedure, it is not surprising that a court considering a setting aside application should not be concerned with substantive issues. Such was the view of the parties before me, who agreed not to touch upon the merits of the Adjudication Determination during the hearing. The Respondent did, however, touch briefly on the merits of the Adjudication Determination in his written submissions for the sake of completeness, but did not press these matters at the hearing.
- [28]
[28] The second point I wish to make concerns whether I am limited to considering jurisdictional issues only in hearing this application. The Claimant had initially argued that there was no jurisdictional issue to be tried and there was thus no ground for me to set aside the Adjudication Determination. It argued that the proper approach was for the Court to ask if the adjudicator had considered the right question, and that if he had, then even if he came to the wrong conclusion, he would still be acting within his jurisdiction. It was submitted that such a decision should not be interfered with.
- [29]
[29] The question asked by the Adjudicator in this case was whether he could consider the reasons for withholding payments which were not included in a relevant payment response under s 15(3) of the SOP Act. This was a question of law. It may be that an error in answering that question would merely be a non-jurisdictional error of law, which is what the Claimant’s argument is suggesting. But I think that it is more important to note that the question raises issues of natural justice. The adjudicator’s obligation to comply with the rules of natural justice is enshrined in s 16(3) of the SOP Act. My own view is that a court examining a setting aside application can review the adjudicator’s decision for compliance with those requirements, quite apart from issues of jurisdiction. As the Claimant himself eventually conceded during the hearing on my prompting, a breach of natural justice would constitute grounds for setting aside the Adjudication Determination.
- [30]
[30] In New South Wales, it was previously the case that judicial review of an adjudicator’s determination was not available for all non-jurisdictional errors of law: Musico v Davenport [2003] NSWSC 977. However, in Brodyn Pty Ltd v Davenport [2004] NSWCA 394, Hodgson JA for the New South Wales Court of Appeal stated that beyond jurisdictional errors, an adjudication determination also had to comply with what he called “basic and essential requirements” of the existence of a determination. Natural justice forms one of these basic and essential requirements, as he explained at [57]:
- [31]
[31] The above dicta is exactly on point for the instant case. If the Respondent is right that s 15(3) of the SOP Act did not prevent the Adjudicator from consider its reasons for withholding payment, then the latter must have committed a breach of natural justice by ignoring the Respondent’s submissions.
- [32]
[32] Likewise, under s 108(2)(e) of the UK Act, an adjudicator is obliged to act impartially, just as in s 16(3) of the SOP Act. It has been established in that jurisdiction that a breach of natural justice is a reason not to enforce an adjudication determination: AMEC Capital Projects Ltd v Whitefriars City Estates Ltd [2005] BLR 1, a case involving allegations of apparent bias.
- [33]
[33] The two points made above are consonant with those of the learned author of Security of Payments and Construction Adjudication (LexisNexis, 2005), who states at p 497 in relation to the SOP Act:
Substantive issue: Whether the Adjudicator was right not to consider the Respondent’s reasons for withholding payment
- [34]
[34] Although the Respondent apparently put its arguments solely in terms of s 15(3) of the SOP Act, I found that it was really making a two-prong argument. The first prong was that s 15(3) of the SOP Act ought to be interpreted in such a manner as to oblige the Adjudicator to consider the Respondent’s reasons for withholding payment. I think the Respondent’s main submission on this point was that s 15(3) of the SOP Act did not apply to cases where there was no payment response submitted, such as the present case, because of considerations of natural justice. I propose to deal with this argument in the following manner: First, I would examine what a literal reading of the provision suggested. Next, I would consider whether the requirements of natural justice obliged me to interpret the provision in a different manner. This would involve a general discussion of the policy behind the SOP Act and how this ought to colour the interpretation of s 15(3) of the SOP Act, as well as a more particular consideration of whether the Adjudicator’s approach denied the Respondent a fair hearing.
- [35]
[35] The second prong was not so clearly highlighted in the Respondent’s submissions as a distinct line of argument, but I think it is in fact an argument in the alternative to the first. The Respondent sought to argue that other provisions of the SOP Act, in particular s 16(7), obliged the Adjudicator to consider all the documents and information available to him, which would include Payment Certificate No. 5, the Adjudication Response and the submissions made thereon.
Interpretation of s 15(3) of the SOP Act
Literal interpretation
- [36]
[36] The first question to ask is whether Payment Certificate No. 5 could be construed as a payment response. In that regard, does the reference to the “relevant payment response” in s 15(3) of the SOP Act refer to payment responses made in time, or can it also refer to late payment responses? If it is the latter, then the Adjudicator should have considered the reasons contained in Payment Certificate No. 5, even though it was not tendered in either the earlier 21-day period or the later 7-day dispute settlement period.
- [37]
[37] From a literal reading, the latter interpretation is not supported. A “payment response” is defined in s 2 of the SOP Act as (in relation to a construction contract) “a response to a payment claim made by a respondent under section 11 (1) or 12 (4)”. Both of these provisions deal with the specific timelines in which a payment response may be provided. The former provision reads:
- [38]
[38] The latter provision, under subsection (b), stipulates that even if a respondent has failed to provide a payment response under the s 11(1) deadline, he still has a second chance to do so during the subsequent dispute settlement period. For completeness, it should be noted that the dispute settlement period is defined in s 12(5) of the SOP Act as “the period of 7 days after the date on which or the period within which the payment response is required to be provided under section 11 (1).”
- [39]
[39] It follows that a payment response is a response which is made during either of these two periods. As noted by the Adjudicator, Payment Certificate No. 5 was only issued after these two periods had expired. Thus, it cannot be considered as “the relevant payment response” under s 15(3) of the SOP Act. In effect, by a literal reading of the provision, there can no such thing as a “late” payment response; any purported response tendered out of time is not a payment response at all. Following this logic, the Respondent had failed to provide any payment response. A plain reading of s 15(3) of the SOP Act would thus support the adjudicator’s decision not to consider any of the Respondent’s reasons why it withheld payment at all.
Consistency with natural justice
- [40]
[40] The Respondent appears to accept that Payment Certificate No. 5 was not a payment response because it was not tendered in time. The focus of its argument was that, nevertheless, s 15(3) of the SOP Act could not be interpreted in a manner which prevented it from raising its reasons for withholding payment at the adjudication hearing as such an interpretation would be inconsistent with natural justice. The Respondent would have been deprived of an opportunity to have his case heard. The proper interpretation of s 15(3) of the SOP Act, the Respondent argued, would be to confine it to cases where a payment response had been tendered and not, as in the present case, where there was no payment response.
- [41]
[41] In support of this argument, the Respondent submitted that Parliament would have intended the SOP Act to be fair and just. As a general proposition, that submission is undoubtedly correct. A passage from Waugh v Pedneault [1949] 1 WWR 14 at 15, was cited to me:
- [42]
[42] The same principle has been forcefully described in another much-cited passage by Lord Bridge in Lloyd v McMahon [1987] AC 625 at 702:
- [43]
[43] In the present case, not only is there an obligation to read the SOP Act in accordance with the rules of natural justice, but also, adherence to such rules is prescribed in the SOP Act itself. Section 16(3) of the SOP Act reads:
- [44]
[44] In the instant case, the Respondent has alleged that its submissions on the reasons why it was entitled to withhold payment were not heard by the Adjudicator. This is an invocation of the rule of natural justice which stipulate that every man has a right for his defence to be heard, otherwise known as audi alteram partem. Such a rule, as has been colourfully stated by Fortescue J in R v University of Cambridge (1723) 1 Str 557, is of ancient and noble vintage:
- [45]
[45] The point has been reiterated by the Court of Appeal in the recent case of Kay Swee Pin v Singapore Island Country Club [2008] 2 SLR 802 at [7]:
- [46]
[46] These rules are simple to state and uncontroversial, but as usual, the devil is in the details. Was it a breach of natural justice for the Adjudicator to have disregarded the reasons for withholding payment put forth by the Respondent in its Payment Certificate No. 5 and its Adjudication Response?
The purpose of the SOP Act
- [47]
[47] As I have stated earlier, the literal reading of s 15(3) of the SOP Act clearly supported the Adjudicator’s decision. In such a case, a court would be leery of legislating from the Bench by imputing a different interpretation to those clear words. Lord Reid has stated in Wiseman v Borneman [1971] AC 297 at 308:
- [48]
[48] What then was the apparent purpose of the SOP Act? The Act, enacted on 1 April 2005, came into being during a time of grave difficulty for the construction industry. The rationale for the legislation was spelt out by the Minister of State for National Development at the Second Reading of the Building and Construction Industry Security of Payment Bill (“the SOP Bill”) on 16 November 2004 at Col 1112:
- [49]
[49] The efficiency of the adjudication process and the assurance of a smooth cash flow even in the event of disputes are thus hallmarks of the SOP Act. In this respect the SOP Act is no different from the UK Act. Dyson J in Macob Civil Engineering Ltd v Morrison Construction Ltd [1999] CLC 739 said at [14]:
- [50]
[50] These special considerations influence how the established canons of natural justice would be applied in relation to the SOP Act. I have quoted Lord Reid’s comment that “the so-called rules of natural justice are not engraved on tablets of stone”: at [42] above. There are numerous other learned pronouncements to the same effect: Lord Denning MR in R v Gaming Board for Great Britain ex p. Benaim and Khaida [1970] 2 QB 417 at 439, saying that “it is not possible to lay down rigid rules as to when the principles of natural justice are to apply: nor as to their scope and extent. Everything depends on the subject-matter”; or Sachs LJ in Re Pergamon Press Ltd [1971] Ch 388 at 403, stating that “in the application of the concept of fair play there must be real flexibility.” Justice, whether performed by a court, a tribunal or any quasi-judicial body, is a balancing exercise between thoroughness and timeliness. More formal settings, such as litigation through a court, would tend to emphasis the former. The adjudication process under the SOP Act instead chooses a quicker, but somewhat less thorough, means of achieving justice. This is a general theme which pervades the SOP Act and in itself is not a ground for saying that natural justice has been denied.
- [51]
[51] I accept that a respondent would face what are admittedly rather tight deadlines for the submission of its payment response under ss 11(1) and 12(4) of the SOP Act. A respondent has, depending on the terms of the contract, only between 7 to 21 days in which it can make its response. This can pose certain difficulties in some cases where the payment claim raises many complicated issues which the respondent must address. (In relation to the following paragraphs, I would expressly reserve my views on whether it is possible to do natural justice for a respondent in the timelines given in cases of exceptional complexity or where the claimant delivers a payment claim just before a long holiday period: c.f. Judge Toulmin CMG QC’s comments in AWG Construction Services Ltd v Rockingham Motor Speedway Ltd [2004] TCLR 6 at [123] in relation to the UK Act.)
- [52]
[52] But for the usual case, and certainly for the present case, it is important to understand that the efficiency of the process places pressures on everyone else involved as well. Under s 13(1) of the SOP Act, the claimant must make his adjudication application within 7 days of the date when his entitlement to make such an application arises. An adjudication application served out of time will be ignored by the adjudicator: s 16(2)(a) of the SOP Act. The adjudicator himself has, subject to the agreement of the parties, only between 7 to 14 days from the commencement of the adjudication to make his adjudication determination: s 17(1) of the SOP Act.
- [53]
[53] Furthermore, while it may seem that the timelines lean in favour of the claimant, it must be remembered that the adjudication determination reached at the end of the process is only an interim determination made in order to promote a smooth cash flow. While such determinations are binding on the parties under s 21(1) of the SOP Act, the rights of any party to challenge the adjudication determination in any proceeding before a court or tribunal or in any other dispute resolution proceeding are unaffected: s 21(3) of the SOP Act. Section 34(1) of the SOP Act also makes it clear that parties are free to pursue any other dispute resolution proceeding concurrently with the adjudication process. In making the preceding comments, I am not saying that defects in procedure in one set of proceedings can be ignored so long as some rectification can be made in different proceedings. Rather, the adjudication process must be understood in its larger context, being, as it were, the handmaiden of more formal dispute resolution procedures, in that it supplies timeliness where the other kinds of proceedings provide thoroughness.
- [54]
[54] The Respondent argued that the Claimant would not be prejudiced by its more liberal interpretation of s 15(3) of the SOP Act as, although Payment Certificate No. 5 was not technically a payment response, it still informed the Claimant the case which the Respondent was going to mount; that is, the Claimant would not have been caught by surprise at the adjudication hearing.
- [56]
[56] Also, if s 15(3) of the SOP Act were to apply only to respondents who did tender a payment response, it would result in the perverse situation where such respondents were in a worse position than respondents who did not tender any payment response at all. Such a situation is obviously unfair.
- [57]
[57] Furthermore, there is a strong connection between the general policy of efficiency described above at [48] and [49] and the more specific concern embodied in s 15(3) of the SOP Act, which is that the respondent should make the reasons for withholding payment known as early as possible in the proceedings. Ironic as it may seem, the goal of the entire adjudication process is not to reach an adjudication determination. The SOP Act recognises that the fastest and most efficient means of disposing of the dispute is through settlement, and this ideal is enshrined in the dispute settlement period provided for in ss 12(4) and 12(5) of the SOP Act. In order for such dispute settlement negotiations to even take place, it is essential for the SOP Act to encourage the parties to air their respective positions as early as possible. Hence, from this angle, it is not unreasonable to require a respondent to make his reasons known sooner rather than later. In this respect, no purpose is served by allowing him to play with his cards close to his chest.
- [58]
[58] The position I have articulated above is generally consistent with reported decisions by various adjudicators under the SOP Act. In Company BO v Company BP [2006] SGSOP 12, there was no payment response served, whether in the initial 21-day period or the subsequent 7-day dispute settlement period. However, an adjudication response was served with what the adjudicator called “an attached payment response.” The respondent argued that s 15(3) of the SOP Act only applied when there was no payment response, but did not preclude the adjudicator from considering a late payment response attached to the adjudication response. This argument was rejected by the adjudicator who noted:
- [59]
[59] Similarly, in AA Pte Ltd v AB Pte Ltd [2005] SGSOP 1, the respondent tendered a letter in response to the claimant’s payment claim within 21 days of the receipt of the payment claim. It was argued that this letter constituted a payment response. However, the adjudicator found that the letter could not be so considered. He went on:
- [60]
[60] On the other hand, the Respondent raised some dicta in AR Pte Ltd v AS Corp [2006] SGSOP 6, at [22], where the adjudicator said:
- [61]
[61] The Respondent’s argument was that the use of the word “or” suggested that the provision of an adjudication response without a payment response would have led to a different result. I do not think the adjudicator was trying to make that point, and if he was, I would nevertheless prefer the approach of the cases cited earlier.
- [62]
[62] Before I leave this subject, I should say that instruction can be drawn from the approach in New South Wales. What we call a payment response is termed a “payment schedule” in s 14 of the NSW Act. The provision states:
- [63]
[63] It should be noted that the NSW Act provides two time periods for the submission of a payment schedule. The first is under s 14(4) and the second is under s 17 of the NSW Act:
- [64]
[64] Another provision of note is s 20 of the NSW Act, which provides for the adjudication response by the respondent. Section 20 states:
- [65]
[65] Finally, s 22 of the NSW Act provides:
- [66]
[66] These provisions are interpreted strictly. In Taylor Projects Group Pty Limited v Brick Dept Pty Limited and Ors [2005] NSWSC 439, a payment claim was served on the respondent on 5 January 2005. The respondent was thus supposed to have served its payment schedule by 19 January 2005. The respondent tendered a “payment schedule” only on 20 January 2005 at about 10 a.m., disputing the sum payable. On the same day, at about 5 p.m., the claimant asserted the respondent’s failure to tender a payment schedule in time and notified the respondent of its intention to apply for adjudication under s 17(2)(a) of the NSW Act if a payment schedule was not tendered within five business days thereafter. Later that same day, the respondent informed the claimant by fax that the document served on 20 January 2005 was a payment schedule served in time as the payment claim had been served on 6 January 2005 and not the day before as the claimant asserted. On 27 January 2005, the respondent sent a fax to the claimant stating that a payment schedule had already been served within time, and the claimant’s request for a payment schedule was thus unnecessary.
- [67]
[67] The adjudicator determined that the payment claim had indeed been served on 5 January 2005 and thus the “payment schedule” of 20 January 2005 was out of time. The claimant had given its s 17(2)(b) notice on 20 January 2005 at 5 p.m., and the respondent thus had to provide a payment schedule within 5 business days thereafter. The faxed document provided earlier that morning at 10 a.m. did not satisfy that requirement as it was served before the notice and there was no other payment schedule tendered after the notice. In such circumstances, the adjudicator could not consider the respondent’s payment schedule and its adjudication response (see s 20(2A) of the NSW Act).
- [68]
[68] In seeking to have the adjudicator’s decision declared void it was argued by the respondent that it had indeed submitted payment schedule, albeit falling between the ss 14(4) and 17(2)(b) periods, but such an error was “a technical infringement incapable of causing prejudice to the claimant or adjudicator” which would nonetheless” substantially prejudice the respondent’s rights in the adjudication process.” Requiring the respondent to re-submit a payment schedule for form’s sake just after it had submitted an earlier (albeit out-of-time) payment schedule would “promote public inconvenience.”
- [69]
[69] The court upheld the adjudicator’s decision. In adopting a strict construction of the NSW Act provisions, the court said:
- [70]
[70] A similarly strict approach is taken with regards to situations where a respondent has tendered a payment schedule in time, but is seeking to rely on reasons for withholding payment not contained in its payment schedule but only in its adjudication response. In Multiplex Constructions Pty Ltd v Luikens and Another [2003] NSWSC 1140 at [67] Palmer J said:
- [71]
[71] The Respondent tried to distinguish these cases on the basis that under the NSW Act, the failure to file a payment schedule results in the respondent becoming liable to pay the claimed amount on the due date for the progress payment to which the payment claim relates: s 14(4) of the NSW Act. A respondent then has a choice whether he wishes to recover the debt or apply for adjudication: s 15(2)(a) of the NSW Act. Under our Act, a failure to file a payment response does not give rise to a payable debt and a claimant still had to obtain an adjudication determination first. The Respondent submitted that this distinction explained why a strict approach was adopted.
- [72]
[72] I do not think that the existence of the respondent’s liability under the NSW Act once it fails to tender a payment schedule is a crucial in this respect. Section 14(4) of the NSW Act merely provides the claimant a short-cut to obtaining payment at its option. The provision of such an option to the claimant does not affect the rationale for the early provision of reasons by the respondent in respect of the adjudication process (that is, the adjudication hearing and the consequent determination).
Not a denial of a fair hearing
- [73]
[73] The Respondent submitted that the approach taken by the adjudicator would mean that a respondent who did not submit a payment response would in effect not be entitled to any adjudication at all, since he was not entitled to raise any reasons for withholding payment. It was argued that s 12(2) of the SOP Act sets out two situations where a claimant may make an adjudication application. Section 12(2)(a) of the SOP Act contemplated a situation where a claimant disputed a payment response which had been tendered, while s 12(2)(b) of the SOP Act contemplated another situation where there was no payment response tendered. In both cases, s 13(1) of the SOP Act applied, and that provision states:
- [74]
[74] According to the Respondent, the effect of s 13(1) read with s 12(2)(b) of the SOP Act was that there had to be an “adjudication” even when there was no payment response. That word, in its plain and ordinary meaning, meant “the act or process of trying and determining judicially.” Thus, in order to enable the adjudicator to perform an adjudication, the respondent ought to be allowed to air its views. It followed that s 15(3) of the SOP Act should be interpreted to be limited to situations where a payment response had been tendered.
- [75]
[75] In my view, there are two points which should be borne in mind. The first is that natural justice requires that a respondent be given a fair opportunity to be heard. There is no requirement that in every case a party is actually heard and it is entirely possible for a party to forfeit his right to be heard through some procedural default. In the instant case, it is clear that the SOP Act does afford a respondent the opportunity to be heard. In regard to the hearing of a respondent’s reasons why payment was withheld, the SOP Act specifies that such hearing is contingent on the reasons being provided in the payment response tendered within certain timelines. What has really happened in this case was that the Respondent chose not to avail itself of the opportunity to be heard on its reasons for withholding payment.
- [76]
[76] But even if a respondent who failed to submit a payment response is not allowed to put forward its reasons why it withheld payment, it does not follow that it would be denied any sort of hearing at all. Quite unlike what the Respondent sought to suggest, it is not the case that the adjudication process becomes a mere rubber-stamping exercise in favour of the claimant. The adjudicator is still obliged to exercise his discretion in a number of matters which a respondent is fully entitled to raise.
- [77]
[77] For instance, I think it is quite undisputable that a respondent can raise procedural arguments based on facts which had arisen only after the due date for a payment response has passed. In AU v AV [2006] SGSOP 7, no payment response had been filed in time. The adjudicator found that he had jurisdiction to adjudicate on the question raised by the respondent in its adjudication response of whether the notices and adjudication applications were filed in time in relation to the first two of three payment claims (or “tax invoices” as they were called in the case). He said:
- [78]
[78] Similarly, in Company BQ v Company BR [2006] SGSOP 13, the adjudicator was of the view that the respondent’s failure to provide a payment response did not stop him from hearing the respondent’s arguments on whether the subcontract was excluded from the SOP Act because it was allegedly made within a period not exceeding 6 months from 1 April 2005 (regulation 4(a) of the SOP Regulations). He also thought it proper to consider whether the adjudication application was made prematurely, and whether it was irregular as it stated a different claimed amount from the payment claim annexed to it and the payment claim submitted to the respondent.
- [79]
[79] The more difficult question is whether an adjudicator may deal with arguments regarding the validity of the payment claim on which the adjudication is based. In AU v AV (above at [77]), the adjudicator thought that s 15(3) of the SOP Act excluded any argument that the third tax invoice did not comply with content requirements of s 10(3) of the SOP Act and regulation 5(2) of the SOP Regulations and thus was an invalid payment claim. He agreed, at [21], with the claimant’s submission that the respondent should have raised this issue in its payment response.
- [80]
[80] In AA Pte Ltd v AB Pte Ltd (above at [59]), the adjudicator was prepared to consider a jurisdictional question of whether there was “a contract made in writing” between the parties as required by s 4(3) of the SOP Act. He also considered whether the payment claim was made out of the time stipulated in s 10(2) of the SOP Act. Finally, he also heard an argument that a purposive reading of the dispute settlement provisions of the SOP Act mandated that the claimant should alert the respondent to consider a settlement during the dispute settlement period. However, he refused to consider the respondent’s argument that the claimant had failed to submit a performance bond, which was a condition precedent to it making any payment claim under the contract. The respondent argued that the claimant was thus not entitled to have submitted any payment claim at all. The adjudicator said at [72]:
- [81]
[81] These authorities can be contrasted with another case which suggests that the invalidity of a payment claim can be raised before the adjudicator even if these were not contained in any payment response. In Company BO v Company BP (above at [78]), the adjudicator allowed the respondent to contend that s 10(1) of the SOP Act permitted a claimant to serve only one payment claim in respect of a progress payment; that the payment claim submitted was a final claim which the SOP Act did not apply to; and that the payment claim was submitted late. While the adjudicator eventually did not find these objections to have merit, he nonetheless gave them consideration. He had these words to say at [23] about the claimant’s argument that it was impermissible to raise these issues as they were not contained in the adjudication response:
- [82]
[82] My own preference is for a stricter interpretation of s 15(3) of the SOP Act. The invalidity of a payment claim is a reason for withholding payment that would have been known at the time when the payment claim was submitted, and as such, it ought to have been included in a payment response. However, this issue was not squarely before me and I make no definite decision on it.
- [83]
[83] Whether or not the invalidity of a payment claim can be brought up when such a reason was not asserted in a payment response, it is clear that even in cases where no payment response has been tendered, it is possible for a respondent to at least argue that there were procedural irregularities arising after date on which the payment response was supposed to be filed, if the facts so permit. An adjudicator is obliged to make a determination on those issues and it is incorrect to say that an adjudication would be a mere rubber-stamping exercise.
Conclusion on natural justice and s 15(3) of the SOP Act
- [84]
[84] The Respondent is essentially urging me to read additional requirements into s 15(3) of the SOP Act in order to make that provision conform to what it submitted was natural justice. Recalling Lord Reid’s dicta in Wiseman v Borneman (above at [47]), I conclude that it was not clear that the statutory procedure under the SOP Act was insufficient to achieve justice. A plain and literal reading of s 15(3) of the SOP Act would not result in the Respondent being denied a fair opportunity to be heard. Indeed, the “additional steps” suggested by the Respondent—in this case, the dis-application of s 15(3) of the SOP Act to cases where no payment response was submitted—would frustrate the apparent purpose of the legislation.
Consideration of the documents available to the adjudicator
- [85]
[85] Apart from the above submission, the Respondent also relied on s 16(7) of the SOP Act, which states:
- [86]
[86] It was argued that, quite apart from any restrictions placed by s 15(3) of the SOP Act, this provision directed the adjudicator to give his consideration to whatever documents and arguments were before him. In the instant case, even if the Respondent was prohibited from raising its reasons for withholding payment, the Adjudicator still ought to have given consideration to Payment Certificate No. 5 and the reasons contained therein as well as the arguments raised orally at the hearing. It was thus incorrect for him to have simply accepted the Claimant’s figures without more.
- [87]
[87] I do not accept this argument. In the first place, the provision is clearly permissive rather than mandatory. Furthermore, its obvious purpose was to enable an adjudicator to continue with the adjudication despite any attempts to hold up the process by any party. It does not compel the adjudicator to give consideration to any matter not contained in s 17(3) of the SOP Act. The learned author of Security of Payments and Construction Adjudication (above at [33]) explains at p 370:
- [88]
[88] At this point, I should also deal with two cases cited by the Respondent which appear support the proposition that while the adjudicator cannot consider reasons for withholding payment not contained in an adjudication response, he nonetheless may examine the available documents to see whether they support the claimant’s claimed amount.
- [89]
[89] I will deal with the easier case first, that of Company CH v Company CI [2006] SGSOP 18. In response to a payment claim, the respondent tendered to the claimant a letter which allegedly showed that (a) the claimant had agreed to increase a discount from 8% to 14.5%, and (b) that the claimant agreed to be paid when the respondent was paid by a third company (“the 9th November Letter”). The 9th November Letter was annexed to the respondent’s adjudication response, which raised these two same reasons. The adjudicator held that the 9th November Letter was not a payment response and there was no other document produced which could be considered a payment response. He held that he was precluded by s 15(3)(a) of the SOP Act from considering the reasons given in the adjudication response, but proceeded to consider whether the 9th November Letter had been served on the claimant, whether it did indeed show that an agreement to increase the discount had been reached, and finally, whether the letter contained a “pay when paid” clause which was prohibited under s 9(1) of the SOP Act.
- [90]
[90] I do find this case somewhat odd, and but it is likely that the adjudicator was only pointing out that the respondent’s case had no merit even if the 9th November Letter was considered a valid payment response, rather than saying that the reasons in the 9th November Letter could be considered despite the fact that the reasons in the adjudication response could not.
- [91]
[91] The more difficult case is that of Company BZ v Company CA [2006] SGSOP 16, in which the adjudicator noted at [8] that the absence of a payment response meant that he had to exclude from his consideration the respondent’s counterclaim for delay and the reasons given for withholding other amounts that the respondent had only set out in the adjudication response and after, but he continued: “Nonetheless, I may determine the application on the basis of the information and documents available to me in accordance with section 16(7)” [emphasis in original]. He proceeded to consider whether the claimant was entitled to add an amount previously left out of its payment claim; what the amount of contractual back-charges to be deducted from the claim was; and whether the claimant was entitled to certain “standby charges” for two subcontracts. It is notable that he did not agree with all the claimant’s calculations and arrived at his own figures, and even more interestingly, heard counter-arguments from the respondent on the number of days which should have been used to calculate the standby charges (at [19]).
- [92]
[92] In New South Wales, the position taken there appears support the approach in the above case. In Pacific General Securities Ltd and Another v Soliman and Sons Pty Ltd and Others [2006] NSWSC 13, it was argued that the adjudicator was wrong to have simply accepted the claimed sum without examination. Brereton J held at [82]:
- [93]
[93] With respect, it appears to me that such an approach has the effect of letting the respondent introduce his reasons for withholding payment through the backdoor. It could be very soundly argued that the respondent ought to have raised all these issues in its payment response but did not do so, and the fact the adjudicator may have identified the possible reasons himself should not excuse the respondent from this duty. My own view is that where there are no reasons provided in any valid payment response, the adjudicator cannot examine whether the claimant’s claim is supported by the documents. Save for the permissible procedural or jurisdictional objections identified earlier, the adjudicator must accept the claim at its face value.
- [94]
[94] One might think this harsh—what if the payment claim states an obviously incorrect amount, either through innocent mistake or deliberate overcharging, completely unsupported by the documents or the facts? One answer to this is that the more obvious the error, the more reason why the respondent could have simply pointed this out in a valid payment response. Furthermore, this approach avoids the problem of the adjudicator having to decide whether he is merely making sure that the claimed amount is supported by the documents or whether he is impermissibly addressing the respondent’s reasons why he withheld payment. In my mind, making such distinctions will be a futile hair-splitting exercise because it is evident that one generally applicable reason why the respondent would have withheld payment is because the claimed amount is not supported by any documentary evidence. As I have stated in relation to s 15(3) of the SOP Act, I am of the view that a strict interpretation is more consonant with the overall purpose and structure of the SOP Act.
- [95]
[95] Further, I believe that there are certain crucial differences between the SOP Act and the NSW Act which would not permit us to follow their approach on this point. It would be recalled that s 15(3) of the SOP Act expressly prohibits an adjudicator from considering any reason for withholding payment which is not included in the relevant payment response. In contrast, while the NSW Act prohibits a respondent from including such reasons in its payment response, it contains no corresponding prohibition on the adjudicator from considering the same reasons. Thus, s 16(7) of the SOP Act, to the extent that it permits the adjudicator to consider the available documents and information, must be read in conjunction with the prohibition in s 15(3) of the SOP Act.
- [96]
[96] For these reasons, I reject the Respondent’s argument that the Adjudicator was incorrect in adopting the Claimant’s figures without further examining whether they were supported by the documents provided, including Payment Claim No. 5.
Conclusion