  1. Introduction

  2. [1] The issue before me is simple – does the written agreement between the parties allow the defendant to unilaterally amend the scope of the services the plaintiff had agreed to provide?

  3. Facts

  4. [2] The plaintiff (“Keppel”) operates a six-storey data centre facility (the “Facility”) in Serangoon North Industrial Estate. On 30 November 2010, Keppel entered into a Standard Services Agreement (the “SSA”) with the defendant (“DXC”), which contained the terms and conditions under which Keppel was to provide data centre space (the “Data Centre”) in the Facility (and associated services) to DXC for a period of five years with an option for renewal. The Statement of Work (“SOW”) at Exhibit A of the SSA stated that the total space to be provided to DXC was 20,300 sq ft, comprising four modules (the “Modules”) – Modules A to D – with each occupying approximately 5,000 sq ft of space. DXC was to pay Keppel a Monthly Recurring Charge (the “MRC”) and electricity charges. These charges were set out in the “Contract Pricing” document (the “Contract Pricing”) at Exhibit B of the SSA.

  5. [4] In 2020 and 2021, DXC carried out a review of its requirements pertaining to the Data Centre. It concluded that the Data Centre had significant space capacity and it was unlikely that DXC would secure new customers to take up this spare capacity. DXC therefore made the decision to give up the use of Modules C and D.

  6. [6] DXC issued similar POs on 8 March 2022 and 7 April 2023 for the use of only Modules A and B for the respective annual periods. To date, DXC has only paid the invoiced amounts relating to Modules A and B from 1 April 2021, and has not paid any amounts relating to Modules C and D.

  7. [7] Keppel claims the sum of $3,021,316.20 as the sum outstanding from April 2021 to December 2021. Further and/or in the alternative, Keppel claims damages to be assessed for all losses it suffered from 1 April 2021 to 31 March 2025 as a result of DXC’s breach, subject to the issue of mitigation.

  8. Summary determination

  9. [8] Much of the dispute centred on the interpretation of the SSA – primarily, whether DXC was permitted under the SSA to unilaterally revise the services provided by Keppel, such that DXC could “return” Modules C and D to Keppel and only use and make payment for the use of Modules A and B for its Data Centre.

  10. [9] The action is currently set down for trial for 12 days in February 2024. At a case conference before me on 6 November 2023, I directed parties to state whether I needed to hear any evidence for the purpose of interpreting the SSA, and whether that issue could be decided summarily pursuant to O 14 r 12(1) of the Rules of Court (Cap 322, 2014 Rev Ed) (“ROC 2014”). Keppel agreed to the summary disposal, but DXC did not.

  11. Applicable law

  12. [13] The relevant principles of contractual interpretation are set out in Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte Ltd [2008] 3 SLR(R) 1029 (“Zurich Insurance”) at [131]:

  13. Nature of the SSA

  14. [14] It is undisputed that the SSA was a standard form agreement that DXC used in its dealings with various counterparties when seeking the provision of services. Thus, it appears that while the SOW and the Contract Pricing were specifically negotiated by parties, the body of the SSA was not.

  15. [15] Although the SSA is framed as a contract for services, it is in substance a fixed‑term contract for a custom-fitted space with services and utilities. This is evidenced by several clauses of the SSA and its exhibits.

  16. [16] First, cl 1.3 of the SSA provides that the SSA “will have a term of five (5) years”, and “parties may agree in writing to renew [the SSA] for successive five (5) year terms”. Similarly, the “Work Summary” at cl 1.2 of the SOW states that Keppel will provide the Data Centre space “according to the agreed specifications for a fixed price … for a period of 5 years (Initial Term) with an option to extend for a further 5 years”. Clause 3.1 of the SOW (titled “Supplier Provided Services”) specifies the total area of the Data Centre (20,300 sq ft initially, later enlarged by consent to 20,500 sq ft) and the technical specifications which Keppel was to design the Data Centre in accordance with (including circuitry, cooling and lighting requirements).

  17. [19] Third, cl 14 of the Contract Pricing provides, similar to cl 5.6 of the SSA, that in the event of suspension or termination of the SSA prior to the end of the term (other than for a material breach by Keppel), DXC must pay Keppel a sum – called a “Minimum Charge” – equivalent to 100% of the total charges which would have been payable to Keppel for the remainder of the initial five‑year term, and, if the SSA was renewed, 50% of the total charges which would have been payable for the remainder of the renewed term.

  18. [20] Thus, the clear implication from these provisions is that the SSA was meant to be a renewable fixed‑term contract for a period of five years, under which Keppel was obligated to provide a fixed amount of space and specified services. In exchange, Keppel was to be paid the MRC and accompanying charges for the entire fixed space for the initial five-year term and second five‑year term (if renewed), and in the event of premature termination, was guaranteed payment of the Minimum Charge, which was based on the MRC and accompanying charges for the entire fixed space.

  19. [21] The provisions make it clear that DXC was contracting for use of the entire space in the Data Centre as a whole, and did not contemplate that DXC had the option of only using, and paying for, some and not all of the Modules during the initial or renewed terms of the SSA.

  20. [22] This analysis is not affected by the subsequent amendments to the SSA in the Amendment Agreement dated 28 February 2017 (the “1st AA”) and the Amendment Agreement dated 27 March 2020 (the “2nd AA”) (collectively, the “AAs”). The AAs renewed or extended the SSA – first for five years commencing 1 March 2017, and then for five years up to 31 March 2025 – and introduced amendments mainly to vary the Contract Pricing and increase the Minimum Charge payable by DXC (under cl 5.6 of the SSA) in respect of the renewed terms.

  21. [23] I note that cl 18.1 of the SSA (as it originally appears) states that “[DXC] reserves the right to terminate [the SSA] or any Statement of Work hereunder without liability at any time, with or without cause, upon thirty (90) [sic] days prior written notice to [Keppel]”. This appears to contradict the requirement under cl 14 of the Contract Pricing and cl 5.6 of the SSA that DXC pay Keppel the Minimum Charge in the event of termination or suspension of services (save for material breach by Keppel). However, the standard terms in the body of the SSA must be read in light of the specifically negotiated terms. A more specific or detailed contractual provision should override an inconsistent general provision: Zurich Insurance at [131]. Thus, the termination provision in cl 18.1 must be read subject to DXC’s obligation to pay the Minimum Charge as stipulated under cl 14 of the Contract Pricing and cl 5.6 of the SSA.

  22. [24] In any event, this apparent inconsistency (as well as the typographical error in cl 18.1) was subsequently addressed. Clause 18.1 of the SSA was amended by the 2nd AA on 27 March 2020 to read “[s]ubject to Section 5.6 (Minimum Charges), DXC reserves the right to terminate [the SSA] or any Statement of Work hereunder without liability at any time … by way of issuing to [Keppel] ninety (90) days’ prior written notice”. Since the dispute began with the issuance of the 2021 PO and the 2021 CO on 13 and 17 May 2021 respectively, the applicable version of the SSA includes the amended cl 18.1 which recognises DXC’s obligation to pay the Minimum Charge in the event it terminates or suspends the SSA.

  23. [25] I highlight that DXC’s case is that the terms of the SSA have been varied, not that the SSA has been suspended or terminated. No Notice of Termination has been issued, and DXC is still making use of Modules A and B.

  24. [26] In the circumstances, the real issue is whether DXC is entitled under the SSA (as amended by the AA) to unilaterally reduce the Data Centre to just Modules A and B, and to pay a reduced charge for the same.

  25. Main issues

  26. Change Order

  27. [27] DXC argues that it is entitled, via a CO under the SSA, to unilaterally amend the SSA to reduce the size of the Data Centre or change the services Keppel is obliged to provide.

  28. [28] This issue turns on the interpretation of the provisions in the SSA relating to COs, set out below:

  29. [29] DXC argues that the issuance of a CO under cl 7.1 of the SSA permits it to make changes in the services provided by Keppel at any time prior to completion. DXC points out that cl 2.3 of the SSA expressly defines a CO as a document in the format set out in Exhibit E of the SSA and “signed by an authorised representative of [DXC]”. DXC submits that there is no requirement for a CO to be signed or otherwise acknowledged by Keppel – this was a deliberate decision made by parties, as evidenced by the fact that other clauses in the SSA (eg, cl 2.11) expressly required that other documents be signed by authorised representatives of both parties.

  30. [30] DXC accepts that its reading of the SSA would result in it being able to freely vary the space provided by Keppel – eg, by requiring 20,500 sq ft of space one year, then 10,000 sq ft the following year, and back to 20,500 sq ft in the third year. However, DXC argues that this scenario is not commercially absurd since Keppel would be able to seek recourse by submitting a written request for additional compensation pursuant to cl 7.1 of the SSA.

  31. [31] DXC’s arguments fail for several reasons.

  32. [32] First, any power given to one party to unilaterally re-write the terms of a contract is an extraordinary one and must be expressed in the clearest of terms. The terms of the SSA do not expressly allow DXC to unilaterally change the services it had contracted for, and indeed, suggest the opposite.

  33. [34] DXC argues that in the event of conflict between Exhibit E and the provisions of the SSA, cl 22 of the SSA provides that the latter would prevail. However, cl 22 only applies where there is a clear contradiction between the exhibits of the SSA and its provisions. That was not the case here since the two could be read harmoniously.

  34. [35] DXC refers to other clauses in the SSA – cll 2.11 and 3.3 – where a party’s acceptance is specifically provided for, and contrasts these with cl 7.1 which does not expressly refer to Keppel’s acceptance of a CO. This does not advance DXC’s case. Those provisions deal with entirely different matters. Further, as explained above, the language of the provisions dealing with COs refers to Keppel’s acceptance of DXC’s request.

  35. [37] Nevertheless, I would not go so far as to say that Keppel has the right to reject any changes requested by DXC. A parallel may be drawn here to building and construction contracts, in which a contractor is generally obliged to carry out variations requested by the employer (subject to appropriate adjustments in compensation), unless the effect of the requested variation would be to change the scope of the contract such that the works as varied become fundamentally different from that contemplated by the parties at the time of contracting: see Chow Kok Fong, Law and Practice of Construction Contracts (Sweet & Maxwell, 5th Ed, 2018) at paras 5.145–5.146, citing Thorn v London Corp (1876) 1 App Cas 120. Similarly, it is arguable that there is an implied term in the SSA that Keppel may not unreasonably reject DXC’s requested changes in so far as they are within the context of the scope of the agreed services. However, DXC is not asserting any such implied term. In any event, it would not be unreasonable for Keppel to reject the request under the 2021 CO to discontinue the use of Modules C and D. In the context of a fixed‑term contract for custom-fitted space and services for a fixed price, that would amount to a change in the scope of the SSA that would make the services provided fundamentally or materially different from that contemplated by the parties at the time of contracting.

  36. [39] Third, DXC’s ability to unilaterally vary the area of the Data Centre in the manner it purported to do would be inconsistent with cl 14 of the Contract Pricing and cl 5.6 of the SSA, which guarantees Keppel the Minimum Charge. As stated above at [20], Keppel is guaranteed the Minimum Charge if DXC suspends or terminates the SSA. If DXC’s interpretation is correct, it can simply avoid paying the Minimum Charge by reducing the Data Centre to only 1 sq ft of space instead of suspending or terminating the SSA. The parties clearly could not have intended such an outcome.

  37. [40] Fourth, I agree with Keppel’s argument that DXC’s reading of the CO mechanism under the SSA would result in commercial absurdity. If DXC is correct, Keppel would be obliged to make the full space – ie, Modules A–D – available for the entire contractual period, even though DXC could potentially request to use only 1 sq ft of space at any point.

  38. [41] Further, as stated above at [30], DXC accepts that its reading of the SSA would result in it being able to freely vary the space provided by Keppel – eg, by requiring 20,500 sq ft of space one year, 10,000 sq ft the following year, and back to 20,500 sq ft in the third year. DXC’s response is that this argument “ignores the nature of the industry in which the parties operate. The very nature of a data centre makes it extremely unlikely for there to be such to-ing and fro‑ing in terms of the space needed”. This argument must fail. Not only is there no evidential basis for this submission, DXC’s argument in fact supports and explains why the parties would agree upfront to a fixed‑term contract for a fixed space – DXC’s requirements were, on its own case, unlikely to change.

  39. [42] DXC’s interpretation would also allow it to “game” the deal it struck with Keppel: should market rates for data centre services fall substantially, DXC would be able to avoid paying Keppel the fixed rates it had agreed by substantially reducing the space under the SSA and taking up space at lower rates with Keppel’s competitors; should the market rates rise, DXC would simply hold Keppel to the agreed bargain under the SSA.

  40. [43] In addition, regardless of DXC’s unilateral reductions of the space used, Keppel would still be obligated under the SSA to continue providing DXC the Media Space free-of-charge.

  41. [44] All these consequences of DXC’s interpretation make no commercial sense and a contractual interpretation resulting in them must be avoided: Zurich Insurance at [131]. The parties, which are both large commercial entities, were highly unlikely to have reached such a lop-sided deal.

  42. [45] Therefore, the 2021 CO was not valid, had no effect, and did not result in any change to the SSA or the services provided under it. Consequently, the POs issued pursuant to the 2021 CO were invalid as well, since the attempted revision of the services provided was ineffective.

  43. Purchase Order

  44. [46] In its submissions, DXC seems to acknowledge that the validity of the POs issued pursuant to the 2021 CO depends on the validity of the 2021 CO itself – DXC notes that “[t]he 2021 CO and the May 2021 PO must be read together”, such that the 2021 CO would contain the “deletion or revision of the Services”, which would be reflected in subsequent POs. However, DXC also appears to argue that the PO mechanism was an alternative way, in addition to the CO mechanism, through which the SSA and the services provided may be varied. For the reasons below, I disagree with this argument.

  45. [48] However, the provisions which DXC relies on must be read and understood subject to what the parties specifically agreed to in the SOW, as well as the purpose of a PO under the SSA. DXC’s position that the POs allow it to freely vary the services to be provided to Keppel does not cohere with the structure of the SSA as a fixed‑term contract with services and fees that were agreed upfront.

  46. [49] Pertinently, it was not the function of the PO under the SSA to set out or vary the services to be provided by Keppel. The SOW is the only document mentioned which is to set out the services to be provided by Keppel – cl 1.1 states that the services shall be described in the SOW; cl 3.1 states that Keppel will provide services described in the SOW; and cl 3.2 states that Keppel shall undertake to perform the services set out in a SOW upon the SOW’s execution with an accompanying PO. Further, the SSA specifically provided (at cl 7.1) that any amendments to the services were to be requested via a CO. The POs were not contemplated as an alternative mechanism through which the SSA could be varied.

  47. [51] I add that there is nothing objectionable with DXC issuing POs on a yearly basis, so long as their terms are consistent with, and reflect, the parties’ agreement under the SSA. DXC is not permitted to issue POs inconsistent with the terms of the SOW and Contract Pricing, and then rely on its own wrong by claiming that it is only bound by the terms of the PO.

  48. [52] As an aside, I highlight that the parties’ conduct also indicated that they understood the POs to be a payment mechanism which had no impact on the provision of services by Keppel (save for the first PO on 8 March 2011 which initiated the provision of services). DXC was late to issue the POs on multiple occasions; yet Keppel did not cease to provide utilities and services to DXC in the periods between the expiry of a previous PO and the issuance of a subsequent PO, and DXC did not object to the provision of such services or claim that they were unauthorised.

  49. [54] I note DXC’s reliance on cl 2.9 of the SSA, which defines a PO as a written authorisation signed by an authorised representative of DXC and which is issued by DXC to authorise Keppel “to perform all or a portion of the Services”. This clause does not assist DXC. It must be read in light of the fact that the SSA contained standard terms which DXC used in securing the provision of services by its various business partners. That may well include contexts where POs for the performance of only a portion of the agreed services are acceptable. Here, as explained above at [50], in the context of the SSA, DXC had already authorised Keppel to provide the services in the SOW. Further, POs for part of the services are acceptable in the present case as well – DXC can issue different partial POs, as long as the entirety of them covers all the services set out in the SOW. It bears reiterating (as noted at [49] above) that the PO did not play a role in defining or amending the services to be provided; that was the function of the SOW and the CO mechanism respectively. Clause 2.9 is therefore not inconsistent with the fact that the POs issued by DXC must be consistent with its obligations under the SSA and SOW.

  50. Conclusion

  51. [55] I therefore accept the interpretation of the SSA as advanced by Keppel. DXC was not permitted under the SSA to unilaterally revise the services to be provided by Keppel to exclude the use of Modules C and D. The 2021 CO was therefore invalid and DXC’s subsequent refusal to pay for Modules C and D amounted to a breach of the SSA.

  52. [56] I will hear the parties separately on the appropriate relief. For the avoidance of doubt, the time to appeal this decision does not run until I have dealt with the entirety of Keppel’s claim.