Singapore International Commercial Court · Decided 12 May 2016
BCBC Singapore Pte Ltd and another v PT Bayan Resources TBK and another
Feedback & support[2016] SGHC(I) 01 · Case no. Suit No 1 of 2015
✱ What happened, in plain English
There is no plain-English summary of this judgment yet.
Ask about this judgment →Grounds of decision
Official text from eLitigation
Introduction and the parties
- [1]
[1] These proceedings in the first case before the Singapore International Commercial Court (“SICC”) concern a joint venture between parties in Australia and Indonesia, with associated companies in Singapore.
- [2]
[2] The joint venture sought to exploit a technology developed in Australia for the upgrading of coal known as the Binderless Coal Briquetting Process (“BCB Process”) in conjunction with a supply of sub-bituminous coal from mines in Tabang, East Kalimantan (“the Project”).
- [3]
[3] The second plaintiff, Binderless Coal Briquetting Company Pty Ltd (“BCBC”), a company incorporated in Australia, holds the exclusive worldwide licence of the BCB Process from a consortium led by the Commonwealth Scientific and Industrial Research Organisation (“CSIRO”). The first plaintiff, BCBC Singapore Pte Ltd (“BCBCS”), is a company incorporated in Singapore. BCBC and BCBCS are indirect wholly-owned subsidiaries of the second defendant by Counterclaim, White Energy Company Ltd (“WEC”), a public-listed company incorporated in Australia. These companies are collectively referred to as “the Plaintiffs” or “the WEC parties”.
- [4]
[4] The first defendant, PT Bayan Resources TBK (“BR”), is a public-listed company incorporated in Indonesia that owns subsidiaries which operate sub-bituminous coal mines in Tabang, Indonesia, including PT Bara Tabang (“Bara”) and PT Fajar Sakti Prima (“FSP”). The second defendant, Bayan International Pte Ltd (“BI”), is a company incorporated in Singapore and is an associated company of BR. These companies are collectively referred to as “the Defendants” or “the Bayan parties”.
- [5]
[5] BCBC and BI were the original parties to the joint venture but BCBCS and BR were subsequently substituted as the joint venture parties. WEC undertook certain guarantee obligations in relation to BCBC and BCBCS.
- [6]
[6] These proceedings were transferred to the SICC on 4 March 2015. At subsequent Case Management Conferences, pursuant to discussions with counsel, directions were given for the trial of certain issues as to the true meaning of a number of provisions in various agreements. The parties were able to agree on the formulation of those issues which related to funding obligations, coal supply obligations and certain implied terms (see [88] below).
Background
- [7]
[7] At a conference in Lexington, Kentucky, in early May 2005, Mr Keith Clark (“Mr Clark”), the then general manager of BCBC, presented a paper entitled “Thermal Drying and Binderless Briquetting of Sub-bituminous Coals”. He described the development and basic concept of the BCB Process – processing raw coal into briquettes with higher calorific value and lower moisture content – as well as some general economics and product properties. In his paper, referring to the development of the BCB process, he said:
- [8]
[8] After he had presented his paper, Mr Clark was approached by Mr Darcy Wentworth (“Mr Wentworth”), a mining engineer of the Bayan parties, Mr Lim Chai Hock (“Mr Lim”) and Mr David Low (“Mr Low”), directors of BR, who introduced themselves as representatives of PT Gunungbayan Pratamacoal and part of the group of Indonesian companies known as the Bayan Resources Group. There followed a discussion about the possibility of using the BCB Process to upgrade coal for the Bayan parties.
- [9]
[9] Following exchanges of emails and a meeting in late May 2005, Mr Clark proposed that testing of coal from the Bayan parties be carried out first at the CSIRO pilot plant and then, if the first coal testing proved to be satisfactory, a larger sample could be processed at the Collie plant to verify the suitability of the coal for the BCB Process.
- [10]
[10] The first sample of coal was received in early June 2005 and tested at the CSIRO pilot plant. This led to Mr Clark preparing a report dated 19 July 2005 entitled “Evaluation of Coal from PT Gunungbayan Pratamacoal’s Tabang Mine for Binderless Coal Briquetting”. After receiving a copy of that report, Mr Wentworth contacted Mr Clark to discuss the next stage of testing. A meeting then took place between Mr Travers Duncan (“Mr Duncan”), the current Chairman of WEC and a director of both BCBC and BCBCS, Mr John Langley (“Mr Langley”), BCBC’s Business Development Director and Mr Clark, representing the WEC parties on the one hand, and Mr Lim, Mr Low and Mr Wentworth representing the Bayan parties on the other, to discuss the further testing and the negotiation of a commercial agreement.
- [11]
[11] On 11 October 2005, Mr Clark sent the Bayan parties a draft proposal and this led to further exchanges and telephone calls. In January 2006, BCBC provided the Bayan parties with a report entitled “Engineering Assessment of the Binderless Coal Briquetting Process” produced by Sinclair Knight Merz (“SKM”) dated 4 November 2005. That report had been produced for WEC, which was at that time known as Amerod Resources Ltd, as part of its due diligence exercise before it made the decision to acquire all the issued capital of BCBC.
- [12]
[12] Following exchanges of drafts, BCBC and BR signed the Heads of Agreement and a Confidentiality Agreement on 16 February 2006. Under the Heads of Agreement, the parties proposed to set up various joint ventures.
- [13]
[13] In the meantime, a further sample of coal had arrived in Australia at the end of October 2005 and was processed at the Collie plant on or about 16 December 2005. That test had to be discontinued prior to processing the entire coal sample because of issues with the dust control and release system. There are issues between the parties as to the cause and significance of the dusty nature of the sample. In an email of 19 December 2005, Mr Clark noted:
- [14]
[14] Ultimately, the second test was considered to have provided satisfactory briquettes. A report dated 28 December 2005 was prepared on behalf of BCBC with the title “Assessment of PT Gunungbayan Pratamacoal’s Tabang Coal in the Collie BCB Demonstration Plant”.
- [15]
[15] Following the signing of the Heads of Agreement, meetings took place in Jakarta between 21 and 23 February 2006 involving the parties, lawyers and other advisers.
- [16]
[16] Drafts of various agreements were then exchanged between the parties leading to the execution of a Coal Briquette Joint Venture Deed (“the JV Deed”) between BCBC and BI on 7 June 2006. The obligations under the JV Deed, together with various subsequent agreements form the subject matter of the issues in this Judgment.
- [17]
[17] Under cl 2 of the JV Deed, there were conditions precedent to completion and there was a Completion Date defined as “the date that the parties decide to proceed with the Project…”. Pursuant to cl 3.1, “the Project” was defined as including, inter alia, the construction and commissioning of a coal briquette processing plant which employed the BCB Process. This plant was to be located in Tabang, Indonesia, and will be referred to as “the Tabang Plant” in this Judgment. The conditions precedent of completion were set out in cl 2 of the JV Deed and cl 2.1 provided that:
The Feasibility Study was defined as “a technical and economic study to assess the viability of the Project”.
- [18]
[18] Two documents forming the Feasibility Study were produced initially as drafts and then in final form. First, SKM produced a report entitled “Technical Feasibility Study on the Tabang Mine Coal Upgrade Project” (“the SKM Technical Feasibility Study”) on 25 August 2006. Secondly, Hyde Park Consultants produced a report entitled “Report on the Financial Viability of the Tabang Binderless Coal Briquette Project” (“the HPC Economic Feasibility Report”) on 6 September 2006.
- [20]
[20] The HPC Economic Feasibility Report contained a preliminary risk assessment of the Project which included technology risk because the “binderless coal briquetting technology [had] not yet been demonstrated in a commercially sized plant”.
- [21]
[21] On 24 August 2006, BI wrote to BCBC under cl 2.1 of the JV Deed saying “we have reviewed the results of the Draft Feasibility Studies provided to us and believe that on the merits of such we are keen to proceed with the development of this project”. On 4 September 2006, BCBC wrote to BI, referring to BI’s letter of 24 August 2006 and to cl 2.1 of the JV Deed and stating “…likewise we are ready to proceed to the next phases of the project…”.
- [22]
[22] On 14 September 2006, cl 3.2 of the JV Deed was amended through another deed to state that it was the intention of the parties to increase the capacity of the Tabang Plant from 1 million metric tonnes per annum (“MTPA”) to 5 MTPA (an increase from the original 3 MTPA) if the Project was successful. The parties also amended cl 3.8(b)(ii) of the JV Deed, which related to the delivery of the coal briquettes.
- [23]
[23] The parties continued to discuss and prepare drafts of the various documents required as part of the joint venture. On 11 January 2007, the parties established the joint venture company, PT Kaltim Supacoal (“KSC”) in Indonesia with BCBCS holding 51% and BI holding 49% respectively of the issued shares.
- [24]
[24] On 16 April 2007, BCBCS and BI entered into separate shareholders’ loan agreements with KSC, each granting a loan of US$25m to KSC to finance its capital expenditure and working capital requirements.
- [25]
[25] In March 2007, a draft business plan for the Project was prepared. At KSC’s board meeting on 9 May 2007, that plan was accepted with minor changes. The plan was subsequently issued in its approved form on 1 June 2007 (“the Business Plan”).
- [27]
[27] In response to that email, Mr Chin wrote on 28 November 2007 and said:
- [29]
[29] Following that meeting, Mr Hitchings sent Mr Chin a draft memorandum of understanding (“the draft MOU”) reflecting the agreement reached at the meeting on 12 December 2007. Mr Chin provided his comments on the draft MOU on 18 December 2007. On 8 January 2008, Dato Low Tuck Kwong, the Chairman of BI, wrote to Mr Duncan in relation to the terms of the draft MOU and said:
- [31]
[31] On 7 February 2008, KSC entered into the D&C Alliance Contract with Thiess with a target completion date of 1 March 2009.
- [32]
[32] On 3 April 2008, the parties entered into a number of agreements:
(a) First, KSC entered into a coal supply agreement with Bara (“the 2008 CSA”). Under cl 8.2 of that agreement, Bara agreed to supply coal to KSC at a base price of US$8.60 per tonne for the first four years.
(b) Secondly, KSC and BR entered into an Upgraded Coal Briquette Sale Agreement (“the Briquette Sale Agreement”) pursuant to which KSC agreed to sell 500,000 tonnes of upgraded coal briquettes each year to BR for each 1m tonnes of installed capacity up to a maximum of 1.5m tonnes at US$46.25 per tonne (see cll 3.1 and 7.2).
(c) Thirdly, a further amendment was made to the JV Deed.
(d) Fourthly, BCBC and KSC entered into a Technology Services Agreement.
- [33]
[33] On 19 May 2008, MS Taxes, a tax consultancy firm engaged to provide tax advice to KSC, pointed out that the Indonesian Tax Office might assess value added tax (“VAT”) and corporate income tax on the sale of the sub-bituminous coal and the upgraded coal briquettes at the market prices instead of the agreed prices of US$8.60 per tonne and US$46.25 per tonne in the 2008 CSA and the Briquette Sale Agreement because these agreed prices could be seen as transfer pricing and as transactions which were not performed at arm’s length.
- [36]
[36] This led to discussions in Jakarta on 16 and 17 September 2008, which culminated in an agreement signed by the parties on 17 September 2008 (“the September 2008 Agreement”) which provided at cll 2 to 6, as follows:
It will be seen that the forecasted cash expenditure to be borne by BCBC and BI in their 51% to 49% proportions had increased by US$10.6m from US$50m to US$60.6m.
- [37]
[37] On 18 September 2008, Mr Maras sent an internal email reporting on the result of the discussions in Jakarta on 16 and 17 September 2008. In addition to relating matters contained in the September 2008 Agreement, he added this:
- [39]
[39] In addition, Mr Maras said this:
- [40]
[40] A KSC board meeting then took place in Jakarta on 18 November 2008. In relation to issues of tax and transfer pricing, it was noted in the minutes of that meeting that, in respect of KSC economics, “[b]oth parties agreed that an acceptable formula had to be devised to take into account the fact that it was unlikely that the current coal off-take and coal supply arrangements could continue due to changes to tax laws”. The KSC board also ratified the September 2008 Agreement relating to the addition of US$10.6m to the working capital of the Project. The issue of how the additional US$12.5m would be funded was not resolved at the meeting.
- [41]
[41] In relation to the commissioning of the plant, Mr Duncan tabled a draft commissioning/operation plan for review and comment by the Bayan parties ahead of the next board meeting where it was agreed that this would be discussed in more detail.
- [42]
[42] On 25 November 2008, BCBCS and BR (not BI) each executed a loan agreement with KSC, in which BCBCS and BR each agreed to loan up to US$15m to finance KSC’s working capital and other corporate activities. This was the second loan agreement which the Bayan parties and the WEC parties executed with KSC (see [24] above). The agreed loan amounts were later increased to US$25m in addenda dated 11 December 2008.
- [43]
[43] On 12 January 2009, the Indonesian Government passed Law No 4 of 2009 on Mineral and Coal Mining, which, among other things, imposed the requirement that permits known as Izin Usaha Pertambangan Operasi Produksi (“IUP”), had to be obtained before parties could mine or sell Indonesian coal.
- [46]
[46] After a KSC board meeting on 11 and 12 February 2009, the parties entered into a Deed of Novation of the JV Deed, dated 12 February 2009, in which it was agreed that BR would be substituted for BI as a party to the JV Deed and that BCBCS would be substituted for BCBC as a party to the JV Deed. In the result, BR and BCBCS became the new parties to the JV Deed.
- [47]
[47] On 17 February 2009, Mr John McGuigan (“Mr McGuigan”), who was the Chairman of WEC at the time, wrote to Mr Chin to document the matters that had been agreed on at the KSC board meeting that had been held on 11 and 12 February 2009 and to address other unresolved issues. He attached two draft memoranda, one covering the future relationship between the Bayan parties and the WEC parties in Indonesia and the other dealing with various funding issues in relation to KSC.
- [48]
[48] This led to an exchange of correspondence between the parties, which eventually culminated in the parties entering into two documents on 16 March 2009: a Memorandum of Understanding (KSC Funding Arrangements) (“the Funding MOU”) and a Memorandum of Understanding (Expansion of joint venture).
- [49]
[49] In an internal email dated 31 March 2009, Mr Maras noted that the Bayan parties’ contribution of US$9.1m for February and March meant that by early April, the Bayan parties would have fully funded their share of capital for the “Production Module/Power Station” for the completion of the Project, leaving only their 49% share of the commissioning budget outstanding “which [WEC] hope[d] they will agree [to] during meetings scheduled in Jakarta Monday - Wednesday next week”.
- [50]
[50] Meetings took place in Jakarta on 14 and 15 April 2009. In minutes of the meeting under Commissioning Proposal it was noted:
- [51]
[51] On 30 April 2009, a Certificate of Practical Completion was issued in relation to the work carried out by Thiess under the D&C Alliance Contract.
- [53]
[53] On 16 September 2009, KSC entered into an agreement with Standard Chartered Bank (“SCB”) for a US$10m working capital loan facility (“the SCB Loan Facility”).
- [55]
[55] On 15 December 2009, KSC made the first draw down of US$6m under the SCB Loan Facility.
- [57]
[57] On 7 April 2010, Mr Maras sent Mr McLeod the KSC cash flow to August 2010 and made funding proposals. This led to an exchange of correspondence in which by the end, Mr Maras said that the WEC board had approved a US$6m Priority Funding loan to KSC from WEC, through BCBCS. Mr McLeod said that the Bayan parties would “provide the feed coal and be paid US$8/mt and defer US$7/mt until Commercial Production starts”.
- [58]
[58] This led to the Priority Loan Funding Agreement (“PLFA”), which was signed by KSC, BR and BCBCS on 17 December 2010 but backdated to 22 April 2010. The PLFA provided as follows:
In essence, BCBCS would make available a revolving working capital facility of up to US$20m (“the Priority Facility”) and BR would make a “Coal Advance” to KSC which involved KSC paying Bara US$8 per tonne for feedstock coal with the balance US$7 per tonne being looked after by BR.
- [60]
[60] In response on 7 June 2010, Mr Maras referred to an agreement by WEC to provide the necessary funds to KSC to cover the temporary repayment of US$5m and US$3m on the SCB Loan Facility due on 11 June 2010 and 23 June 2010 respectively. He asked Mr Chin or Mr McLeod to confirm by return that the Bayan parties would ensure that WEC would be repaid by KSC immediately when the reciprocal redraw on the SCB Loan Facility occurred on 11 and 23 June 2010 respectively.
- [61]
[61] This correspondence led to further exchange between Mr Maras and Mr McLeod on 7 to 9 June 2010, which is considered under Issues 1 and 3 below.
- [62]
[62] On 23 September 2010, Regulation 17 of 2010 on Procedures to Determine the Benchmark Price for the Sale of Minerals and Coals (“the HBA Regulations”) was introduced to determine the benchmark price for the sale of minerals and coal in Indonesia (“the HBA prices” or “the HBA benchmark price”). The HBA Regulations came into force on 1 October 2010.
- [63]
[63] On 12 October 2010, a KSC Board Meeting was held in Jakarta. The minutes record that a total of US$110.4m had been advanced by shareholders as at 31 August 2010 of which WEC, via BCBCS, had advanced US$69.6m (63%) and the Bayan parties had contributed US$40.8m (37%). It stated that a further US$1.9m was advanced by BCBCS during September 2010 as part of the Priority Facility and that a total of approximately US$14m had been advanced to date by BCBCS as part of the Priority Facility. In addition, it was stated that a schedule was presented by Mr Maras outlining further funding requirements of approximately US$7m to 31 December 2010.
- [64]
[64] On 3 March 2011, a further KSC board meeting was held in Jakarta. In that meeting, the Bayan parties continued to state that their position “[had] not changed and they [would] not contribute until the plant [was] fully commissioned”.
- [65]
[65] On 29 March 2011, BCBC, BR, Bara and KSC entered into the first Side Letter. On 5 April 2011, BCBC, BR, Bara and KSC entered into the second Side Letter (“the April 2011 Side Letter”). The April 2011 Side Letter superseded the first Side Letter.
- [66]
[66] Between March and June 2011, KSC entered into two coal supply agreements (“the 2010 CSAs”) with Bara and FSP respectively. The 2010 CSAs replaced the 2008 CSA. These agreements were backdated to 1 October 2010, the date when the HBA Regulations came into force.
- [67]
[67] On 29 June 2011, the parties entered into an addendum to the PLFA extending the Availability Period (defined at [58] above) to 31 December 2011.
- [68]
[68] On 18 October 2011, Mr Neil circulated a draft agenda for a KSC board meeting planned for 2 November 2011. The agenda items were:
- [69]
[69] On 2 and 3 November 2011, there was a KSC board meeting in Jakarta. Mr Maras’ notes record that Mr Chin raised the issue of the future feasibility of the Project and that the major shareholders of BR had instructed its management to find a solution, which Mr McLeod said was to “get out of [the] project” and Mr Chin said was to “‘sell’ [the] project back to WEC”.
- [70]
[70] On 9 November 2011, WEC made a public announcement on the Australian Stock Exchange:
- [71]
[71] On 21 November 2011, BCBCS wrote to BR stating that it considered that BR had breached the terms of the JV Deed as amended and novated and requesting that the breach be remedied. It was stated that at a meeting on 17 November 2011, BR had said that Bara was only prepared to supply coal to KSC on condition that WEC repaid in full loans of approximately US$45m made by BR to KSC and that Bara intended to cease supplying coal immediately unless WEC agreed to pay BR that amount.
- [72]
[72] On 24 November 2011, BR responded to the letter from BCBCS saying that the letter was misconceived. It stated that BR had maintained that the supply of coal by Bara to KSC must be at HBA prices and that Bara “will supply coal based on the [2010 CSAs] which supersedes the [2008 CSA].” It also stated that “at no point in time did we link the issue of [the Bayan parties]’ intention to withdraw from the joint venture to an issue of cessation of coal supply”. It then demanded the retraction of the letter of 21 November 2011.
- [73]
[73] On 29 November 2011, WEC responded to BR and stated:
- [74]
[74] On 2 December 2011, BR replied to WEC and stated:
- [75]
[75] On 6 December 2011, an Extraordinary General Meeting (“EGM”) of KSC shareholders took place in Jakarta. In the draft minutes produced by Mr Oliver Khaw (“Mr Khaw”), BR’s legal counsel, with revisions by Ms Andromeda Neale (“Ms Neale”), WEC’s Business Development Counsel, it was noted that Mr Chin had reiterated “BR’s intention to quit the joint venture as the [P]roject [was] no longer viable and offer to sell its 49% in KSC to BCBCS [or] WEC”.
- [76]
[76] On 12 December 2011, the WEC parties wrote to BR asking it to “confirm that [it would] fund 49% of KSC’s funding requirements … by no later than 10am Jakarta time Tuesday 13 December 2011, being the time at which it was agreed that the EGM of 6 December 2011 would be adjourned”. They added that if BR failed to do so, they would be “commencing proceedings in Singapore to recover damages arising from BR’s breach of its funding obligation, and from its breach of [its] obligation to procure [Bara] to supply coal to KSC in accordance with the [2010 CSAs] between Bara and KSC dated 1 October 2010 as amended on 5 April 2011…”
- [77]
[77] In reply on 13 December 2011, BR sent a “Default Notice” to WEC and BCBCS in which it alleged breaches of the JV Deed by BCBCS and total failure of consideration and purpose of the JV Deed. It also gave notice that the Plaintiffs were to remedy all the defaults within 30 days.
- [78]
[78] On 20 December 2011, the WEC parties replied to BR, maintaining their position on BR’s breach of its funding obligation, requesting confirmation that BR would fund 49% of payments to SCB amounting to US$3.92m relating to the SCB loan and requesting confirmation that BR would provide 49% of the funding necessary for the care and maintenance of the Project.
- [79]
[79] BR replied to WEC and BCBCS on 22 December 2011, agreeing to transfer certain funds relating to the SCB Loan Facility, solely for the purposes of mitigating any further loss and damage and without any admission of liability and on the basis that BR reserved its rights. In relation to the funding for the care and maintenance of the Project, BR said:
- [80]
[80] On 27 December 2011, BCBCS and BCBC commenced the High Court action against BR and BI.
- [81]
[81] On 4 March 2015, the High Court transferred the action to the SICC.
- [82]
[82] The hearing of the agreed issues took place from 16 to 26 November 2015, with oral closing submissions being heard on 14 January 2016.
Witness evidence
- [83]
[83] The Plaintiffs called the following witnesses to give evidence:
(a) Mr Duncan (see above at [10]) – He is the current Chairman of WEC and a civil engineer with over 60 years’ experience in project management of large international mining and infrastructure development projects as well as the development and operation of ten coal mines. As Chairman, he was the driving force for WEC, through BCBC, to use the BCB Process in coal markets throughout the world. He recounted the history of the Project from 2005 until 2011.
(b) Ms Neale (see above at [75]) – She was the Business Development Counsel of WEC from June 2007. Her role was to assist in various areas relating to WEC’s business development and legal activities. She explained her involvement in the various meetings and discussions starting with the Jakarta MOU and ending in the breakdown of relations in November and December 2011.
(c) Mr Maras (see above at [34]) – He was the CFO of WEC from July 2006. He also assumed responsibilities as CFO of BCBC and BCBCS and worked part-time for WEC until April 2008 when he commenced working full-time. He gave evidence of his involvement in the various meetings and financial dealings from 2006 until 2011.
(d) Mr Clark (see above at [7]) – Apart from being the general manager of BCBC from 2004 to 2010, he was also a director of technology of WEC from 2006 till his retirement in 2010. He has a degree in metallurgy and has written extensively on issues relating to mineral agglomeration, drying, coal liquefaction, fluid dynamics, briquetting and coal cleaning. He is the originator of eight patents. Between 1969 and 2002 he was employed by the CSIRO, Australia’s national science agency, and from 1991 to 1996, he was the Project Manager of CSIRO’s coal briquetting programme. He managed the coal briquetting programme, including a joint development programme with K R Komarek Inc (USA), one of the major world producers of briquetting and agglomeration equipment, Tra-Det Inc, an internationally recognised leader in thermal coal dryer design and optimisation and later introduced Griffin Coal Mining Company Pty Ltd, a subbituminous coal mining company in Western Australia to the programme. This led to the BCB Process. Subsequently from 1996 until his departure from CSIRO in 2002, he was the group manager of the Coal Treatment Group.
(e) Mr Hitchings (see above at [26]) – He was the Manager of Engineering of WEC and Director of Operations and Infrastructure of BCBC from July to October 2011. He has some 44 years’ experience of civil engineering in the international mining and construction industries. From 2006 to 2011, he worked for WEC as a consultant and was involved in the Project. He gave evidence of his involvement from 2006 until about April 2010.
- [84]
[84] The Defendants called the following witnesses:
(a) Mr Neil (see above at [34]) – As a director and Chief Development Officer of BR and a director of BI, he explained his involvement in the agreements entered into between the parties from the 2006 Heads of Agreement until the 2011 Side Letters, as well as his involvement up to the end of 2011.
(b) Mr McLeod (see above at [34]) – As a director and the CFO of BR and a director of BI, he dealt with various financial matters in which he had been involved from 2007 until early 2012.
(c) Mr Chin (see above at [26]) – He is a shareholder, the President Director and Chief Executive Officer of BR and a director of BI. He detailed his involvement in the December 2007 KSC board meeting leading to the Jakarta MOU and to meetings and events after November 2011.
(d) Mr Lim (see above at [8]) – He is a director and the Chief Operating Officer of BR and also a director of BI. He gave evidence of his involvement in discussions at, and following, the Lexington Conference in May 2005 and his visit to the Collie plant in December 2005.
- [85]
[85] In addition to filing an initial affidavit of evidence-in-chief (“AEIC”), all witnesses except Mr Lim also filed a reply witness statement.
The issues
- [86]
[86] By agreement, the parties asked the Court to decide, in a first tranche, issues relating to the contractual obligations of the parties without going into whether these obligations had been breached or not; those and further issues will be decided in later tranches. The nine issues that the parties had initially agreed on can be broadly grouped into three categories:
(a) funding issues;
(b) coal supply issues; and
(c) counterclaim issues.
- [87]
[87] Whilst those issues need to be considered in context, the scope of admissible evidence was limited. Much of the evidence was put forward to explain the position of the parties and the way in which the Project progressed until the events of late 2011/early 2012 and, although not directly relevant to the issues, assisted in putting the issues in the context of the overall dispute between the parties.
- [88]
[88] The parties formulated a list of 9 issues for Tranche 1 as follows:
- [89]
[89] At various stages, the Plaintiffs withdrew or made concessions on Issues 3(a), (c), (d) and Issue 8. As a result of an agreed framing of WEC’s guarantee obligations set out in Exhibit P-7, Issue 9 also fell away. The agreed issues for the decision of this Court in this tranche of the trial are thus Issues 1, 2, 3(b), 4, 5, 6 and 7 (“the Agreed Issues”).
- [90]
[90] As we have stated at [16] above, the original parties to the joint venture were BI and BCBC. Subsequently, through the Deed of Novation, BI was substituted by BR and BCBC was substituted by BCBCS (see [46] above). Through the course of the trial and during submissions, the parties seemed willing to refer to these entities interchangeably. Therefore, for ease of reference, we will hereafter refer to the joint venture parties as BR and BCBCS. For the avoidance of doubt, our references to “BR” and “BCBCS” are also, where relevant, references to BI and BCBC respectively.
Funding issues
- [91]
[91] There are three funding issues to be determined: Issues 1, 2 and 3(b). As earlier noted, since the Plaintiffs are no longer pursuing Issues 3(a), (c) and (d), for ease of reference, we will simply refer to Issue 3(b) as “Issue 3”. There have been slightly differing formulations of the three issues in the course of these proceedings. We will adopt the formulation of the issues as set out in the Plaintiffs’ Closing Submissions. The three issues are thus:
(a) Issue 1: In the period between November 2011 and 2 March 2012, was BR obliged to provide funding for the commissioning, operations and maintenance of the Tabang Plant in accordance with cl 4 of the Funding MOU and (if so) what was the scope of the obligation?
(b) Issue 2: In or around November 2011, was BR obliged to consent to KSC obtaining a further advance of US$3.033m from SCB to repay BCBCS’ temporary loan to KSC?
(c) Issue 3: In the period between November 2011 and 2 March 2012, was BR obliged to contribute to 49% of KSC’s care and maintenance costs and (if so) what was the scope of the obligation?
Issues 1 and 3
Overview
- [92]
[92] Just as the Plaintiffs did in their Closing Submissions, we will consider Issues 1 and 3 together since they are related.
- [93]
[93] Mr Francis Xavier SC (“Mr Xavier”), counsel for the Plaintiffs, distinguished Issue 1 from 3 by reference to the EGM of KSC’s shareholders on 6 December 2011. By a letter dated 29 November 2011, BCBCS informed BR that, in BCBCS’ assessment, KSC would require funding of about US$20m to the end of June 2012. BR refused to fund 49% of that US$20m. In light of BR’s refusal, it was decided at the EGM that KSC would suspend its operations and go into a care and maintenance programme. Issue 1 concerns BR’s alleged obligation to fund 49% of the US$20m assessed by BCBCS prior to the EGM. Issue 3 concerns BR’s refusal to fund 49% of KSC’s care and maintenance expenses following the EGM.
Parties’ arguments
- [94]
[94] The essence of the Plaintiffs’ argument is that cl 4 of the Funding MOU imposed an obligation on BR to fund 49% of the US$20m. According to the Plaintiffs, BR’s obligation to fund was regardless of amount or duration and regardless of whether BR consented to the expenditure being incurred by KSC.
- [95]
[95] In response, the Defendants say that any obligation on their part arising out of the Funding MOU was subject to their overriding rights under cl 7.1 of the JV Deed. The Defendants submit that, in any event, whether construing the Funding MOU in its plain and ordinary meaning or reading the document contextually, cl 4 did not give rise to the funding obligation alleged by the Plaintiffs.
- [96]
[96] In further response to the Plaintiffs’ argument, the Defendants claim that BCBCS gave an enforceable undertaking to BR that BCBCS alone would be solely responsible for funding KSC until the Tabang Plant achieved commercial production. The Plaintiffs deny having given such an undertaking and contend that, in any case even if there had been any such undertaking, it would have been premised on the Defendants ensuring a continuous supply of coal to KSC.
- [97]
[97] The Plaintiffs accept that the alleged funding obligation on BR’s part was modified by the PLFA, but argue that it only did so temporarily. They submit that once the Priority Facility had been completely drawn down or, alternatively, upon expiry of the Availability Period of the Priority Facility, BR’s obligation was reinstated.
- [98]
[98] We will discuss Issues 1 and 3 by construing the relevant provisions of the JV Deed before examining the proper construction of cl 4 of the Funding MOU. Thereafter, we will deal with the effect (if any) of the PLFA on BR’s rights and obligations. Finally, on Issues 1 and 3, we will consider the allegation that the Plaintiffs undertook to fund the Tabang Plant until it achieved commercial production.
Contractual interpretation under Singapore law
- [99]
[99] The JV Deed and the Funding MOU are expressly governed by Singapore law. It will be convenient at the outset to summarise the principles of contractual construction under Singapore law.
- [100]
[100] Singapore law adopts a contextual approach to the interpretation of contracts (see Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte Ltd [2008] 3 SLR(R) 1029 (“Zurich Insurance”) at [132]). This means that the Court ascertains the intention of the parties at the time when they entered into a contract based on all “relevant” evidence.
- [101]
[101] The starting point should be the text of the contract to be construed (see Y.E.S. F&B Group Pte Ltd v Soup Restaurant Singapore Pte Ltd (formerly known as Soup Restaurant (Causeway Point) Pte Ltd) [2015] 5 SLR 1187 at [32]). But extrinsic evidence is admissible to interpret the words of an agreement, provided the evidence is “relevant, reasonably available to all the contracting parties and relates to a clear or obvious context” (see Zurich Insurance at [132(d)]).
- [102]
[102] Extrinsic evidence is “relevant” to the extent that the material sought to be adduced demonstrably affected the way in which the parties understood specific terms of a contract. Thus, extrinsic material must “always go towards proof of what the parties, from an objective viewpoint, ultimately agreed upon” (Zurich Insurance at [132(d)]). For this reason, evidence of a subjective intention that has not been clearly communicated to the other party at the time of contracting will usually be inadmissible. At all times, the Court should be “careful to ensure that extrinsic evidence is used to explain and illuminate the written words, and not to contradict or vary them” (see Zurich Insurance at [125] and [132(f)]).
- [103]
[103] The Singapore Court of Appeal has not closed the door to subsequent conduct being used as an aid towards the construction of a contract. However, the Court has indicated that such evidence is unlikely to be admissible in many cases due to non-compliance with the tripartite requirements of relevance, reasonable availability and the presence of a relation to a clear or obvious context (see Zurich Insurance at [132(d)] and more recently the decision of Hewlett-Packard Singapore (Sales) Pte Ltd v Chin Shu Hwa Corinna [2016] 2 SLR 1083 at [56]).
The JV Deed
- [104]
[104] Clause 7.1 of the JV Deed provides as follows:
Clause 7.1 has to be read in conjunction with cll 8 and 20.13 of the JV Deed.
- [105]
[105] Clause 8.1 provides that any Relevant Amount, defined as any amount in excess of KSC’s own resources to satisfy its needs under the Business Plan, will “[u]nless agreed in advance by each of the Members, be raised by borrowing from third parties without the need for any guarantees from the Members”. Where the requisite amount could not be raised on reasonable terms by borrowing from third parties, cl 8.2 provided for the shareholders to provide the same to KSC through loans.
- [106]
[106] Clause 8.4 states as follows:
- [107]
[107] Clause 8.5 deals with the situation where a Member undertakes to contribute towards an amount required by KSC, but later fails to provide the same. In such a situation, the other Member may pursue the remedies specified in cl 8.5, including terminating the JV Deed under the provisions of cl 13.
- [108]
[108] Clause 20.13 stipulates as follows:
- [109]
[109] In their natural and ordinary meaning, the combined effect of cll 7, 8 and 20.13 of the JV Deed may consequently be encapsulated as follows:
(a) Any funding required by KSC has to be unanimously agreed by BCBCS and BR (cl 7.1).
(b) BCBCS and BR could refuse to provide additional funding for KSC in their absolute discretion (cl 20.13).
(c) BCBCS and BR could consent to provide additional funding by an agreement to such effect or by approving a Business Plan calling for the provision of the additional funding (cl 8).
(d) If BCBCS or BR agreed to provide additional funding for KSC, their respective maximum obligations would not exceed 51% and 49% of the Relevant Amount (cl 8.4).
(e) If BCBCS or BR agreed to provide additional funding for KSC, they were bound by such consent so that, if a party defaulted in its obligation to provide funding, the other party would be entitled to enforce the obligation to fund by means of the remedies in cll 8 and 13 (cl 8.5).
- [110]
[110] We do not understand the Plaintiffs to be contending differently from what has just been summarised. It is instead their case that, pursuant to cl 8 of the JV Deed, by entering into the Funding MOU, BR undertook to provide 49% of KSC’s funding requirement without limit as to amount or duration and without need for further consent to be obtained from BR.
The Funding MOU
- [112]
[112] The Funding MOU provides as follows:
- [113]
[113] The Plaintiffs put their case on cl 4 of the Funding MOU in several ways.
- [115]
[115] With respect, we disagree.
- [116]
[116] The preamble to the Funding MOU explicitly states that “any terms and conditions of the [JV] Deed not specifically amended by this MOU shall remain valid and shall continue to be in force”. One would have expected that if the parties were intending to give up their significant rights under cll 7.1 and 8 to withhold consent to any call for funding, they would have clearly said so. But nothing is said in cl 4 of the Funding MOU about overriding cll 7.1, 8 and 20.13 of the JV Deed. The presumption must be that the latter provisions remained in force.
- [118]
[118] Secondly, the Plaintiffs refer to an email of 6 March 2009 from BR’s legal counsel, Mr Khaw. They say that the email shows that the expression “subject to the mutual agreement of the Parties” in cl 2 of the Funding MOU was inserted at BR’s request. This allegedly bolsters the submission that the omission of the same expression in cl 4 was deliberate. The Plaintiffs reason that the expression was not inserted into cl 4 because BR was knowingly giving up its right to veto further funding requests.
- [121]
[121] The Plaintiffs also rely on the evidence of Mr Maras as to his understanding of cl 4. But we do not find Mr Maras’ subjective understanding of cl 4 to be of assistance in its construction. As the Defendants note, there is no contemporary document or other evidence that shows that Mr Maras’ subjective understanding was communicated to anyone on BR’s side prior to the execution of the Funding MOU.
- [122]
[122] Thirdly, the Plaintiffs point to certain extrinsic matters as contextually establishing that cl 4 of the Funding MOU was intended to override cll 7.1 and 8 of the JV Deed. Those extrinsic matters and the Plaintiffs’ arguments may be encapsulated as such:
(a) The failure to issue a revised business plan following the engagement of Thiess. The Plaintiffs say that such a failure is evidence that BCBCS and BR had decided to no longer follow the procedure of preparing a business plan for the approval of funding under cll 4.2 and 7.1 of the JV Deed. They infer from such a decision that from December 2007, funding was to be in accordance with some other mechanism, such as that in cl 4.
(b) The entry of the parties into the September 2008 Agreement (see [36] above). By this document, the parties agreed to raise the project cost expenditure cap from US$50m to US$60.6m. The Plaintiffs draw attention to cl 6 of the September 2008 Agreement which states:
The Plaintiffs observe that, in the agendas and minutes of KSC meetings on 18 November 2008 and 4 June 2009, KSC’s operating expenditure was not tabled for discussion or for agreement between BCBCS and BR. From these indications, they infer that shareholders’ consent was never required for operating costs and the agreement between the parties had always been that such costs would be funded on a 51% to 49% ratio. They conclude that, if so, the parties must have, by cl 4, done something more than agree on a sharing ratio.
(c) BR’s adverse reaction to BCBCS’ proposal in February 2009 that, because BCBCS was experiencing cash-flow difficulties, work on the power plant (which formed part of the Project) should be suspended. By email dated 5 February 2009, BR responded:
BR’s response shows, according to the Plaintiffs, that BR itself did not regard BCBCS as having the right to unilaterally exit from (and cease to fund) the Project simply because it wished to do so.
- [123]
[123] We do not think that the extrinsic evidence detailed above is “relevant” in the sense as explained in Zurich Insurance. The evidence does not unequivocally point to the Plaintiffs’ suggested conclusions. The material does not provide a clear contextual framework from which it may objectively be deduced that, at the time, the parties regarded cl 4 as having the meaning and consequences which the Plaintiffs now contend.
- [126]
[126] Fifthly, the Plaintiffs submit in the alternative that cl 7.1 should be read as being qualified by the obligation of good faith in cl 17.3 of the JV Deed. Clause 17 provides:
- [127]
[127] Clause 1.1 of the JV Deed defines “Good Faith” as follows:
- [128]
[128] The Plaintiffs submit that, in light of cl 17.3, even if BR’s consent was required for KSC’s funding of its operations up to June 2012, BR was obliged to consider the additional funding requested for KSC in a fair, reasonable and honest manner that would not impede or restrict the performance of the JV Deed.
- [129]
[129] We accept that cl 7.1 must be read in the context of the entire JV Deed (including cl 17.3). But that alone would not assist the Plaintiffs’ case.
- [131]
[131] The obligation of “good faith” as narrowly defined in cl 1.1 would not have precluded BR, having considered BCBCS’ clarification, from then deciding in light of BR’s own situation not to contribute further funding. The requirements (1) to be “fair, reasonable and honest”; (2) to act reasonably to give effect to the JV Deed; and (3) to not impede BCBCS’ performance of its obligations, would not by themselves have restricted the absolute discretion given to BR by cl 20.13 of the JV Deed. In other words, the good faith obligation in cl 17.3 did not mean that BR was constrained to approve any and all additional expenditure assessed by BCBCS.
Effect of the PLFA
- [132]
[132] We turn to consider the effect (if any) of the PLFA on BR’s rights and obligations.
- [133]
[133] The Plaintiffs’ case on the PLFA is that it was only a short-term arrangement and was not intended to completely supersede BCBCS’ existing arrangements with BR (including those under the Funding MOU). In support of their submission on the temporary nature of the PLFA, the Plaintiffs refer to two provisions in the document. Article 9.7 provides that the PLFA did “not alter any of the terms under the existing shareholder loan or MOU Funding Agreements between [KSC], BCBCS and BR”. Article 11 provides that the PLFA was “a short term priority funding facility which [may be] extended by mutual agreement of both Parties”.
- [134]
[134] The Availability Period for the Priority Facility of US$20m was initially to last until 30 June 2011. The Priority Facility was later increased to US$40m and the Availability Period extended to 31 December 2011 by an addendum dated 29 June 2011 (see [67] above). Although the PLFA did not expressly state what was to happen once the Priority Facility was exhausted (as it did in August 2011), the Plaintiffs submit that in light of Arts 9.7 and 11, the parties intended the arrangements under the Funding MOU to be reinstated.
- [136]
[136] We would simply indicate our agreement with the Plaintiffs that, in light of Arts 9.7 and 11 of the JV Deed, the PLFA was only intended to have temporary effect. Upon exhaustion of the Priority Facility or upon expiration of the Availability Period, the parties’ obligations under the Funding MOU resumed. Nonetheless, in light of our conclusion on the limited effect of cl 4 of the Funding MOU, the exhaustion of the Priority Facility or the expiration of the Availability Period would not have affected the Defendants’ rights under cll 7.1 and 8 of the JV Deed.
Whether there was a binding undertaking by BCBCS to pay costs up to commercial production
- [137]
[137] We turn to discuss the Defendants’ allegation that the Plaintiffs had undertaken to fund the Tabang Plant until it achieved commercial production.
- [138]
[138] We briefly set out the chronology of events giving rise to the alleged undertaking by BCBCS (via WEC):
(a) By a letter dated 7 June 2010, BR wrote:
(b) By a letter on the same day, the Plaintiffs (through Mr Maras) responded:
(c) By an email dated 9 June 2010, BR sought an undertaking that BCBCS would provide additional funds (over and above the US$6m obtained from the Priority Facility) in the event that KSC needed such funding. BR wrote:
(d) By an email of the same day, WEC (through Mr Maras) stated that WEC was “conscious” of BR’s position that:
(e) By an email of the same day, BR (through Mr McLeod) responded:
- [139]
[139] We are unable to read the email correspondence as giving rise to an unambiguous undertaking on BCBCS’ part (given via WEC) that it would fund the joint venture until commercial production. It is also not apparent from the correspondence that Mr McLeod understood Mr Maras to have given such an undertaking.
- [140]
[140] The sentence “I assume this [is] the undertaking that you were looking for?” in Mr Maras’ email of 9 June 2010 ends with a question. Mr Maras thus seems to be asking Mr McLeod whether the undertaking sought is related to the “obvious” fact highlighted in the previous sentence that “any further funding required by KSC until commercial production will only be met by one of its shareholders – [WEC]”. It is clear, in this regard, that though WEC was referred to in the correspondence between Mr McLeod and Mr Maras, the parties were in substance referring to BCBCS as it was BCBCS, and not WEC, that was the relevant shareholder of KSC and the entity through which funds were injected into KSC.
- [141]
[141] Mr Maras refers in a later paragraph of the same email to “our undertakings above”. But this appears to be a reference to “the US$5m and US$3m that we have undertaken to provide to KSC in temporary “24 hour” funding on 11/6/10 and 23/6/10” [emphasis added] in the immediately preceding sentence.
- [142]
[142] It is possible that Mr Maras was deliberately vague about whether he was giving an undertaking of the nature sought by BR. Mr Maras may have wanted to appear as if he was giving an undertaking when in fact he was not doing so. This would be consistent with Mr Maras’ evidence in cross-examination that he did not regard the email as “a legal document” giving rise to a legally binding undertaking. At one stage in cross-examination, Mr Maras conceded that he did provide an undertaking of the nature sought by BR. But he qualified the concession by saying that he was under the impression that the undertaking would not be legally binding since it had not had prior board approval.
- [143]
[143] Whatever Mr Maras may have subjectively thought at the time he was writing, it is far from clear that Mr McLeod understood him to be giving an undertaking.
- [144]
[144] Mr McLeod emailed back: “On the basis of [WEC] continuing to fund KSC we agree that the SCB redraw will immediately be transferred back to [WEC] and will use best efforts to ensure this happens.” On its face, the reply merely states that, provided WEC (via BCBCS) continues to fund the joint venture, BR agrees to allow monies from the SCB Loan Facility to be immediately used to pay back the funds injected by WEC (via BCBCS) on 11 and 23 June 2010.
- [145]
[145] Mr McLeod’s email does not then address the question of an undertaking. Nor does it confirm an understanding that BCBCS would continue to fund the joint venture until commercial production. Indeed, given the vague nature of Mr Maras’ email of 9 June 2010, as we have pointed out at [142] above, it is hard to see how Mr McLeod could reasonably have concluded that BCBCS had given any clear-cut undertaking. Under cross-examination, Mr McLeod himself accepted that “I think I got [the undertaking] from Ivan Maras but I still thought it was a topic that was needing [sic] discussion at the senior level” [emphasis added]. This buttresses our conclusion that there was no clear understanding between the parties that an undertaking had been given by BCBCS.
- [146]
[146] In our judgment, the issue of an undertaking on the part of BCBCS to fund until commercial production was left in abeyance, the parties having reached a stalemate in their 9 June 2010 correspondence.
Issue 2
- [147]
[147] We move on to Issue 2, which was framed as such: in or around November 2011, was BR obliged to consent to KSC obtaining a further advance of US$3.033m from SCB to repay BCBCS’ temporary loan to KSC?
- [148]
[148] On 4 November 2011, BCBCS advanced a loan of US$3.033m to KSC to enable it to repay the SCB Loan Facility. When BCBCS asked BR to consent to KSC drawing on the SCB Loan Facility to repay BCBCS for the US$3.033m loan, BR refused.
- [149]
[149] The Plaintiffs submit that that BR was wrong to have refused. The Plaintiffs say that by the email correspondence of 7 and 9 June 2010 already set out above, BR agreed to allow KSC to immediately draw on the SCB Loan Facility to pay back loans from BCBCS. In response, the Defendants claim that BR only agreed that the SCB Loan Facility could be drawn on to repay BCBCS for monies loaned to KSC on 11 and 23 June 2010, but did not agree to a further advance being made from the SCB Loan Facility to repay the loan from BCBCS on 4 November 2011
- [150]
[150] As an alternative argument, the Plaintiffs submit that BR is estopped from denying that KSC could use the SCB Loan Facility to repay the loan of US$3.033m to BCBCS.
- [151]
[151] Further, the Plaintiffs also say that BR was obliged to repay 49% of the US$3.033m loan in any event. This is because, if the Plaintiffs’ monies had not been used to pay off the US$3.033m, BR would have had to bear 49% of the US$3.033m under the JV Deed as modified by the Funding MOU.
- [152]
[152] In oral submissions, Mr Xavier frankly accepted that his argument on Issue 2 was difficult. We agree that there are difficulties:
(a) The email correspondence that took place in June 2010, fairly read, shows that BR only agreed to the SCB Loan Facility being used for immediate re-payments of BCBCS’ 11 and 23 June 2010 loans. Nothing is unambiguously said in the email correspondence about how later injections of cash into KSC by BCBCS would be handled insofar as immediate repayment was concerned.
(b) The immediate reimbursement of the 11 and 23 June 2010 BCBCS loans, are only two instances, and can hardly constitute a representation that future cash injections will be dealt with in a similar fashion. In the absence of a clear representation to that effect, there cannot be an estoppel.
(c) Whether or not BR was under a separate obligation (under the JV Deed and/or the Funding MOU) to pay 49% of the US$3.033m would have no logical bearing on whether BR was obliged to consent to the SCB Loan Facility being used to repay BCBCS.
- [153]
[153] Accordingly, we conclude that BR was not obliged to consent to the SCB Loan Facility being used to repay BCBCS’ loan of US$3.033m to KSC.
Conclusion on Funding Issues
- [154]
[154] We would answer the three Funding Issues as follows:
(a) On Issue 1, BR was not obliged to provide funding. Clause 4 of the Funding MOU did not override cll 7.1 and 8 and of the JV Deed.
(b) On Issue 2, BR was not obliged to consent to KSC obtaining a further advance of US$3.033m from SCB to repay BCBCS’ temporary loan to KSC on 4 November 2011.
(c) On Issue 3, BR was not obliged to provide funding. There was no clear undertaking by BCBCS at the time to provide funding until commercial production.
Coal supply issues
Issue 4
- [155]
[155] We now turn to Issue 4: whether BR was under an obligation to supply and/or assist in procuring coal to be supplied to KSC on the basis set out in the JV Deed, PLFA and/or the April 2011 Side Letter, in around the period between early November 2011 to 2 March 2012.
- [156]
[156] Clause 2.6(b)(vi)(A) of the JV Deed obliged BR to use its voting power and other rights, and to take any necessary steps, to give full effect to the JV Deed and to ensure that KSC executed an agreement for the supply of coal with its subsidiaries. Clause 3.8(b)(iii) also provides that BR “must assist in procuring [c]oal for the operation of the Business”. The “Business” was defined as “acquiring [c]oal from the Tabang Concession in accordance with the Coal Supply Agreement or from some other party; production of Upgraded Coal Briquettes by upgrading Coal using the [BCB] Process, and marketing and selling Upgraded Coal Briquettes to Utilities including sale of Upgraded Coal Briquettes under the Upgraded Coal Briquette Sale Agreement”.
- [157]
[157] Pursuant to these provisions, KSC entered into the 2008 CSA with Bara. As noted above (at [66]), the 2008 CSA, was subsequently replaced by two agreements – one with Bara and another with FSP (collectively referred to as the 2010 CSAs). For convenience we will refer to “Bara” as including FSP as the parties accept that both Bara and FSP were under similar obligations under the 2010 CSAs to deliver coal to KSC. In the PLFA, only obligations relating to FSP appear in Art 7.1 but in light of the Recital, the parties accept, as is evidently the case, that the obligations to supply coal extended to Bara as well.
- [158]
[158] The provisions of the 2008 CSA to supply feedstock coal included at cl 3.8 a provision that Bara “must supply to [KSC], as and when requested by [KSC], on the same terms and conditions as are set out in this Agreement with respect to price and quality, sufficient [c]oal to allow testing of the: (a) Coal Briquette Processing Plant up to the point where [its] Commissioning is achieved; and (b) each Electricity Generator up to the point where the Electricity Generator Commissioning is achieved”.
- [159]
[159] The recital to the PLFA, which was signed by KSC, BCBCS and BR on 17 December 2010 but backdated to 22 April 2010, reads:
- [160]
[160] Article 7 of the PLFA dealt with the supply of feedstock coal to KSC (see above at [58]):
(a) Article 7.1 of the PLFA provides that “[d]uring the Availability Period [defined as the period up to 30 June 2011 or as mutually agreed between the Parties], BR shall ensure that FSP supplies Feedstock Coal to [KSC]”.
(b) Article 7.2 of the PLFA provides that “the deferred balance of the Market Price less US$8 per tonne of Feedstock Coal supplied to [KSC] during the Availability Period represents BR’s contribution to the Priority Loan being made to [KSC], and this is reflected in the amount of the Coal Advance”.
(c) “Coal Advance” is defined as “[t]he Priority Coal Supply enables [KSC] to procure the feedstock coal from FSP at Market Price of which US$8 per tonne would be payable immediately by [KSC] while the deferred balance shall be payable to FSP pursuant to the provisions herein relating to [the] Priority Loan”.
(d) “Priority Coal Supply” is defined as “[t]he supply of feedstock coal to [KSC] by FSP at Market Price of which US$8 per tonne would be payable immediately by [KSC] while the deferred balance shall lead to the establishment of the Coal Advance”.
- [161]
[161] The 2010 CSAs contained similar provisions to the 2008 CSA save that amendments were effected for the sale of feedstock coal by Bara to KSC to comply with the new legislation and the HBA Regulations. The 2010 CSAs contained an identically worded clause, numbered cl 3.9, to cl 3.8 of the 2008 CSA referred to above (at [158]).
The Plaintiffs’ case
- [163]
[163] The Plaintiffs rely on cl 3.8(b)(iii) of the JV Deed and Art 7.1 of the PLFA to establish BR’s obligation to supply or assist in the supply of coal to KSC in November 2011. They submit that so long as the joint venture was alive, cl 3.8(b)(iii) of the JV Deed and Art 7.1 of the PLFA operated to impose an obligation on BR to ensure the supply of feedstock coal to the joint venture.