High Court · Decided 29 October 2004
Australian Timber Products Pte Ltd v Koh Brothers Building & Civil Engineering Contractor (Pte) Ltd
Feedback & support[2004] SGHC 243 · Case no. DC Suit 190/2004, RAS 23/2004 · 26 paragraphs
✱ What happened, in plain English
There is no plain-English summary of this judgment yet.
Ask about this judgment →Laws this judgment relies on
Grounds of decision
Official text from eLitigation
Belinda Ang Saw Ean J:
- [1]
[1] The facts of this appeal are simple. On 16 June 1997, the defendant, Koh Brothers Building & Civil Engineering Contractor (Pte) Ltd, as the main contractor for the “Villa Begonia” development at Saraca Road/Begonia Road (“the project”), appointed the plaintiff, Australian Timber Products Pte Ltd, as its nominated sub-contractor for the supply and installation of timber strip flooring for the project (“the works”). Following the purported completion of all of the works, a dispute arose between the plaintiff and the defendant as to the amount due to the plaintiff in respect of the works. That dispute was not resolved, and on 15 January 2004 the plaintiff commenced proceedings in the District Court against the defendant for the balance sum of $134,031.24.
- [2]
[2] The writ of summons was served on 20 January 2004. On the same day, an appearance to the action was entered on behalf of the defendant. An amended writ of summons was re-served on the defendant’s solicitor on 5 February 2004. The deadline for the defendant to serve its defence was 20 February 2004.
- [4]
[4] The defendant’s case is that the contract with the plaintiff contained in or evidenced by the defendant’s letter dated 16 June 1997 provided for disputes to be referred to arbitration. The contrary position, which was taken by the plaintiff, was that the matters forming the subject matter of the action were not covered by the alleged arbitration clause. There was no agreement to arbitration as the arbitration clause relied upon by the defendant was inapplicable as far as the relationship between the plaintiff and the defendant was concerned.
- [5]
[5] It is common ground that the 48-hour notice expired on 24 February 2004. Since no defence was served, the plaintiff on 25 February 2004 entered judgment in default of defence in the sum of $134,031.24. On 9 March 2004, the defendant applied to set aside the default judgment.
- [6]
[6] The defendant’s application to set aside the default judgment was refused by the Deputy Registrar, whose decision was reversed on appeal to the district judge in chambers on 5 May 2004. The plaintiff on 14 May 2004 appealed against the decision of the district judge in which he set aside the default judgment.
- [7]
[7] Mr Andrew Chan was engaged as counsel to argue the appeal before me on behalf of the plaintiff. He contends that the plaintiff was entitled to enter default judgment following the failure of the defendant to serve its defence. If anything, it was up to the defendant to apply for leave to extend time to serve the defence. The default judgment was a regular judgment and it should not be set aside, the contention being that the defendant had not shown that it had a real prospect of successfully defending the claim.
- [8]
[8] To the defendant, the notice to serve the defence was issued without basis as the plaintiff was already served with the stay application on 18 February 2004. The defendant relied on the decision in Samsung Corp v Chinese Chamber Realty Pte Ltd [2004] 1 SLR 382 (“Samsung”) for the proposition that once a stay application has been served, and until it has been finally disposed of, it is not proper for the plaintiff to insist on the defence being served and to enter judgment in default of defence. Mr Lai pinned his colours on the following passage by Chao Hick Tin JA in Samsung at [7]:
- [9]
[9] In resisting the appeal before me, the defendant adopted the reasoning of the learned district judge, who in his Notes of Arguments said that:
- [10]
[10] A further ground was added as a postscript to the Notes of Arguments. After setting out in full the text of O 1 r 2(3) of the Rules of Court (Cap 322, R 5 2004 Rev Ed), the district judge stated:
- [11]
[11] As stated above, the plaintiff does not accept that the claims advanced in the action are within the arbitration clause. Be that as it may, even on the defendant’s view, the starting point is that the existence of an agreement to arbitrate does not prevent either party from commencing the action herein. The common law rule is based on the principle that the parties may not agree to oust the jurisdiction of the court: see Arbitration Law by Robert Merkin (LLP, 1991) at para 6.1. Above all, the challenge is not as to the court’s jurisdiction as such. The defendant here is asking the court to exercise its discretion not to assume jurisdiction over the case, but to let the case be heard by the agreed forum of arbitration. The power to grant a stay under the Arbitration Act is discretionary: see s 6(2) Arbitration Act and Halsbury’s Laws of Singapore, vol 2 (LexisNexis, 2003 Reissue) at paras 20.032 and 20.037. The court has discretion to refuse a stay of the action if it is satisfied that there is “sufficient reason why the matter should not be referred in accordance with the arbitration agreement”. In contrast, the stay of proceedings involving a non-domestic arbitration under the International Arbitration Act (Cap 143A, 2002 Rev Ed) is mandatory.
- [12]
[12] I agree with the submissions of Mr Chan that Samsung is distinguishable on its facts and that the issues therein were different. In that case, the Court of Appeal had to consider whether it was proper for the court to either waive the requirement of O 14 r 1, or, in the alternative, compel a defendant to serve his defence so as to enable the plaintiff to apply for summary judgment. In so allowing, both the stay and O 14 applications could be heard at the same sitting, as was the practice prior to the amendments to O 14 r 1 that came into effect on 1 December 2002. Previously, a plaintiff could apply for summary judgment even though a stay application had been filed. The Court of Appeal held that the new O 14 r 1 changed the previous practice and that the court should not make a compromise order to compel the defendant to serve its defence. The compromise order would have allowed the defence to be served without treating that course as a step in the proceedings.
- [13]
[13] In Yeoh Poh San v Won Siok Wan [2002] 4 SLR 91, the defendant applied for a stay of a Singapore action on grounds of forum non conveniens. The assistant registrar dismissed the application and the defendant appealed. No defence was filed. Before the appeal was heard, the plaintiff applied for summary judgment in default of defence, presumably preferring to obtain a judgment on the merits. In turn, the defendant applied for an extension of time until after the hearing of the appeal to serve her defence. The Deputy Registrar who heard the application extended the time to serve the defence by 14 days together with a reservation that in so doing the defendant would not be treated as having taken a step in the proceedings in the pending appeal to the judge in chambers. The defendant appealed against the order of the Deputy Registrar and before Woo Bih Li JC (as he then was) she sought a longer extension of time until she had exhausted all avenues of appeal on the forum non conveniens point.
- [14]
[14] Woo JC first commented on the situation where parties in general voluntarily or tacitly agree to keep matters in abeyance pending an application to stay proceedings on grounds of forum non conveniens. He also went on to deal with the converse situation where a plaintiff, nonetheless, insists on a defence being served. In the event, the defendant should apply to extend time to serve the defence under O 3 r 4. The proper order that the court should make was to extend time to serve the defence until after the final resolution of the stay application.
- [15]
[15] In my judgment, the proper occasion to cite the observations made by Chao JA in Samsung and Woo JC in Yeoh Poh San v Won Siok Wan is at the time when the court hears an application to extend time. Woo JC observed at [19] that the court should generally allow an application to extend time on the ground that there was a pending stay application or an appeal to stay the proceedings, and the court should extend time to serve the defence until the final resolution of the stay question. The rationale, as explained by Woo JC and accepted by Chao JA in Samsung, is that the filing of the defence before the hearing of the original stay application would defeat the purpose of the stay application. This is equally applicable to an appeal. Woo JC said that the extension should generally be granted so as not to render the appeal nugatory. I agree that the court should be wary of a requirement to serve a pleading, which might be liable to be a temporary pleading, especially when the action might be stayed for another forum or arbitration. Woo JC reasoned that a defendant should not be required to meet the plaintiff’s claim on the merits and have its attention distracted by engaging in two contradictory courses of action at the same time. In the context of s 6(1) of the Arbitration Act, the wording of the subsection does not allow for such a dual approach. It is clear that the court has no jurisdiction (as opposed to discretion) under s 6(1) to stay the proceedings once a step in the proceedings has been taken: see Arbitration Law ([11] supra) at para 6.19. I would venture to state that the “compromise order” made by the judge in Samsung would undoubtedly blur, if not affect, the jurisdiction of the court to stay the proceedings. As alluded to by Chao JA at [24], such a compromise order would not be in line with the object and spirit of s 6(1).
- [16]
[16] In my judgment, a pending stay application in itself does not stop time running for the service of the defence. The Rules of Court have their own self-contained provisions relating to the service of defence, time extension and default judgment. Unless and until there is a stay order to halt proceedings, the plaintiff is entitled to give notice to the defendant to serve its defence. It is for a defendant, faced with a 48-hour notice to serve its defence, to respond appropriately. A proactive approach should be adopted. The defendant could have seen the duty registrar to bring forward the hearing date of the stay application for immediate hearing as a matter of urgency or apply for an extension of time to serve the defence under O 3 r 4 and at the same time seek an urgent hearing of the matter. In the present case, Samsung had not been interpreted correctly. Consequently, the defendant did not take any valid step before the time ran out under the plaintiff’s notice. Mr Lai tried to argue that the defendant had in its summons sought an extension of time to serve the defence. Mr Lai’s submission is misconceived. The alternative prayer in the defendant’s stay application is not a proper application to extend time but was taken out contingent upon its application for a stay being unsuccessful.
- [17]
[17] Mr Chan argues that the defendant would not have lost its right to stay the proceedings under s 6(1) of the Arbitration Act if it had made an application to extend time to serve the defence. He referred me to London Sack & Bag Co, Ltd v Dixon & Lugton, Ltd [1943] 2 All ER 763 in support of his contention that an application to extend time to serve the defence would not be viewed as a “step in the proceedings”. In that case, the defendant applied to stay the action for arbitration. The defendant also applied for and obtained an order to extend time to serve its defence until the hearing of the stay application. McKinnon LJ was of the view that in these circumstances, the defendant could not be said to have taken a “step in the proceedings”. Scott LJ said in obiter that on the facts of the case, he was doubtful whether a step had been taken that barred the right to a stay. The third member, Du Parcq LJ, expressed no opinion on the question whether the defendant could be said to “have taken a step in the proceedings”.
- [18]
[18] The question what amounts to a step in the proceedings has been considered a number of times by the English courts: see Pitchers, Ltd v Plaza (Queensbury), Ltd [1940] 1 All ER 151, Eagle Star Insurance Co Ltd v Yuval Insurance Co Ltd [1978] 1 Lloyd’s Rep 357 (“the Eagle Star case”), Kuwait Airways Corporation v Iraq Airways Co [1994] 1 Lloyd’s Rep 276 (“the Kuwait Airways case”) and Patel v Patel [2000] QB 551. In Patel v Patel, the English Court of Appeal held that the principle outlined in Pitchers, Ltd v Plaza (Queensbury), Ltd applied to the new law under the UK Arbitration Act 1996 as it did to the UK Arbitration Act 1950. Section 9(3) of the UK Arbitration Act 1996 is on similar terms to s 1(1) of the UK Arbitration Act 1975 and s 4 of the UK Arbitration Act 1950.
- [19]
[19] The underlying principle was set out in the Eagle Star case by Lord Denning MR at 361, in a passage that was subsequently followed in the Kuwait Airways case:
- [20]
[20] Lord Denning’s approach is echoed in Halsbury’s Laws of Singapore ([11] supra), at 20.035, which reads:
- [21]
[21] Mustill and Boyd in The Law and Practice of Commercial Arbitration (Butterworths, 2nd ed, 1989) at p 472 said:
- [22]
[22] In addition, an act, which would otherwise be regarded as a step in the proceedings, will not be treated as such if the applicant has specifically stated that he intends to seek a stay or expressly reserves his right to do so: see Chong Long Hak Kee Construction Trading Co v IEC Global Pte Ltd [2003] 4 SLR 499.
- [23]
[23] In my judgment, an application by the defendant to extend time to serve the defence will not constitute a step in the proceedings within the meaning of s 6(1) of the Arbitration Act on the basis of the principles set out above. In the present case, the defendant clearly intends to seek a stay. An application to extend time would be to safeguard the defendant’s position pending the determination of the stay application as opposed to an act that seeks to contest the proceedings on its merits.
- [24]
[24] For completeness, I make the following observation. After default judgment was entered, the defendant applied to court to set it aside. The fact that the defendant had applied to have the default judgment set aside was not a step in the proceedings. As the English Court of Appeal noted in Patel v Patel ([18] supra), unless there was an application to set aside the default judgment there would be nothing to stay.
- [24]
[24] I now turn to the issue whether or not the default judgment should be set aside. The default judgment here was a regular judgment. The defendant’s decision not to serve the defence stemmed from its incorrect interpretation of Samsung. In Singapore Civil Procedure 2003 (Sweet & Maxwell Asia, 2003) at para 13/8/2, it is stated:
- [25]
[25] To set aside a judgment regularly obtained, the burden is on the defendant to satisfy the court that it has a defence on the merits which has a real prospect of success and carries some degree of conviction, an approach set out in the decision of Alpine Bulk Transport Co Inc v Saudi Eagle Shipping Co Inc (The Saudi Eagle) [1986] 2 Lloyd’s Rep 221 and followed in Abdul Gaffer v Chua Kwang Yong [1995] 1 SLR 484 and subsequent decisions like Oversea-Chinese Banking Corp Ltd v Measurex Corp Bhd [2002] 4 SLR 578 at [17].
- [26]
[26] The defendant argues that the plaintiff’s works were incomplete and defective, which caused the defendant to incur extra expenses in the sum of $114,198. That seems to be a bare assertion in the face of countervailing evidence. Despite the plaintiff’s request, the defendant did not give details of the allegations and the documentation it referred to is outdated. It was first disclosed, according to the date on the fax transmission, in May 2000. According to the plaintiff, it is being re-circulated for use in these proceedings. Since the time the document was first disclosed, the defendant had on 20 December 2002 countersigned the plaintiff’s statement of final account for $134,031.02 whereby the defendant confirmed that it had no further claims on this sub-contract against the plaintiff. This admission was not denied by the defendant. Furthermore, on 13 October 2003, the project’s quantity surveyor had certified the plaintiff’s work in the sum of $134,031.24. The architect’s final certificate dated 29 October 2003 showed that the employer had paid the defendant for the plaintiff’s work in the sum of $134,031.24. In my judgment, there is no substance in the suggested defence and I conclude that the defendant has not discharged its burden so as to warrant a setting aside of the default judgment.