Grounds of decision

Official text from eLitigation

  1. Introduction

  2. [1] The present case concerned two separate actions: a claim against the Defendant based on invoices relating to a contract for the supply of labour and materials (“Invoices Claim”) under Suit No 169 of 2014 (“S 169/2014”), and a minority oppression claim against the Defendant and its shareholders (“Oppression Claim”) under Suit No 170 of 2014 (“S 170/2014”). Under the Invoices Claim, the key question related to the nature of the oral agreement between the parties concerning the mark-up to be charged on the labour and materials supplied, and whether the Plaintiff was entitled to the claim amount based on a contractual debt and as proven by its invoices provided to the court. By way of an oral judgment dated 3 December 2015, I dismissed the Invoices Claim and allowed the Oppression Claim. The Plaintiff in the Invoices Claim has since appealed against my decision, and I now set out the grounds for my decision.

  3. Parties to the dispute

  4. [3] The Plaintiff, Seaquest Enterprise Pte Ltd (“Seaquest”) was incorporated in 2003 and had been in the business of, inter alia, shipbuilding and ship repairing. Tan Meng Hin (“Clement Tan”) was a director and majority shareholder of Seaquest holding 51% of Seaquest’s shares. According to Seaquest, Clement Tan had been holding his shares in Seaquest on trust for himself and two of his close friends, Tan Cheng San (“Sunny Tan”) and Liew Ken Foon (“Ken Foon”) in equal proportions. Lui Kee (“Ricky”) held the remaining shares in Seaquest.

  5. [4] The Defendant, Agile Accomm Pte Ltd (“Agile”) was incorporated in 2009 to carry on the business of marine accommodation work for shipbuilding. Tan Beng Yong (“Bill Tan”) was a director and majority shareholder of Agile. His wife, Ho Shen Shen (“Lynn Ho”) was also a shareholder of Agile.

  6. [5] Lim Siew Fern (“Mdm Lim”) was the Plaintiff in S 170/2014 and the registered owner of 45,000 shares in Agile (“the Shares”). Mdm Lim is the wife of Sunny Tan.

  7. Factual background

  8. [8] According to Seaquest, sometime in October 2011, Clement Tan instructed Yeo Pick Har (“Iris Yeo”), the Accounts Manager in Seaquest, to conduct an internal review of Seaquest’s accounts to ascertain the profit margin in Seaquest and the proportion that Seaquest’s overheads were in relation to Seaquest’s revenue. It was through this internal review that Seaquest discovered that its overheads were at least 20% of its revenue. Clement Tan therefore instructed Iris Yeo to invoice Agile an administrative charge of 20% on all its invoices for labour and materials to reflect Seaquest’s overheads, and this was to take effect immediately.

  9. [9] Sometime in 2013, the relationship between the parties became strained. Clement Tan met up with the other partners in Seaquest - Ricky, Sunny Tan and Ken Foon, and made a decision to stop supplying labour and materials to Agile as they claimed that Agile’s directors were paying themselves excessively high remuneration. Pursuant to this discussion, Seaquest stopped supplying labour and materials to Agile on 22 February 2013 and pulled out of the Noble Jack 1104 Project (“NJ 1104”). It also demanded that Agile make payment for all the outstanding invoices relating to the supply of labour and materials. Pursuant to the above, Seaquest commenced proceedings against Agile in respect of the Invoices Claim and Mdm Lim commenced proceedings against Agile in respect of the Oppression Claim.

  10. The Oppression Claim

  11. [10] Even though the decision in relation to the Oppression Claim has not been appealed against, I find it useful to set out briefly the parties’ respective positions at trial relating to the Oppression Claim and the findings made therein. It was undisputed at trial that Mdm Lim was the registered owner of the Shares. What was disputed, however, was whether the share transfer was merely intended to be a temporary transfer, and whether she held the Shares as a nominee of Clement Tan in person or as a nominee of Seaquest. In relation to the former, Agile asserted that Clement Tan had himself stated during settlement negotiations that if the invoices were resolved, the 45,000 shares would be transferred back to Agile. This allegedly indicated a temporary transfer. But these statements were expressed in the context of settlement negotiations whereby both parties were seeking to resolve their disputes amicably. Consequently, they were not necessarily an indication of their intentions at the time the Agreement was formed. In fact, the manner in which Seaquest attempted to use the Shares as a bargaining tool to persuade Agile to pay off the invoices may actually go toward evidencing that the Shares were actually beneficially owned by Seaquest. If they were not beneficially owned by Seaquest, Seaquest would not have been able to leverage on the potential return of the Shares as a negotiation tactic. Most importantly, Bill Tan himself had stated in an email dated 23 November 2012 to Clement Tan that “[w]hether it is financing of the project or Agile company share given, you and me know it very well. From starting till date, I have never changed by mind on the support we agreed and even done my part for giving the share” [emphasis added]. The fact that Bill Tan expressed the Shares as having been given to Seaquest contradicts its contentions at trial that the share transfer was meant to be a temporary one.

  12. [11] Further, Agile contended that Mdm Lim held the Shares as a nominee of Clement Tan as he was the instructing individual in both the Invoices Claim and the Oppression Claim and had instructed Mdm Lim not to attend the meetings in Agile or sign off on Agile’s accounts. But the key question which was not asked was, in what capacity had Clement Tan been giving Mdm Lim such instructions – as the managing director of Seaquest, or on behalf of himself? The answer to that question was apparent in the context of the case. The Agreement entered into between Seaquest and Agile allowed Agile to be able to procure labour and materials at a rate that was lower than the market rate. Pursuant to the Agreement, Agile transferred 45% of its shares to Mdm Lim, the wife of one of Clement Tan’s partners in Seaquest (ie, Sunny Tan). In the context of the Agreement, I found that Mdm Lim held the Shares as a nominee for Seaquest because Seaquest’s shareholding in Agile was in effect quid pro quo for Seaquest’s supply of labour and materials at below-market prices, reflecting the reality that when businessmen come together, both would expect mutual benefits and be willing to make certain compromises. This arrangement would allow Seaquest to own the Shares and thus earn profits through dividends from other projects undertaken by Agile.

  13. Seaquest’s position on the Invoices Claim

  14. [13] Seaquest had pleaded that it was in a partnership with Agile not in the sense of a formal partnership structure, but in the sense that it was a business partnership; an informal joint venture (but admittedly without a written joint venture agreement). To support its claim, it raised a few examples as evidence of how the relationship between the parties was not merely that of a sub-contractor and main contractor but had instead resembled a partnership:

  15. (a) Clement Tan had acted as a mediator to a dispute between Exquisite and BIP;

  16. (b) Clement Tan procured the transfer of distributorship rights over Sung Mi products from Sung Mi (Asia) Pte Ltd (“Sung Mi Asia”), Seaquest’s wholly-owned subsidiary, to Exquisite in or around early 2009 free-of-charge;

  17. (c) Agile provided financial information to Seaquest for the proposed takeover of Seaquest by Kaefer, a German company;

  18. (d) Seaquest was able to instruct Agile to purchase hardware from Xing Wan Hardware Pte Ltd (“Xing Wan”); and

  19. (e) Seaquest would assist Agile in its tender submissions.

  20. Agile’s position on the Invoices Claim

  21. Issues

  22. [16] The following issues had to be determined in the present case:

  23. (a) whether the parties had agreed on a fixed mark-up, and if so, whether it was 5%, 7% or 20% of Seaquest’s costs (“Issue 1”);

  24. (b) whether Seaquest had satisfactorily proven its claim amount based on the invoices provided to Agile and the court (“Issue 2”); and

  25. (c) whether Agile was entitled to its counterclaim of laminates and additional labour cost incurred (“Issue 3”).

  26. Analysis of Issue 1

  27. Whether the parties had agreed on a fixed mark-up in the Agreement

  28. [17] In examining the terms of the Agreement, and in particular whether there was an agreed mark-up to cover Seaquest’s overheads as part of the Agreement, the events leading up to the Agreement and what they demonstrated about the relationship of the parties may be of some relevance. Seaquest had devoted a considerable amount of time at trial and in its closing submissions detailing the relationship between the parties, and asserted that the parties enjoyed a “special relationship” that was not akin to that of a sub-contractor and main contractor. But it was not entirely clear what Seaquest was seeking to prove through these various assertions about the relationship between the parties and how they had a bearing on the resolution of the case. In my judgment, even if I accepted Seaquest’s portrayal of the events (which I did not), these events were not very persuasive one way or another as they did not lead to the inevitable conclusion which Seaquest sought to establish – that because of the allegedly close relationship that Agile and Seaquest shared,akin to partners in a partnership rather than that of a sub-contractor and main contractor, Agile was in the likely position to have agreed to a variable mark-up as a term of the Agreement that was sufficient to cover Seaquest’s overheads, whatever they may currently be. For Seaquest to succeed in justifying its claim based on the invoices which had a 20% mark-up in them, the court would have to find on the facts of the case that the mark-up could be varied at any point in time according to the fluctuations in Seaquest’s overheads relative to its revenue. Thus, I was of the view that these events were ultimately only tangentially relevant to the case at hand. However, I will still address the submissions made in this regard first because Seaquest had devoted a considerable amount of the time to them, both at trial and in its closing submissions.

  29. Seaquest’s allegations relating to the relationship of the parties

  30. [18] First, Seaquest alleged that in 2009, it had assisted Agile in procuring the transfer of distributorship rights for Sung Mi products from Sung Mi Asia to Exquisite free-of-charge. To this end, Seaquest relied on an email from Clement Tan to Bill Tan dated 26 November 2012 in which Clement Tan stated “please don’t forget that agency of Sung Mi is allocated to you FOC as well … FYI, Seaquest paid $123,602.00 to KE wood for the agency. I can provide information to you if you want to take a look”. Seaquest further relied on the fact that Bill Tan did not reply to Clement Tan’s assertion regarding the Sung Mi distributorship being free-of-charge by way of email to buttress its assertion that it had procured the Sung Mi distributorship for Agile on account of their special relationship. Prior to the transfer of the distributorship rights, it was Sung Mi Asia which was the sole distributor of Sung Mi products in Singapore. On Seaquest’s own admission, Sung Mi Asia was not able to sell Sung Mi products successfully to Seaquest’s competitors because it was common knowledge that Sung Mi Asia was associated with Seaquest. Further, even after the distributorship rights had been transferred to Exquisite, Sung Mi Asia retained the right to obtain Sung Mi products directly from Sung Mi Co Ltd. In assessing Seaquest’s allegations relating to the Sung Mi distributorship, it may be noted that both parties did not produce further documentary evidence relating to the transfer of the Sung Mi distributorship, and in my view it was difficult for the court to come to a firm conclusion on the matter in the absence of such evidence. In any event, I observed that even after the transfer of the distributorship, Seaquest retained the benefit which was useful to itself – the ability to obtain Sung Mi products directly, and the rest of the agency (which Seaquest could not exploit even when it had the distributorship) was given away to Agile. This transfer of the distributorship agreement, even free-of charge, was not, to my mind, evidence of the special relationship which Seaquest sought to prove (and pursuant to which Seaquest had forsaken some benefit), for Seaquest had merely done what was reasonable and commercially sensible for businessmen to do, ie, to give away what it could not exploit.

  31. [19] Secondly, Seaquest asserted that Agile was merely a shell company between 2009 to 2010 with little or no business of its own. Seaquest argued that this was demonstrated by the fact that Agile’s register of sales for June 2009 to December 2010 only documented one customer, Exquisite, for the period between June and December 2009. However, I was of the view that this did not get Seaquest very far in its case. Both parties did not dispute that Agile was a small company and that the Saudi Aramco Project offered to Agile was its first major project. But companies cooperate for mutual benefit and in my view, each one needs the other in an agreement, whatever the relative strength and size of the parties may be. In fact, as Clement Tan had admitted, working together with Agile on the Saudi Aramco Project sounded like a good business opportunity for Seaquest as well, because the project was at a shipyard in which Seaquest had no foothold, ie, Jurong Shipyard. Merely because one contracting party was relatively small in comparison did not mean that it had no benefit to offer the other contracting party. Rather, this enables both parties, as reasonable businessmen, to contract for mutual interests.

  32. [20] Thirdly, Seaquest highlighted that Agile’s provision of “intimate” financial information to Seaquest when Kaefer was considering a potential takeover of Seaquest demonstrated that the relationship between Seaquest and Agile was not that of a mere sub-contractor and main contractor. But at this point in time, the transfer of the shareholding in Agile had taken place and Seaquest held a 45% shareholding in Agile through its nominee. Indeed the relationship between the parties was not merely that of sub-contractor and main contractor, as Seaquest did own 45% of Agile through its nominee. Given that the Shares formed part of Seaquest’s ownership of assets and that Seaquest had the potential to receive dividends as a result of such shareholding, it was only natural, and perhaps even somewhat of an expectation, for Agile to furnish Seaquest with such information in the context of a potential takeover. In my judgment, this had very little bearing on the nature and terms of the Agreement.

  33. [22] From the foregoing, it was clear that Seaquest’s submission on the alleged partnership and/or informal joint venture were not very persuasive. Even if a few examples were slightly more noteworthy, like the fact that Seaquest would assist Agile in its tender submissions from time to time, the incidents, in my view, merely pointed to the fact that Clement Tan and Bill Tan enjoyed a close working relationship and friendship. There may thus be certain matters on which Seaquest and Agile would provide assistance to each other that may not be common in the industry, but these could easily be explained as the help that they rendered to each other on account of their friendship, and not necessarily because they were in an partnership and/or informal joint venture. Even businessmen who are in a business relationship without an existing friendship may ask favours from the other party or make certain requests, and the other party may choose whether to accede to the favour or request. Ultimately, in my assessment of the facts and circumstances of the case, Seaquest and Agile retained their freedom to make choices in line with their individual business interests and remained separate companies, albeit separate companies with managing directors in a close working relationship.

  34. Whether the parties had agreed on a variable mark-up in the Agreement

  35. Analysis of Issue 2

  36. Whether Seaquest is entitled to its claim of $1,933,172.57 based on an allegedly unpaid contractual debt

  37. Seaquest was not entitled to charge a mark-up of more than 7%

  38. [24] Moving on to the invoices, given that I had found that Seaquest was only entitled to charge a mark-up of not more than 7%, the first objection that I had to Seaquest’s claim on the invoices was that the claim based on the invoices which were issued after the internal review had allegedly been conducted in October 2011 and which had a 20% mark-up on them should not be allowed.

  39. The invoices could not be relied on to justify payment

  40. (1) The invoices

  41. [26] Seaquest’s claim in S 169/2014 was for the sum of $1,933,172.57 pursuant to invoices and credit notes issued between June 2012 and April 2013. The invoices which form the basis of the claim were set out in the Annex of the Statement of Claim. The invoices are in respect of the PRM Offshore Heavy Industries Pte Ltd (“PRM”) shipyard projects, Jurong Shipyard Heavy Industries Pte Ltd (“JSY”) shipyard projects, and other claims including an office renovation claim. The invoices can largely be divided into two time periods – invoices issued before and after 10 April 2013.

  42. [27] For those issued prior to that date, Seaquest’s invoices did not clearly reflect a mark-up on the face of the invoices, except four invoices that reflected an additional 7% administration charge. The charges were set out in lump sum amounts under the categories of “labour” and “purchase” with little breakdown of manpower or items.

  43. [28] Between 10 April 2013 and 25 April 2013, Seaquest issued invoices which reflected a 20% additional charge which was described as an “administrative charge”. “Labour”, “Other Purchases” and “Local Purchases” were set out in lump sum amounts, though items under “Furniture Supply as per Delivery Orders” were set out with their quantity and unit prices.

  44. (2) Analysis

  45. [29] The parties had raised a preliminary issue relating to the burden of proof in respect of the invoices as Agile had submitted that Seaquest should be put to “strict proof” of its claim while Seaquest had submitted that the standard of proof in civil cases is on a balance of probabilities and “strict proof” does not, and cannot, elevate the burden of proof to one of beyond “reasonable doubt” or worse, beyond “all doubt”. A defendant putting the plaintiff to “strict proof” merely evinces an express non-admission of the material allegations made against the said defendant. In my view, it was clear that the standard of proof to be applied is that of a balance of probabilities. The proper way to analyse Seaquest’s claim on the invoices was to consider the supporting documents provided by Seaquest for its claim, then to consider the allegations raised by Agile in relation to those same supporting documents, and conclude as to whether Seaquest had discharged its burden of proof and satisfied the court of its claim based on an alleged contractual debt and as proven by the supporting documents tendered.

  46. [30] The charges on the invoices produced by Seaquest can broadly be divided into the following categories:

  47. (a) Labour: workers’ wages, dinner claims and dormitory and levy charges:

  48. (i) allegedly supported by Seaquest’s Summaries of Manpower, PRM’s Sub-Contractor Daily Manpower Records, JSY’s time-in and time-out entries, Work Record Cards, Dinner Claims and Salary Sheets.

  49. (b) Purchases, whether “Other Purchases” or “Local Purchases”, and furniture:

  50. (i) allegedly supported by Third Party Invoices, Seaquest Malaysia Sdn Bhd’s (“Seaquest Malaysia”) purchase orders, Seaquest invoices to Seaquest Malaysia and Seaquest Malaysia’s delivery orders.

  51. [31] In respect of Seaquest’s claim relating to the workers’ wages, which form the bulk of the labour charges in the invoices, I found that they had not been satisfactorily proven for the following reasons. First, although Seaquest’s witness, Iris Yeo, had testified that the Salary Sheets were the appropriate category of documents to rely on (to determine the labour charges) and that they were, in turn, based on the Work Record Cards, it had been uncovered at trial that there were numerous inconsistencies between the Salary Sheets and the Work Record Cards. When the Salary Sheets and Work Record Cards were compared to ascertain which project a particular worker had been working on on a particular date, it became evident that at times, the Salary Sheets recorded a worker as having worked on an Agile project on a particular date, but according to the Work Record Cards, on the very same date that worker had not actually worked on an Agile project, but on a non-Agile project. This had serious implications on the charges which Seaquest were using to charge Agile because it would mean that Seaquest had factored in the time which a worker spent working on a non-Agile project as an Agile project, and charged Agile for such number of hours as was required to perform the services in respect of another shipyard project. This was not the only type of discrepancy that had been identified by Agile at trial. At other times, the Work Record Card for a particular worker indicated a certain time period in which the worker had worked at the shipyard, but the Salary Sheets would show a different time period for the same day, the same worker, and presumably for the same project. Even though the Salary Sheets were held out by Seaquest as supporting documents which evinced the labour charges in the invoices, and which were allegedly used to pay the workers, these documents were fraught with errors and inconsistencies with the primary documents which they were allegedly based upon.

  52. [32] Secondly, there were no means of justifying the sums claimed based on the Work Record Cards. Seaquest’s invoices to Agile that have been tendered as proof of its current claim were classified on a project-by-project basis. But the Work Record Cards were classified on a worker-by-worker basis instead of being divided by projects. It was almost impossible for Agile, or anyone for that matter, to compare the Work Record Cards with the amount of labour charged in the invoices given to Agile, and determine whether the charges were accurate. Indeed, in my view, it was not the court’s role to do so in an adversarial system where the burden of proof lies on the plaintiff to prove its case on a balance of probabilities. It was not satisfactory for a plaintiff to merely provide documents in bulk and assert that these documents, taken together, justified a particular amount claimed in the invoice where there was no coherent basis on which to analyse the quantum claimed and verify the accuracy of the sums.

  53. [33] Thirdly, in any event, even if we look beyond the Salary Sheets and the Work Record Cards, the other documentary evidence we have to prove the labour charges such as the PRM and JSY records are ultimately of limited utility in supporting Seaquest’s claim as to the labour charges. PRM’s Sub-contractor Daily Manpower Records were limited to the period between 1 October 2012 to 31 January 2013, and could not be used to verify the projects which fell outside of this time period. For the JSY Records, JSY’s representative Mr Kenneth Wong Keh Woei, had also clarified that certain records were incomplete because there were times at which the Records would display a time-in entry but no time-out entry or vice versa due to either the clock readers at JSY’s guardhouse failing or a worker failing to punch in or out. The JSY Records also did not track the type of project or vessel for which the workers whom had clocked in were working on, and for whom they were working for on a particular day. These records from the shipyards were thus of limited utility in justifying Seaquest’s claim. Further, given that Seaquest had clarified that it was not relying on Seaquest’s Summaries of Manpower reports to prove its claim I decided it was neither appropriate nor necessary to analyse Seaquest’s claim with reference to Seaquest’s Summaries of Manpower reports.

  54. [35] I thus found that Agile’s objections to the invoices were valid because they demonstrated that the claim amounts which Seaquest sought to charge Agile for were not corroborated by supporting documents and could, in fact, be contradicted by various documents of a similar nature.

  55. The invoices were not transparent

  56. Analysis of Issue 3

  57. Whether Agile is entitled to its counterclaim for laminates and additional cost of labour incurred

  58. Conclusion