Introduction
- [1]
[1] This appeal arose from the decision of the High Court judge (“the Judge”) as reported in Geocon Piling & Engineering Pte Ltd (in compulsory liquidation) v Multistar Holdings Ltd (formerly known as Multi-Con Systems Ltd) and another suit [2015] 3 SLR 1213 (“the GD”). The Appellant, Multistar Holdings Ltd (“Multistar”), contended that the Judge erred in granting the Respondent, Geocon Piling & Engineering Pte Ltd (“Geocon”), leave to amend its statement of claim to include a new claim which was time-barred.
- [2]
[2] One of the central concerns where amendments are sought to be made after the expiry of the limitation period is whether they seek to introduce a new cause of action. An amendment that does not advance a new cause of action but rather makes good the error of failing to tell the complete story at the outset would be allowed, whereas attempts to include a claim which is distinct from those originally pleaded under the guise of an amendment would be denied where in the meantime limitation has set in in relation to that claim. In the court below, Geocon sought leave to make two sets of amendments to its statement of claim. Based on the parties’ written submissions, we initially had the impression that the first set of amendments that Geocon sought to introduce into its statement of claim fell within the latter category, until counsel for Geocon, Mr Leo Cheng Suan (“Mr Leo”), in the course of his oral submission before us drew our attention to the particulars contained in an annexure that was appended to the original statement of claim. While we observed that Geocon’s pleadings left much to be desired, we were satisfied that certain particulars contained in this annexure on the cause of action that Geocon was seeking to introduce by way of the amendment was not really “new”. Hence, we dismissed the appeal.
- [3]
[3] These grounds are issued because, while we did not overturn the Judge’s decision, some aspects of the Judge’s reasoning needed further reconsideration. First, we thought the Judge erred in defining what constitutes a new “cause of action” within the meaning of O 20 r 5(5) of the Rules of Court (Cap 322, R 5, 2014 Rev Ed) (“the ROC”). Second, the Judge fell into the error of treating the amendment as a routine application under O 20 r 5(1) of the ROC when the correct provision to apply in relation to the application should have been O 20 r 5(2) read with r 5(5) of the ROC, which requires a different test to be applied. In fact, because of this misconception, the Judge refused to even hear Multistar’s request to make further submissions on the latter set of provisions, and decided the matter solely on the basis of O 20 r 5(1). Our analysis on these two points follows hereunder.
Facts
The trial below
- [4]
[4] In the suit, Geocon claims for reimbursement from Multistar for works done in respect of two stages of a construction project. These were duly completed but the amount owing to Geocon for its services remained outstanding. Upon Geocon being wound up by its creditors, the liquidator commenced the suit to recover the debt owed by Multistar. Multistar refused to pay, and a trial was held to determine its liability to Geocon. The trial reached the submissions stage, when a ruling by the Judge on the amendment issue brought about the present appeal.
- [5]
[5] Multistar is the parent company of a group of companies in the engineering and construction business. Geocon was a wholly-owned subsidiary of Multistar. Until Geocon went into compulsory liquidation in 2006, it was the specialist piling sub-contractor in the Multistar group of companies.
- [6]
[6] In 2001, the Land Transport Authority (“LTA”) awarded a contract known as C421 to SembCorp Engineers and Constructors Pte Ltd (“Sembcorp”). Sembcorp’s scope of work under C421 was to construct part of the Kallang Paya Lebar Expressway (“KPE”) from the East Coast Park (“ECP”) to Nicoll Highway. Its scope of work included, but was not limited to, the bored piling at all locations along this stretch of the KPE.
- [7]
[7] Sembcorp subcontracted the entire scope of its bored piling works under C421 (“subcontract works”) to Multistar. The Sembcorp-Multistar subcontract was a lump sum contract, subject to variations, valued at $27.48m.
- [8]
[8] Multistar in turn sub-contracted the entire scope of its work under the Sembcorp-Multistar subcontract to Geocon. The Multistar-Geocon subcontract stipulated a price of $26m, but was otherwise expressed to be on the same terms as the Sembcorp-Multistar subcontract. Therefore, it was also a lump sum contract subject to variations.
- [9]
[9] Geocon, further subcontracted its entire scope of work under the Multistar-Geocon subcontract to a third party called Resource Piling Pte Ltd (“Resource Piling”), valued at $18.7m. Multistar was to pay the difference of $7.3m to Geocon as a project management fee.
- [10]
[10] In the carrying out of the subcontract works, Multistar bypassed the chain of subcontracts and dealt directly with Resource Piling as if the latter was a direct contractual counterparty. Resource Piling presented its progress claims directly to Multistar and in turn, progress payments were paid directly by Multistar to Resource Piling.
- [11]
[11] Resource Piling did not follow through with the subcontract works to completion. It stopped works in two stages. By late 2002, Resource Piling stopped all work at a location known as “ECP South Location”. However, it continued its work at all other locations until the end of April 2004 when it stopped work even at these other locations. At the trial below, the case that Geocon ran was that on each occasion when Resource Piling stopped work, it took over and continued the uncompleted subcontract works.
(a) GC1063, which stated Geocon’s costs incurred from January 2002 until the end of April 2004.
(b) GC1077, which stated Geocon’s costs incurred from May 2004 to the end of 2005.
- [13]
[13] In 2004, Multistar sued Resource Piling for breaching its contractual obligations on the basis that the parties were in direct contractual relationship. Resource Piling in turn sued both Multistar and Geocon. Both actions were tried together. Resource Piling emerged victorious in this set of litigation; Geocon was found liable to pay damages to the tune of $3.3m to Resource Piling. The Judge referred to this set of litigation in his GD as the “2004 Litigation”.
- [14]
[14] Geocon did not pay its judgment debt due to Resource Piling and was as a result wound up in June 2006. A liquidator was appointed for Geocon and he instituted the present action against Multistar for monies due to Geocon under the Multistar-Geocon subcontract.
- [15]
[15] The total claim which Geocon made in the present action against Multistar is for the sum of $10.9m. The original statement of claim filed on 31 January 2011 (“the Original SOC”) disclosed that this figure was arrived at as follows:
(a) $1.8m as being the sum due to Geocon in respect of GC1063;
(b) $6.75m being the total sum due to Geocon in respect of GC1077; and
(c) $2.3m being the amount overcharged by Multistar.
- [16]
[16] Multistar in its defence averred that Geocon’s claims were barred by limitation; moreover, even if limitation were not applicable to the claims, whatever claims Geocon was entitled to should be based on the rates specified in the Multistar-Geocon subcontract which was entered into between the parties and not on a reimbursement basis.
Geocon’s application to amend its SOC
- [17]
[17] The action proceeded to trial. Evidence was adduced by both Geocon and Multistar over seven days. It was only after written submissions had been tendered by both parties that Geocon applied to amend the Original SOC. To provide some context to the proposed amendments, it will be recalled that Resource Piling stopped work in two stages – first in 2002 at the ECP South Location (“the First Stage”) and second in 2004 in respect of the remaining locations (“the Second Stage”) (see [11] above). The case ran by Geocon at the trial below was that on both occasions, it took over from Resource Piling and completed the works. However, the problem is that in the Original SOC, Geocon only set out – in clear terms – facts relating to the Second Stage. The fact that it had taken over Resource Piling’s work in 2002 was not pleaded, at least not in clear and express terms.
- [18]
[18] The Original SOC read as follows:
- [19]
[19] At the trial below, Geocon led evidence on the works done in relation to the First Stage, and it was evident that Geocon wanted Multistar to reimburse it for that part of the works, on top of the works that it had done at the Second Stage. The relevant amended parts of the statement of claim read (“the Amended SOC”):
- [20]
[20] The above amendments formed the first set of proposed amendments. The second set of proposed amendments put forward four additional alternative claims against Multistar, the principal basis for which was Geocon’s alternative case that Multistar was liable on a lump-sum basis as opposed to its original case that it was liable on a reimbursement basis. We found the Judge’s summary of the second set of proposed amendments useful and we reproduce them in full as follows:
- [21]
[21] Multistar objected to both categories of amendments. It argued that the amendments would prejudice Multistar, but its arguments did not find favour with the Judge. After the Judge granted Geocon leave to amend the pleadings, Multistar requested for an opportunity to present further arguments, arguing that the amendments violated O 20 r 5(2) read with 5(5) of the ROC as it added a new cause of action that did not arise from the same facts supporting the cause of action pleaded in the Original SOC.
Decision below
- [23]
[23] The Judge also rejected Multistar’s request to make further arguments in relation to O 20 r 5(2) read with r 5(5) of the ROC. He declined to hear Multistar on the merits of the proposed line of argument (at [108] of the GD). But in his GD, the Judge went on to discuss by way of obiter dicta why, in any event, Multistar’s arguments under this heading would likely have failed. He opined as follows:
(a) The amendments did not add a new cause of action because Geocon was not seeking a different relief or remedy using the amendments; instead it was merely inserting “additional factual material” in support of its existing cause of action on the reimbursement basis (at [128] of the GD).
(b) Even if the amendments purported to add a new cause of action, they arose from substantially the same facts as those pleaded in the Original SOC. Multistar would suffer no prejudice because the evidence relating to Geocon’s amended case was already before the court and Multistar would be accorded an opportunity to address the court on the amended case (at [145] of the GD). The Judge’s basic point was, and here we quote him from his GD at [146], that even if the amended cause was new, it “arises out of precisely the same facts as Geocon’s existing cause of action” (emphasis in original).
Our decision
Overview
- [25]
[25] As is apparent from s 34(1)(a), matters listed under the Fourth Schedule, unless otherwise specified, are not appealable to the Court of Appeal. The relevant provision governing the present appeal is paragraph (g), which reads as follows:
- [27]
[27] The exception in paragraph (g) would allow Multistar’s appeal to proceed only upon the satisfaction of two conditions:
(a) at the time of the application, the applicable limitation period has expired; and
(b) the amendment would in effect add a new cause of action.
- [28]
[28] If Multistar were found to have a right to appeal under paragraph (g) of the Fourth Schedule, O 20 r 5(2) read with r 5(5) would arise for consideration. The two provisions read as follows:
- [29]
[29] O 20 r 5(2) read with r 5(5) has been said to contain four elements as follows, upon the satisfaction of which the court would have the power to allow the amendment (see Lim Yong Swan v Lim Jee Tee [1992] 3 SLR(R) 940 (“Lim Yong Swan”) at [24] and [28]; Hancock Shipping Co v Kawasaki Heavy Industries Ltd, The Casper Trader [1992] 3 All ER 132 at 135 (“The Casper Trader”), per Staughton LJ):
(a) the amendment introduces a new cause of action;
(b) the new cause of action would have been time-barred if raised in a new action on the date when the application was made;
(c) the new cause of action arises out of the same facts or substantially the same facts as the originally pleaded cause of action; and
(d) the court thinks it just to allow the amendment.
(a) Did the amendment application introduce a new cause of action?
(b) If yes, would the new cause of action be time-barred had it been raised in a fresh suit on the date of the amendment application?
(c) If yes, did the new cause of action arise out of the same facts or substantially the same facts as the originally pleaded cause of action?
(d) If yes, did the court think it is just to allow the amendment?
Cause of action
- [31]
[31] We first considered whether the amendment application introduced a new cause of action.
The legal principles
- [32]
[32] Limitation of actions imposes time-limits within which notice of claims of a particular kind must be given to the other party. In Singapore, limitation periods find expression in the Limitation Act (Cap 163, 1996 Rev Ed) (“the Limitation Act”). If the potential claimant fails to do so within the stipulated time-frame, he will be barred from bringing his claim afterwards. In the context of civil procedure, questions of limitation often arise when a claimant seeks to change the character or scope of the action after the expiry of the limitation period.
- [33]
[33] Traditionally, the English cases demonstrate that the limitation policy would apply with equal force to bar claimants from bringing fresh claims within existing actions as it would to fresh actions. The old rule of practice would not allow a claimant to amend its statement of claim if it had the effect of allowing the claimant to set up a cause of action which would otherwise be barred by the Limitation Act had it been brought by way of a fresh action (see Weldon v Neal (1887) 19 QBD 394). The reason for this position is obvious. Permitting the claimant to introduce a new cause of action against the defendant by way of an amendment instead of bringing a fresh suit would, in effect, allow him to circumvent the Limitation Act because the new claim, having been introduced into the statement of claim, will be treated as having been instituted, not on the date of the amendment, but on the date of the original writ. The operation of this concept of relation back would prejudice the defendant in that he would be deprived of his right to raise a limitation defence which would otherwise have availed to him had the claimant commenced fresh proceedings against him in respect of the new claim. A claimant who wants to amend its pleadings after the limitation period has expired would thus have to show that he is not trying to introduce a new cause of action.
- [35]
[35] It is evident that Lord Diplock was not so much concerned with the relief or remedy sought by the claimant, but rather the factual material undergirding the claim. Marshall v London Passenger Transport Board [1936] 3 All ER 83 was another case that adopted this fact-centric approach. The plaintiff alleged that he was injured by the negligent driving of a tramcar by the defendant’s servant and sought, after the expiry of the limitation period, to set up a claim in negligence by the defendants in failing to keep the highway and tramway in repair, that being a duty laid on them by statute. The amendment was not allowed because the latter allegation is premised on “quite a different allegation of fact”. Bad repair of road and the tramlines implicate a “quite new sets of facts” than would negligent driving.
Thus, notwithstanding the different labels given the court found that the cause of action was one and the same. The factual story remained substantially intact; what the plaintiff did was to give it a different legal characterisation.
- [38]
[38] The relevant rule in the “rules of court” is CPR 17.4(2) which provides:
- [39]
[39] The UK House of Lords interpreted the 1980 Act and CPR 17.4(2) to have the effect of retaining the scope of the court’s powers to allow an amendment insofar as it adds a new cause of action (Roberts v Gill & Co and others [2010] UKSC 22 at [38]).
- [40]
[40] Despite the streams of legislative changes in 1965 and 1999, English courts continued to apply the classic definitions of “cause of action” as defined by the earlier cases (see for instance, British Airways plc v Apogee Enterprises Inc [2007] EWHC 93 at [7]). This is important to our analysis because our O 20 r 5 is not only modelled after RSC O 20 r 5; both provisions are almost in pari materia.
- [41]
[41] Steamship Mutual Underwriting Association Ltd v Trollope & Colls (City) Ltd (1986) 33 B.L.R. 77 (“Steamship”) is useful insofar as it demonstrates that the legislative amendments did not alter the legal definition of a “cause of action”. In that case, the plaintiffs, building owners, had commenced an action against the contractors, the architects and the structural engineers for damages for alleged defects in the air conditioning plant in the building. Two and a half years after the delivery of the statement of claim, the plaintiffs applied to amend it to claim also damages for alleged defects in the structure of the walls. The English Court of Appeal applied Letang v Cooper and concluded that the amendments introduced a new cause of action. While both claims pertained to defects, they were treated as different causes of action because the subject matter of the defect was different.
- [42]
[42] Co-operative Group Ltd v Birse Developments Ltd and another [2013] 148 ConLR 264 was another construction case which we found useful in illustrating the concepts we have discussed. The plaintiff sued the defendant-contractor alleging cracks in the concrete floors of the warehouse constructed by the defendant. Its amendment after the expiry of the limitation period alleged that the steel fibre content within the concrete slabs was also inadequate and as a result the concrete flooring may not be able to withstand heavy load. The English Court of Appeal rejected the amendments, holding:
- [45]
[45] In Paragon Finance plc v D B Thakerar & Co (a firm) [1999] 1 All ER 400 (“Paragon Finance”), the English Court of Appeal affirmed the principles in Letang v Cooper in the following terms:
(a) Only facts which are material to be proved are to be taken into account. The pleading of unnecessary allegations or the addition of further instances or better particulars do not amount to a distinct cause of action (at 405).
(b) An amendment to make an allegation of intentional wrongdoing where previously no intentional wrongdoing was alleged constitutes the introduction of a new cause of action (at 406, 418 and 420).
- [47]
[47] In the light of these legal principles, it was apparent to us that the Judge’s definition of what constitutes a “cause of action” was erroneous. He defined the term to mean the “relief or remedy” and not the “underlying facts”. He said:
- [48]
[48] In our judgment, the Judge was wrong to have focused on the label given to the pleaded set of facts. The Judge referred to the High Court decision of Multi-Pak Singapore Pte Ltd (in receivership) v Intraco Ltd and others [1992] 2 SLR(R) 382 (“Multi-Pak (HC)”) in support of the proposition he arrived at. With respect, Multi-Pak (HC) did not quite stand for such a proposition. It was clear from Multi-Pak (HC) that Selvam JC (as he then was) took a fact-centric approach towards construing a “cause of action”:
- [51]
[51] With these principles in mind, we turn now to the facts of the present appeal.
The present facts
- [52]
[52] Applying these principles to the facts before us, we were satisfied that insofar as Geocon in the alternative claimed entitlement on the “lump sum” basis instead of the reimbursement basis, they were not new causes of action. While reimbursement and “lump sum” were different reliefs sought, they arose from different legal characterisations of the same underlying facts. No additional factual material was required to advance the alternative claims. Indeed, at the hearing of this appeal, counsel for Multistar, Mr Govind Asokan (“Mr Asokan”) was unable to point to any additional facts that underlie the alternative claims.
- [53]
[53] A slightly different analysis however applied to the first set of amendments. As was apparent from a side-by-side comparison of the Original SOC and the Amended SOC (see [18] and [19] above), the Respondent made them evidently with the intention of including in the Original SOC the factual premise that pertained to the First Stage of works, ie, works done from October 2002 to April 2004 at the ECP South Location. Only the facts relating to the Second Stage of works, ie, works done after April 2004 at the remaining locations appeared to have been pleaded in the Original SOC – at least in express terms. Mr Leo, on behalf of Geocon, initially tried to persuade us that the two set of facts were the same or substantially the same. We disagreed. The factual material in the former category was eminently different from that of the latter – it pertained to a different location and a different time frame. This is so notwithstanding the same label of relief attached to both claims, ie, a reimbursement claim. All the cases cited above expressed the same conviction on this matter – the focus is on the factual material and not the label. The First Stage of works would have entitled the Respondent to claim against the Appellant an entirely separate sum of monies and would have required the Appellant to investigate a new set of facts.
- [54]
[54] Indeed, the Judge agreed that the amendments sought to add new factual material into the Original SOC. It was only because he applied an erroneous test that led him to conclude that these new facts did not amount to a new cause of action. In his GD, the Judge focused on the label of the relief rather than the factual premises. He said:
- [55]
[55] We reiterate the reasons why the Judge was wrong in this regard at [47]–[50] above. On the face of it, and based on the written submissions tendered for the appeal, the amendments did suggest to us that Geocon was seeking to introduce a new cause of action.
- [57]
[57] Since Multistar had failed to satisfy us on the first question stated at [30] above, namely, the amendments introduced a new cause of action, we need not concern ourselves with the remaining three questions given rise to by O 20 r 5(2) read with r 5(5). It also followed from this that Multistar did not have the right to appeal against the Judge’s decision by reason of paragraph (g) of the Fourth Schedule to the SCJA. The decision was non-appealable. In any event, even if Multistar had a right of appeal, the appeal would have had no chance of succeeding in light of O 20 r 5(2) read with r 5(5).
Observations on the legislative framework of O 20 r 5
- [61]
[61] The effect of the phrase “subject to … this Rule” is that the court no longer has the power and discretion to allow an amendment under O 20 r 5(1) if the proposed amendment engages O 20 r 5(2). O 20 r 5(2) is engaged if, in relation to the proposed amended claim, limitation at that point in time has set in.
- [62]
[62] The question of whether the court still has a residual discretion under O 20 r 5(1) to allow an amendment that does not fit within the four corners of O 20 r 5(2)–(5) was an issue which troubled the English courts. There was a time when the English courts thought that the enactment of the RSC gave courts a wide discretion to grant an amendment notwithstanding that the statutory period had run out. In Chatsworth Investments Ltd v Cussins (Contractors) Ltd [1969] 1 WLR 1 (“Chatsworth”), Lord Denning pronounced that the then newly-enacted RSC O 20 r 5(1) gave the court wide powers to permit an amendment which would otherwise have been barred under O 20 r 5(2). He said (at 5):
- [63]
[63] In Sterman v E.W. & W.J. Moore [1970] 1 QB 596, Lord Denning once again took the opportunity to affirm the earlier comments he made in Chatsworth. He disagreed with an English Court of Appeal decision of Braniff v Holland & Hannen and Cubitts (Southern) Ltd [1969] 1 WLR 1533, a decision delivered shortly after Chatsworth in which Widgery LJ doubted Lord Denning’s interpretation of O 20 r 5, and reiterated that O 20 r 5(2)–(5) should not cut down the court’s wide powers contained in O 20 r 5(1) at 604:
- [64]
[64] The debate continued in Brickfield Properties Ltd v Newton [1971] 1 WLR 862. Sachs LJ, who sat on the same coram as Lord Denning in Chatsworth, lent support to Lord Denning’s approach. He observed that the court, despite the expiry of the applicable limitation period, has jurisdiction under both O 20 r 5(1) and r 5(5) to allow the amendment (at 873). Between the approaches advocated in Barniff and Chatsworth, he preferred the latter (at 874). He said (at 875-6):
- [65]
[65] Sachs LJ’s views however did not find favour with the other members of the coram. Edmund Davies LJ said that, where the operation of a limitation statute is involved, the matter ends when the applicant cannot bring himself within the four corners of O 20 r 5(5). Sachs LJ’s construction would be tantamount to treating the opening words of O 20 r 5(1) (ie, “subject to the following provisions of this rule”) as not being there at all, and having been inserted by the legislature, they must have intended to fulfil some purpose (at 879). Cross LJ too held that Sachs LJ’s construction would put great strain on the language used in O 20 r 5(1).
- [66]
[66] In our judgment, we were in complete agreement with the observations made by Davies and Cross LJJ. O 20 r 5(1) does not give the court an unfettered discretion. It was plain to us that the term “subject to … this Rule” signalled the draftsman’s intent for O 20 r 5(2)–(5) to cut down the scope of the general discretion under O 20 r 5(1) in circumstances where limitation has set in. The approach advocated by Lord Denning and Sachs LJ is, in our view, wrong because it would render this phrase meaningless. There is no reason why effect should not be given to the ordinary meaning of this phrase, and certainly no reason for us to give it a completely different meaning as to suggest that O 20 r 5(2)–(5) were intended to operate without prejudice to the generality of O 20 r 5(1).
- [67]
[67] This interpretation also makes sense when understood in light of the history of the provision. Any other conclusion would render it meaningless for the draftsman to have added O 20 r 5(2)–(5) to O 20 r 5(1) which existed long before the 1965 legislative amendments, albeit in a slightly different form (see The Rules of the Supreme Court 1883 (UK), O 28 r 1). It would be incongruous for the draftsman to prescribe parameters under O 20 r 5(2)–(5), within which the court may allow an amendment notwithstanding the expiry of the limitation period, only to leave the court with a discretion-at-large to allow amendments under O 20 r 5(1) even if they fail to meet the requirements prescribed. In this regard, we found Staughton LJ’s analysis to be insightful (see The Casper Trader at 137):
- [68]
[68] Given the linguistic and historical difficulties in the approach suggested by Lord Denning and Sachs LJ, we respectfully declined to follow it. Indeed, slightly more than two decades ago, this court chose not to follow Chatsworth in Lim Yong Swan for similar reasons:
- [69]
[69] In sum, on the facts as the Judge had determined to be relevant, we found that he had erred in treating Geocon’s application in relation to the first set of amendments as a routine one to be dealt with under O 20 r 5(1). It should have been under O 20 r 5(5). However, in the light of what was found to be set out in the annexure to the Original SOC (see [56] above), we held that, and for that reason alone, the first set of amendments also did not introduce a new cause of action. The claim was there all along; just an instance of bad drafting. It was only on this basis that the first set of amendments should have been allowed under O 20 r 5(1).
Conclusion
Sundaresh Menon Chao Hick Tin Andrew Phang Boon LeongChief Justice Judge of Appeal Judge of Appeal