Singapore International Commercial Court · Decided 5 May 2025
DOI v DOJ and others and another matter
Feedback & support[2025] SGHC(I) 15 · Case no. Originating Application No 20 of 2024 and Summons No 12 of 2025
✱ What happened, in plain English
There is no plain-English summary of this judgment yet.
Ask about this judgment →Laws this judgment relies on
Grounds of decision
Official text from eLitigation
Introduction
- [1]
[1] In SIC/OA 20/2024 (“OA 20”) the Claimant applies to set aside the award, by a majority (“the Majority“), in a Singapore seated arbitration. Its case, in summary, is that the Majority did not apply their mind to the evidence and arguments in the arbitration but came to their decision with a closed mind, as shown in particular by what it said was the cut-and-paste copying in the award of the contents of the awards in prior related arbitrations. In its witness statement in support of OA 20, it said that the award should be set aside on one or more of:
(a) Ground 1: breach of the rules of natural justice in connection with the making of the award by which its rights were prejudiced, pursuant to s 24(b) of the International Arbitration Act 1994 (2020 Rev Ed) (“the IAA”);
(b) Ground 2: inability to present its case, pursuant to Art 34(2)(a)(ii) of the UNCITRAL Model Law on International Commercial Arbitration (“the Model Law”) as given the force of law by s 3(1) of the IAA;
(c) Ground 3: adoption of an arbitral procedure not in accordance with the agreement of the parties, pursuant to Art 34(2)(a)(iv) of the Model Law; and
(d) Ground 4: the award being in conflict with the public policy of Singapore, pursuant to Art 34(2)(b)(ii) of the Model Law.
- [2]
[2] By a late grant of permission, the Defendants say that the Claimant is precluded from seeking and/or has waived its right to seek to set aside the award on the basis of the alleged copying of the awards in the prior related arbitrations. They otherwise say, again in summary, that the Majority applied its mind to all essential issues in the arbitration, that there is no basis to the grounds for setting the award aside, and that the Claimant is engaged in an impermissible attempt to appeal on the merits of the award.
- [3]
[3] In these reasons I will first consider whether the award should be set aside, passing over whether the Claimant is precluded from and/or has waived its right to seek to set it aside. I will then give the reasons for granting the permission above-mentioned to the Defendants, over the Claimant’s opposition: the explanation may be better understood in the light of the preceding consideration. I will then consider whether the Claimant is indeed precluded from and/or has waived its right to seek to set the award aside.
- [4]
[4] Orders sealing the file in OA 20 and for redacted publication have been made, and these reasons are written accordingly. They will explain that the Claimant is not disentitled from seeking to set the award aside, and that the award should be set aside on Ground 1. Although the other grounds become unnecessary, some brief consideration is then given to them.
Background to the arbitration
The CTP-11 Contract
- [5]
[5] The Claimant is a special purpose vehicle formed under the laws of India for the construction and operation of dedicated freight corridors, being a network of railways in India for the exclusive use of freight trains. The Defendants are three companies associated in an unincorporated consortium for the contract next mentioned. One is a Japanese company; the others are Indian companies.
- [6]
[6] By a contract dated 10 November 2016 (“the CTP-11 Contract”), the Claimant engaged the Defendants as the contractor to undertake works for a section of one of the dedicated freight corridors. The CTP-11 Contract was a Design and Build Lump Sum Contract, incorporating the FIDIC Conditions of Contract for Plant and Design Build (First Edition, 1999), as amended by the Particular Conditions of Contract and the Appendix to Bid. The governing law of the CTP-11 Contract was Indian law. The provisions of the CTP-11 Contract relevant to the dispute are identified, so far as necessary, in the course of these reasons.
- [7]
[7] The CTP-11 Contract provided for reference of disputes to a Dispute Adjudication Board (“the DAB”), and if not settled amicably or by a binding decision of the DAB for settlement by arbitration. Through one of the Defendants being a “foreign contractor”, the arbitration was to be in accordance with the rules of arbitration of the International Chamber of Commerce (“the ICC”), and by a selection forming part of the contractual documentation was to be seated in Singapore.
The dispute
- [10]
[10] The qualifying reference to cl 20.1 was to part of the FIDIC general claims provision. By the clause, any notice to the Engineer claiming additional payment “shall be given as soon as practicable”, “describing the event or circumstance giving rise to the claim”, and “not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance”. It provided that if notice of a claim was not given within the 28 days “the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim”. As well, it provided that the “Contractor shall keep such contemporary records, as may be necessary to substantiate any claim …”
- [13]
[13] The Defendants contested the rejection and requested reconsideration, and in April 2018 the Engineer responded maintaining its rejection. After a period of silence, in February 2020 the Defendants made a further claim with a quantified “interim” amount to the end of December 2019, which the Engineer rejected in June 2020 noting its earlier rejections but after fresh consideration coming to the same conclusion. The Engineer’s letters included that the claims had been made outside the 28 days in cl 20.1.
- [14]
[14] The Defendants took the rejection of their claims to the DAB. After hearing the parties, it decided adversely to the Defendants on the ground that the periodic revision of wages could not be considered a change in law, with reference to cl 13.8 as the provision for price escalation. A subsequent meeting in the presence of the Engineer failed to resolve the matter amicably. The Defendants then took the matter to arbitration.
The arbitration
- [15]
[15] The Defendants filed their Request for Arbitration (“the RFA”) with the ICC on 2 December 2021. In the RFA, they nominated Judge A as their party-appointed arbitrator. The Claimant nominated Judge B as its party-appointed arbitrator, and the tribunal was constituted by the joint nomination by Judge A and Judge B of Judge C as the presiding arbitrator, confirmed by the ICC Secretariat on 19 April 2022. Each of Judge A, Judge B and Judge C was a retired Indian judicial officer.
- [16]
[16] There were procedural hearings and completion of the pleadings, then the hearing of arguments spread over the period May to September 2023 and the filing of written notes of submissions at the end of October 2023. The proceedings were declared closed on 10 November 2023.
- [17]
[17] The award in the CTP-11 arbitration (“the Award”) was issued on 5 June 2024. As earlier noted, the award was by a majority, being the presiding arbitrator Judge C together with Judge A. Judge B issued a dissenting opinion dated 28 May 2024; she signed the Award, but with the note that she “has expressed her views separately in her Dissenting opinion”.
The issues in the arbitration
- [18]
[18] As recorded in the Award, the Defendants as claimants sought the relief, in summary:
(a) a declaration that the January 2017 Notification constituted a change in law “as per Clause 13.7” and that the Claimant should accordingly pay “the increase in cost arising from the same” on a monthly basis;
(b) an award of Rs 100,84,39,906 towards that increased cost due to the increase in minimum wages, calculated to 30 September 2021, together with applicable tax;
(c) a declaration that the Claimant was further liable to pay the increased cost due to the increase in minimum wages from 1 October 2021 onwards, together with applicable tax;
(d) an award of Rs 6,26,44,043 towards interest;
(e) an award of pre- and post-award interest;
(f) an award of the costs of the arbitration; and
(g) further or other relief as the tribunal felt just and appropriate.
- [19]
[19] In the Terms of Reference agreed between the parties (“the TOR”), the particular issues to be determined were:
The parties’ positions
- [22]
[22] On the issue of the cl 20.1 time bar, as well as relying on failure to claim within the 28 days, the Claimant contended that the Defendants were estopped from bringing their claim or had waived their right to do so because they had not challenged the Engineer’s decisions in 2017 and 2018 before the DAB. The Defendants contended that cl 13.7 was “self-operative” and not subject to cl 20.1; that the change in the rate of minimum wages had a “continual impact” and their “cause of action” was “continual in nature” and they were not limited to making only one claim within the 28 days; and that if cl 20.1 did act as a time bar to their claims, it was void and invalid under s 28 of the Indian Contract Act 1872 (Act No 9 of 1872) (India) (“the Indian Contract Act”).
- [23]
[23] On quantum to 30 September 2021, the Defendants did not furnish proof of actual additional expenditure, but took a notional formula using coefficients of labour from the table to cl 13.8. The Claimant did not provide its own quantification, but contended that the Defendants’ formula had no basis in the contract and had a number of errors; but more fundamentally, the Claimant said that cl 13.7 required substantiation of the claim from contemporary records (a contention which it supported by reference to statutory and contractual obligations to maintain records of payment of wages) but no such proof had been provided by the Defendants. It contended also that the Defendants had not taken account of other amendments, such as Employees Provident Fund and Employee State Insurance Contribution, which may have resulted in reduction of the impact of the change in minimum wages.
- [24]
[24] The positions for the period after 30 September 2021 followed from the preceding issues; the Defendants contended for a declaration of their future entitlement, the Claimant said that there was no entitlement.
The Award
- [26]
[26] In the Award, the Defendants were substantially successful.
- [27]
[27] The Award was described as an award “(Per Justice [C], President) (For himself and Justice [A]) – Majority view”, but as earlier indicated was signed by Judge B with a note referring to her dissenting opinion. It comprised 340 paragraphs. The first 68 paragraphs were essentially procedural, a summary of the parties’ positions, and the statement of the issues for determination. The issues were then dealt with sequentially, generally in the form of briefly setting out the claimant’s position and the respondent’s position and then explaining the tribunal’s reasoning and analysis: issue 1 in paragraphs 69 to 125; issue 2 in paragraphs 126 to 171; issues 3 and 4 together in paragraphs 172 to 230; issues 5 and 6 together in paragraphs 231 to 290; and issues 7, 8 and 9 together in paragraphs 291 to 332. The remaining paragraphs 333 to 340 were essentially dispositive in accordance with the previous paragraphs.
- [28]
[28] On the central question, the Majority held in a complex analysis that cl 13.8 had the limited purpose of compensating the Defendants when there was a variation in the VDA, an inflation-related allowance being only one component of the rate of minimum wages. The January 2017 Notification was a variation in the other component, the BRW, and the Majority held that it was a change in law for the purposes of cl 13.7. They held that the Defendants were entitled to an upwards adjustment of the contract price due to the increase in minimum wages, including accepting that the January 2017 Notification applied to the CTP-11 Contract.
- [29]
[29] The Majority held that the Defendants’ claim was not barred pursuant to cl 20.1, because its notice requirement was “directory” and not mandatory, and that even if it had been mandatory it would be void pursuant to s 28 of the Indian Contract Act. They held further that the impact of the January 2017 Notification had been continuing, so that the Defendants had “a continuing or a recurring cause of action” and they could raise successive claims for the Engineer’s determination. For that reason, the Majority also rejected the Claimant’s contentions of estoppel and waiver.
- [32]
[32] Referring to the Indian Arbitration and Conciliation Act 1996 (No 26 of 1996) (India) (“the Indian Arbitration Act”) and the Indian Interest Act (No 14 of 1978) (India) (“the Indian Interest Act”) and Indian authorities, the Majority held that the Defendants were entitled to pre-award interest at 8% compounded monthly on the Rs 80,29,92,737 from 27 March 2020. Again with reference to Indian law, the Majority awarded post-award interest on the total of the Rs 80,29,92,737 and the pre-award interest at 7.5% from two months from the date of the Award.
The prior related arbitrations
- [39]
[39] As a reminder, the arbitration in the present case was commenced on 2 December 2021 as an ICC arbitration. The hearing was over the period May 2023 to September 2023, and the closing submissions were received at the end of October 2023/early in November 2023. The Award was issued on 5 June 2024.
- [40]
[40] In all four arbitrations the claimants (and so the Defendants as claimants in the CTP-11 arbitration) were represented by essentially the same team of counsel. The Claimant as respondent in the arbitrations was represented by essentially different teams of counsel; its team in the CTP-11 arbitration was without any counsel from the prior arbitrations.
- [41]
[41] Judge C was the presiding arbitrator in all four arbitrations, and when he came to his decision together with Judge A in the Award he had given decisions in the three prior arbitrations. At the close of submissions in the CTP-11 arbitration the awards in the first two arbitrations had been issued, and the award in the CTP-13 arbitration was imminent. Judge A was a member of the tribunal in both the CTP-11 arbitration and the immediately preceding CTP-13 arbitration, and when he joined with Judge C as the Majority in the Award, he had earlier joined with him in the decision in that arbitration.
- [42]
[42] The contractors were substantially successful in all three prior related arbitrations. In the Claimant’s case in OA 20, the cut-and-paste copying was from the awards in these arbitrations, particularly from the CTP-13 Award.
- [43]
[43] It should be said that the CTP-13 Award has been set aside, on the Claimant’s application: see DJO v DJP and others [2024] SGHC(I) 24 (“DJO (HC)”). The Claimant applied on similar but not identical grounds to those in the present application, and mounted a similar but not identical case to that which it seeks to make out in OA 20. It was held that the award should be set aside because it was made in breach of the rules of natural justice. The Claimant submitted that the facts of the present case fell within the facts of DJO (HC) and that the Award bore “practically identical” concerns as the CTP-13 Award, and said that the Award should similarly be set aside.
- [44]
[44] While appropriate regard may be had to DJO (HC), the challenge to the Award must be addressed on an examination of its own merits. DJO (HC) was under appeal, the appeal having been heard in January 2025 with the decision not yet issued. Deferring my decision in these proceedings until the decision on appeal was issued, for the likely assistance then available, was raised with the parties. The Claimant was agnostic, the Defendants opposed that course, and in the circumstances I considered that I should give my decision in the ordinary course.
The Claimant’s complaints
- [46]
[46] The primary focus of the Claimant’s case was on its Ground 1, breach of the rules of natural justice, more specifically those against apparent bias in the form of prejudgment and against failure to give a fair hearing. It put forward a number of matters, which I will call its complaints, in support of Ground 1, and relied on the same or most of the same matters for the other Grounds 2, 3 and 4. It is convenient first to describe the complaints.
Copying from the awards in the prior related arbitrations
- [47]
[47] The overarching complaint, on which the further complaints built, was that the Majority had used the CTP-13 Award (which was itself copied from the CP-302 and CP-301 Awards) by copying from it as a template for its reasoning and analysis of the issues in the Award. By “template” was not meant just form, but reproduction of substance. The Claimant said that the Majority’s reasoning and analysis across all ten issues in the Award spanned 176 paragraphs, and with an extensive comparative schedule that 157 paragraphs out of the 176 had been reproduced from the CTP-13 Award, in many cases stemming from the CP-301 and CP-302 Awards also, either verbatim or with what it called minor modifications.
- [48]
[48] The parties traded numbers of paragraphs, and the Defendants produced a commentary on the schedule. The Defendants did not and could not contest that there was extensive reproduction in the Award from the CTP-13 Award, and through it from the earlier awards: some more detail of this appears in the consideration of the further complaints. The Defendants’ response was for the most part that they did not accept that the paragraph in the CTP-11 Award was common to or a reproduction of one or more of the earlier awards as the wording and/or phrasing was different, saying that at least 135 of the 157 paragraphs contained differences from the corresponding paragraphs in the prior related awards and that at least 39 of the 157 were legal propositions or the citation of texts or authorities.
- [49]
[49] It is impractical to go through the paragraphs in the awards in these reasons, nor is it necessary to resolve a precise number of paragraphs or classify the minutiae of the changes in wording and/or phrasing. It is correct that in some instances there is a change in the wording or phrasing, but the change is editorial only and emphasises rather than negates the otherwise reproduction of the paragraph from the prior related award. It is apparent that the Award was written with the CTP-13 Award, and perhaps the earlier awards, before the writer, and clear that in the Majority’s reasoning and analyses the CTP-13 Award was largely used as the basis for the Award, with some textual amendment but extensive reproduction of the substance of its paragraphs.
- [50]
[50] The complexion to be put on the reproduction is considered later in these reasons, and is informed by regard to the Claimant’s other complaints. It can be said now, however, that the use of the CTP-13 Award as the basis for the Award was at the least problematic. There was at the least the risk of the appearance and the actuality of the Majority coming to its decision in the CTP-11 arbitration without proper regard to the facts and the submissions in that arbitration.
Copying and relying on contractual provisions not found in the CTP-11 Contract
- [51]
[51] The Claimant pointed to three instances in which the Majority referred to and relied on the wrong contractual provision; the significance, it said, was not just the errors, but that they indicated that the Majority had used the CTP-13 Award as the template for the Award (in the sense indicated above) without properly applying their minds to the relevant issue.
The wrong cl 13.8
- [52]
[52] For issue 2, cl 13.8 of the CTP-11 Contract was a central provision; the Claimant relied on it as the provision applicable to the increase in the minimum rate of wages. In their decision of issue 2 the Majority held that it applied only to the VDA, and accordingly that the Defendants were entitled to an adjustment pursuant to cl 13.7. In the course of a complex analysis they set out in paragraph 150 of the Award a price adjustment formula as the formula in cl 13.8 of the CTP-11 Contract.
- [53]
[53] However, the formula set out in paragraph 150 of the Award was not the formula in cl 13.8 of the CTP-11 Contract. Paragraph 150 was a verbatim copy of paragraph 275 from the CTP-13 Award, which was a verbatim copy of a paragraph from the CP-302 Award which was a verbatim copy of a paragraph from the CP-301 Award. The formula was in fact the formula in the CP-302 Contract and the CP-301 Contract: indeed, when set out in paragraph 275 of the CTP-13 Award it was incorrect as a citation from cl 13.8 of the CTP-13 Contract, having been copied from the CP-302 Award or the CP-301 Award. (The Claimant pointed to DJO (HC) at [71] noting this as a “clear demonstration that the Tribunal were drawing upon the submissions made to, and the labours of, the Tribunal in the CP-301 Arbitration rather than focusing on the submissions made to them in [the CTP-13 Arbitration]”.) The differences in the formula were significant, in the sources from which some components of the formula were to be obtained.
The wrong adjustment data
- [56]
[56] The incorrect reference to the indices published by the Government of India, as opposed to those published by the Reserve Bank of India, was repeated in each of paragraphs 151, 153, and 159 of the Award. Those paragraphs were reproductions of paragraphs 276, 279 and 287 of the CTP-13 Award, each itself reproducing paragraphs in the earlier awards, with an immaterial change between paragraphs 279 and 153 (“it is evincible that” to “it is seen that”, typical of the editorial differences on which the Defendants relied as noted at [48] above).
The non-existent annexure
- [58]
[58] The CTP-11 Contract did not contain an Annexure 1 of the Appendix to the Tender. Paragraph 279 of the Award down to setting out the table was a reproduction of paragraphs 388–389 of the CTP-13 Award, which was correct for the CTP-13 Contract and which again had antecedents in the earlier awards. In the CTP-11 Contract, cl 13.8 provided that the relevant coefficients of labour were to be found at “Section 6, Financial Submission, Schedule 1”. It should be said, however, that while there was reference to a non-existent annexure as its source, it appears that the table then set out in paragraph 279 of the Award was of the labour coefficients found as provided in the CTP-11 Contract (the Defendants so stated, the Claimant did not say otherwise, and the CTP-11 Contract in evidence was incomplete in this respect).
- [59]
[59] In their submissions, the Defendants described these errors as “clerical or typographical”. That cannot be accepted. They were plainly not clerical or typographical errors, but came from the reproduction of the paragraphs from the earlier awards, not always cut-and-paste but substantially so and part of the extensive reproduction earlier described.
Placing weight on arguments which the parties did not raise in the arbitration but were copied from the prior related awards
- [60]
[60] The Claimant complained of four instances in which, it said, in their analysis the Majority had adopted or considered arguments which the parties had not raised, but for which their analysis was a reproduction from the prior related awards.
Purposive construction and directory not mandatory
- [62]
[62] The Claimant’s complaint ran as follows:
(a) in its submissions, the Claimant contended for the requirement being mandatory on a “bare perusal” of the contract;
(b) in their submissions, the Defendants said that “on a bare reading of the Contract” no notice to the Engineer was required, because cl 13.7 provided that the contract price “shall be adjusted” and this was “a self-operative clause”;
(c) neither party submitted that there was ambiguity calling for purposive interpretation of cl 20.1, or raised purposive interpretation; and more particularly the Defendants did not submit that on a purposive interpretation, or at all, “shall” in cl 20.1 was directory rather than mandatory;
(d) but the Majority applied the purposive rule of interpretation to the CTP-11 Contract, and on that interpretation held that “shall” in cl 20.1 was directory rather than mandatory;
(e) the paragraphs in the CTP-11 Award containing the Majority’s analysis in these respects were reproductions, with minor editorial changes, of paragraphs in the CTP-13 Award, which were in turn reproductions from the two earlier awards.
- [63]
[63] In substance, then, the Claimant’s complaint was that the Majority’s dismissal in this way of its reliance on cl 20.1 had been lifted without notice from the CTP-13 Award.
- [64]
[64] I do not think that the Defendants contested that the Majority came to the conclusion that cl 20.1 was directory rather than mandatory of their own initiative, as it were, in the Award. In their written submissions, they suggested that the Majority had sought to arrive at a commercially sensible construction so as to give effect to the intention of the parties. Their answer to the Claimant’s complaint was that an arbitral tribunal is entitled to “adopt reasonable inferences, findings of fact or lines of arguments even if these have not been specifically addressed by the parties” and “to arrive at conclusions that are different from the views adopted by parties” (referring to Song Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd [2007] 3 SLR(R) 86 (“Soh Beng Tee”) at [65(e)]), and that the construction of cl 20.1 was “very much in play” and it was not open to the Claimant to complain that the Majority relied on accepted principles of contractual interpretation to construe the clause. But this missed the Claimant’s point: not that the Majority had gone outside the parties’ submissions to reasoning of their own, but that they had done so by substantial, untelegraphed and unattributed reproduction of the Majority’s analysis on the same issue in the CTP-13 Award (with its antecedents in the earlier awards), indicative of prejudgment with a mind closed to the parties’ submissions.
Statutory limitation
- [66]
[66] The Majority went on to refer, in paragraph 115, to the rejection of the Defendants’ claim by the Engineer and the filing of the RFA as well within the period of three years being the period of limitation from the accrual of the cause of action; and in paragraphs 116 and 117 they referred to authorities for when a cause of action accrued, with the conclusion that the period of limitation would start running from when the final bill under the contract ought to have been paid. Paragraphs 116 and 117 were reproductions of the corresponding paragraphs in the CTP-13 Award.
- [67]
[67] However, the Claimant said, it had not in the arbitration raised an argument of a statutory limitation period of three years. Its case was founded on the contractual limitation of 28 days in cl 20.1 of the CTP-11 Contract, and issue 1 was framed accordingly – whether the Defendants’ claim was “barred under limitation as provided under Clause 20.1 …”. The apparent explanation for the Majority’s extraneous attribution to it and rejection of a defence of statutory limitation, the Claimant said, was that they were copying from the CTP-13 Award, where statutory limitation was argued because in that arbitration the claimants did not raise a claim to the Engineer until three years after the January 2017 Notification.
- [68]
[68] The Defendants submitted that the Claimant had in fact raised statutory limitation in the arbitration, referring to a plea in its Defence that the Defendants’ claims were “barred by limitation” and not maintainable “in law”. They said also that they had raised statutory limitation, referring to their Statement of Rejoinder in which they had said that the Claimant had “failed to point out any provision of the limitation act [sic] under which it contends that the claim is barred by limitation”, and to their Opening Submissions in which they had attributed to the Claimant a contention that their claim was “barred by the law of limitation under Article 137 of the Limitation Act, 1963” because the arbitration had been commenced more than three years after 19 January 2017.
- [69]
[69] The words in the Claimant’s pleading must be taken together with the framing of issue 1, and the Defendants did not point to any other pleading or any submission to the tribunal by the Claimant, or by themselves, raising statutory limitation or showing it as a live question. However, while the Majority’s paragraph 113 bears a relationship with the corresponding paragraph 127 in the CTP-13 Award, it is not a reproduction or even a reproduction with textual changes, and from the Claimant’s table paragraph 115 does not have a corresponding paragraph in the CTP-13 Award. This suggests that, although it was an incorrect attribution, the Majority took up the Defendants’ attribution to the Claimant of limitation because of the three years between the January 2017 Notification and the commencement of the arbitration. I do not think that this can be confidently excluded.
- [70]
[70] To its full extent, therefore, I do not think that the Claimant’s complaint can be accepted, although as earlier stated paragraphs 116 and 117 in the Award were reproductions of the corresponding paragraphs in the CTP-13 Award. What remains is that, if the Majority thought that issue 1 included statutory limitation as well as the limitation of 28 days, it seems that they came to their decision on that matter without either party having provided submissions for or against, influenced by and in part copying from the CTP-13 Award.
Calculation of quantum
- [71]
[71] As earlier described (see at [30]), the Majority did not adopt the Defendants’ calculation leading to Rs 92,31,18,812, but made their own calculation of an adjustment based on a 40% increase in the minimum wages to arrive at an amount of Rs 80,29,92,737. Neither party had made submissions for or against that way of calculating the adjustment. The Majority was evidently conscious of this, saying with citation of authority at paragraph 273 of the Award:
- [72]
[72] The Claimant’s complaint, however, was not just that the Majority had made the calculation according to its own formula, without reference to the parties. It was that the formula was copied from the CTP-13 Award (as was paragraph 273 of the Award, although with varied citation of authority). On a comparison of the analyses explaining the calculations, while necessarily with different inputs and results the paragraphs containing the analysis in the Award are in similar and sometimes identical terms to those in the CTP-13 Award, such that the description of copying is well warranted.
- [73]
[73] The Claimant added to its complaint that, because of what it called “mechanical replication”, the Majority had “ignored crucial arguments and points which [it] had raised during the Arbitration to refute [the Defendants’] quantification of its claims”. Since the Majority had not adopted the Defendants’ calculation, so far as it was meant that the Majority had not paid regard to the Claimant’s arguments and points in making its own calculation, this is subsumed within the complaint of copying from the CTP-13 Award; that is, the “mechanical replication” instead of regard to the parties’ arguments.
Cut-and-paste reliance on authorities not raised or the subject of submissions in the arbitration
- [75]
[75] Referring to a table of the authorities and the paragraphs in the Award in which they were cited, in its written submissions the Claimant said that almost 50 authorities (texts and judicial decisions) cited by the Majority in their analyses had not been raised or relied on by either party, but had been reproduced from the CTP-13 Award and in most cases reproduced in that award from the earlier awards. The authorities were cited, it said:
(a) in support of applying the purposive rule of construction;
(b) in support of construing cl 20.1 as directory;
(c) in characterising the Defendants’ claim as a continuing cause of action;
(d) in holding that the Defendants’ claim for its increased labour cost did not fall within cl 13.8;
(e) in holding that the January 2017 Notification was a change in law; and
(f) in holding that the January 2017 Notification applied to the CTP-11 Contract.
- [76]
[76] The table was not constructed in accordance with these topics, but according to the issues stated in the TOR: twenty authorities for issue 1; eight authorities for issue 2; ten authorities for issues 3 and 4; seven authorities for issues 7, 8 and 9; and four authorities for issue 10. However broken down, there was extensive citation of authorities on important questions in the arbitration, and the Claimant’s complaint was again not just that the authorities had been cited by the Majority although not raised or relied on by either party (and it said that it had therefore not had the opportunity to address the tribunal on the authorities): the greater complaint was that they had been cited by wholesale reproduction from the awards in the earlier related arbitrations.
- [77]
[77] The Defendants did not seriously contest this reproduction of authorities not raised by the parties, which in their written submissions they called “the Alleged Extraneous Authorities”. They said that some of the authorities were for legal propositions found in, or consistent with, authorities which had been raised by the parties, and that others were “largely repetitive of trite propositions of law and did not add any novel legal reasoning”. In a table of their own they categorised the authorities in the Claimant’s table in one or other of these ways. They said that the Majority’s decision was supported by the other authorities cited (although they may have limited this to the liability issues), and would have remained the same even if the citation of the alleged extraneous authorities had been excluded. It must be said, again, that this missed the point of the Claimant’s complaint – it was the reproduction, indicative of prejudgment.
Copying the decisions on interest and costs
- [78]
[78] In the RFA the Defendants had claimed interest at 8% compounding monthly pursuant to cl 14.8 of the CTP-11 Contract, which provided that failure in payment gave an entitlement to receive financing charges, compounded monthly on the amount unpaid during the period of delay, at a rate three percentage points above the discount rate of the central bank in the country of the currency of payment.
- [79]
[79] The Majority awarded the pre-award interest on Rs 80,29,92,737 at 8% compounded monthly on the basis that s 31(7)(a) of the Indian Arbitration Act provided that “[u]nless otherwise agreed by the parties” the arbitral tribunal was empowered to award pre-award interest; that cl 14.8 of the CTP-11 Contract was an “otherwise agreement”; and, referring to Indian authorities, that the settled position was that the agreement was decisive, the tribunal was bound by it, and interest had to be awarded in accordance with that agreement. The relevant paragraphs of the Award, paragraphs 296 to 304, were a reproduction of the corresponding paragraphs in the CTP-13 Award, with immaterial changes in some words in three of the paragraphs and the different amount and commencing date in the final paragraph. The paragraphs in the CTP-13 Award were similarly all but identical with the corresponding paragraphs in the CP-301 and CP-302 Awards.
- [80]
[80] The application of s 31(7)(a) of the Indian Arbitration Act was incorrect. The arbitration was seated in Singapore, and Singapore law governed the award of pre-award interest: it should not have been decided by application of Indian law. The reproduced analysis from the earlier awards had correctly applied Indian law in the cases of the CP-301 and CP-302 Awards, where the arbitrations were seated in India, although it had been incorrect in the case of the CTP-13 Award, which was also seated in Singapore – a matter noted and part of the reasoning to setting aside the CTP-13 Award in DJO (HC) (see at [87] below).
- [81]
[81] The Defendants did not dispute that the application of Indian law was incorrect. They said that the Majority was clearly alive to the fact that the seat of the arbitration was Singapore, as shown by their citation at paragraph 9 of the Award of cl 20.6 of the CTP-11 Contract as governing the arbitration and their noting at paragraph 12 of the Award of Singapore as the seat. They said that the Claimant had had the opportunity to make submissions on the applicable law, but had submitted only that no interest should be awarded because the Defendants’ claim should be dismissed, and that the error was at best one of law, which was not a ground for setting aside the Award. (It should be said that here and elsewhere the Defendants also made submissions as to the absence of prejudice to the Claimant; I will come to that later in these reasons, see at [124] –[133] below.)
- [82]
[82] The Defendants’ response again missed the point of the Claimant’s complaint in relation to breach of the rules of natural justice. The Claimant’s submission was that the wholesale erroneous reproduction of the paragraphs from the prior awards showed that the Majority had not given independent consideration to the position in the arbitration, but had come to their decision on interest (as in the Claimant’s submission they had generally) with prejudgment from the decision in the earlier arbitrations; that point, it could be said, was underlined by the disconnect between the early recognition that the arbitration was seated in Singapore and the failure to give effect to that recognition when addressing the award of interest. While the tribunal was not assisted by submissions on the applicable law, it was a necessary question and the application of the law of the seat is well established: the Claimant’s point was well made.
- [83]
[83] Going to post-award interest, the position is much the same and can be dealt with more concisely. The Majority’s analysis was in paragraphs 305 to 310 of the Award. Applying s 31(7)(b) of the Indian Arbitration Act and citing two Indian authorities, they held that under s 31(7)(b) the post-award interest was on the sum awarded, which included the pre-award interest, and they applied s 2 of the Indian Interest Act in arriving at the interest rate of 7.5%. This was incorrect. The paragraphs in which the Majority expressed this decision on post-award interest were in precisely the same words as the corresponding paragraphs in the CTP-13 Award, which but for a few words of no materiality were in the same words as the corresponding paragraphs in the CP-301 Award and the CP-302 Award. The point of the Claimant’s complaint and the Defendants’ response were as above.
Failure to deal with arguments raised in the arbitration
- [89]
[89] The tribunal did not have to engage with every argument put to it: it was obliged to deal with all essential issues, but if its decisions made other arguments irrelevant or of little significance it did not have to deal with them: SEF Construction Pte Ltd v Skoy Connected Pte Ltd [2010] 1 SLR 733 at [58]–[60]. For some of the arguments this appears to have been the case, and the complaint was not so much that the arguments had not been dealt with, but that the decisions which made them irrelevant or of little significance had been come to in breach of the rules of natural justice as found from the preceding complaints. The complaint really depends on otherwise being satisfied of the breach of the rules of natural justice, and it is preferable not to go into the arguments and their possible significance to the decisions as that would move into review of the merits of the decisions. As will appear, in the view I take it is not necessary to do so or to include this complaint when considering the Claimant’s grounds.
No opportunity for submissions
- [90]
[90] As a more general complaint, the Claimant said that because of the reproduction from the earlier awards it had not had the opportunity to make submissions on the reasoning and authorities in the Majority’s analyses. This went more particularly to failure to give a fair hearing, to which I will come (see at [134]–[140] below).
Ground 1: breach of the rules of natural justice
- [91]
[91] Section 24(b) of the IAA provides that an award may be set aside if “a breach of the rules of natural justice occurred in connection with the making of the award by which the rights of any party have been prejudiced”.
Arbitrations and the rules of natural justice
- [92]
[92] The principle of minimal curial intervention in arbitral proceedings is well established. It is founded on encouragement of finality in arbitrations and the acceptance of the parties, when they go to arbitration, of the limited recourse to the courts under (in a case such as this) the IAA and the Model Law: see for example Soh Beng Tee at [65(c)]. But that makes the avenues of recourse all the more important to achieving justice. As is said in CJA v CIZ [2022] 2 SLR 557 at [1], “parties to an arbitration do not have the right to a ‘correct’ decision from an arbitral tribunal … , but only the right to a decision that is within the ambit of their agreement to arbitrate, and that is arrived at following a fair process”. The due process rights must therefore be stringently upheld. On the other hand, care must be taken lest due process complaints be used improperly to challenge awards when the matter complained of is within the tribunal’s discretion or otherwise a course open to it. The threshold for finding a breach of natural justice is a high one, and it is only in exceptional cases that a court will find that threshold crossed: Soh Beng Tee at [54]; China Machine New Energy Corp v Jaguar Energy Guatemala LLC and another [2020] 1 SLR 695 (“China Machine”) at [87].
- [93]
[93] In Soh Beng Tee at [43] the Court of Appeal said that Marks J in Gas & Fuel Corporation of Victoria v Wood Hall Ltd & Leonard Pipeline Contractors Ltd [1978] VR 385 at 396 had “helpfully distilled the essence of the two pillars of natural justice” in the terms:
- [94]
[94] A party challenging an award as having contravened the rules of natural justice must establish (a) which rule of natural justice was breached; (b) how it was breached; (c) in what way the breach was connected to the making of the award; and (d) how the breach prejudiced its rights: Soh Beng Tee at [29]; L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal [2013] 1 SLR 125 (“L W Infrastructure”) at [48].
- [95]
[95] As earlier noted, here the two sub-rules of natural justice on which the Claimant relied were apparent bias in the form of prejudgment and failure to give a fair hearing.
Breach by apparent bias
- [96]
[96] There may be breach of the rules of natural justice not only where the arbitrator is actually biased, but also (as is inherent in the well-known statement from The King v Sussex Justices, ex p McCarthy [1924] 1 KB 256, at [93] above) where there is apparent bias. That is governed by the “reasonable suspicion” test: whether there are circumstances that would give rise to a reasonable suspicion or apprehension of bias in the fair-minded and informed observer (who I will hereafter refer to simply as “the observer”).
- [97]
[97] In BOI v BOJ [2018] 2 SLR 1156 (“BOI”) at [103] the amplification of this included:
- [98]
[98] Particularly material to the Claimant’s complaints, prejudgment can be a form of apparent bias: see BOI at [108] where a number of cases are cited where prejudgment has been said to amount to apparent bias or to be a form of apprehended bias. After citing the cases, the court continued, at [109]:
- [99]
[99] At the heart of prejudgment as a form of apparent bias is the observer’s reasonable suspicion that the decision-maker has approached “the matter at hand”, that is, the issue or issues before him or her for decision, with a closed mind. Too much weight cannot be given to the words that the decision-maker has reached a final and conclusive decision before being made aware of all relevant evidence and arguments; those words may come from a decision being given at the close of evidence and argument, but where the decision is reserved, the critical time is when the decision-maker comes to his or her decision as found in the later rendered judgment or award. In the Defendants’ written submissions the question was reframed in terms of reaching a final and conclusive decision on the issues before considering the evidence and arguments put before him or her, another way of expressing coming to the decision of the issues with a closed mind and one which may be thought more helpful.
There was breach by prejudgment amounting to apparent bias
- [100]
[100] I go first to the copying from the awards in the prior related arbitrations, the subject of the Claimant’s overarching complaint. A number of cases, although on different facts and in different contexts, illustrate that reproduction can be seen and has been seen as showing failure of the decision-maker to apply his or her mind to the evidence and arguments before him or her, and that this can amount to apparent bias.
- [101]
[101] Yap Ah Lai v Public Prosecutor [2014] 3 SLR 180 (“Yap Ah Lai”) was a sentencing appeal. Sundaresh Menon CJ held that he was entitled to consider the sentencing anew because the District Judge had “erred in failing to fully appreciate the material that was before him in each case” (at [73]). “Each case” was the case that was the subject of the appeal and another case decided by the District Judge, and the error was found in the District Judge’s reproduction of the same crucial passages of reasoning in the two cases. The Chief Justice said of this (at [69]–[70]):
- [102]
[102] Lim Chee Huat v Public Prosecutor [2019] 5 SLR 433 (“Lim Chee Huat”) was also a sentencing appeal. The District Judge had reproduced 27 of the 43 paragraphs in the grounds of decision from the Prosecution’s submissions, with some rearrangement and paraphrasing but even including a typographical error. Aidan Xu J said (at [49]) that the practice of copying to adopt submissions as the court’s reasoning should not be undertaken, because it raised the concerns that the judge is biased or at least appears to be biased in favour of the party whose submissions are adopted, and because it creates substantial doubt about the judge’s independent exercise of judgment and discernment. He said (at [52]):
- [103]
[103] Newton, David Christopher v Public Prosecutor [2024] 3 SLR 1370 (“Newton”) was also a case of reproduction of the Prosecution’s submissions. In addition to Yap Ah Lai and Lim Chee Huat, Sundaresh Menon CJ referred at [37] to a Canadian case (Cojocaru v British Columbia Women’s Hospital and Health Centre [2013] 2 SCR 357), at [38] to a Hong Kong case (Nina Kung v Wong Din Shin (2005) 8 HKCFAR 387) and at [39] to an English case (IG Markets Ltd v Declan Crinion [2013] EWCA Civ 587) for criticisms of judicial copying from one side’s submissions. The criticisms were respectively, as conveying the impression that the reasons for judgment do not reflect the judge’s thinking but that of someone else; as raising serious questions as to whether the judge has abdicated his judicial function or at least as to whether justice has been seen to be done by an independent judicial tribunal; and as risking creating the impression that the judge had abdicated his core judicial responsibility to think through for himself and had not performed his task of considering both parties’ cases, independently and even-handedly. The Chief Justice said (at [40(a)] and [40(b)]) that reproduction of substantial portions of the submissions of one side “opens [the court] to the charge that it has failed to apply a judicious mind and has simply, and without sufficient consideration and discernment, adopted the submissions of one party”, and that this in turn “opens the court to a complaint of actual and/or apparent bias”. However, his Honour declined to set aside the District Judge’s decision on the ground of apparent bias: while being critical of what had occurred, on the facts as a whole he considered that the observer would not conclude that the District Judge “had a closed mind and was not open to being persuaded otherwise” (at [47(b)]).
- [104]
[104] In Ler Chun Poh v Public Prosecutor [2024] 6 SLR 410 there was again substantial reproduction of the Prosecution’s submissions in the District Judge’s decision, and despite some paraphrasing and reorganisation it was found on consideration of the circumstances as a whole that the District Judge had failed to apply his mind to the material before him in coming to his decision. The reasons of Aidan Xu J included (at [13] and [15]), after reference to [49] of Lim Chee Huat (at [12]):
- [105]
[105] In that case, however, while finding that the District Judge had failed to apply his mind to the matter, Aidan Xu J considered that apparent bias had not been made out, because the summary of the appellant’s version of events showed that he did not shut his mind to the appellant’s testimony and the notes of evidence showed that he “gave leeway to the appellant in his questioning of the victim and the prosecution’s witnesses” (at [57]).
- [106]
[106] In short, reproduction can amount to apparent bias if on the reasonable suspicion test the decision-maker appears to the observer to have had (or can amount to actual bias because the court finds that the decision-maker had) a closed mind, a mind which was closed to a decision on the evidence and arguments before him or her: in that manner, prejudgment.
- [107]
[107] In the present case the reproduction was extensive and covered the Majority’s reasoning in their analyses across all issues in the Award. From examination of the comparative schedule and commentary , I am satisfied that the limited textual amendments are no more than that, changes in wording or phrasing without any change in the reasoning or any substantive change in the expression of the reasoning. Having regard to all the circumstances including the Claimant’s other complaints, and notwithstanding the Defendants’ submissions to the contrary to which I will come, I have no doubt that the observer would have a reasonable suspicion of bias in the form of prejudgment through the Majority coming to their decision with a closed mind, a mind which imported and imposed the reasoning and decision in the CTP-13 Award (often also in the earlier awards) rather than came to a decision on the evidence and arguments before them.
- [109]
[109] As indicated, in coming to this view I have considered but not found persuasive the submissions against it made by the Defendants. The submissions were, with respect, occasionally Delphic, and I have sought to encapsulate their substance.
- [110]
[110] In a preliminary submission going also to failure to give a fair hearing, the Defendants reminded from China Machine that the threshold for finding a breach of natural justice is a high one and that it is only in exceptional cases that a court will find that threshold crossed. They referred to warnings to the effect that the court should not be over-critical of an award or its expression, including that the court should not “assiduously comb an arbitral award microscopically in attempting to determine if there was any blame or fault in the arbitral process” (Soh Beng Tee at [65(f)]), and cautioning against a challenge based on alleged breach of the rules of natural justice being a disguised appeal on the merits of the award. I have borne these matters well in mind. I find that the threshold is crossed, without being overly critical of the Award, and the breach of the rules of natural justice in the form of prejudgment does not go to the merits but to the following of a fair process: it matters not whether the Majority was right or wrong, there was breach in the coming to their decisions.
- [111]
[111] What appeared to be the principal submission went to the circumstances in the knowledge of the observer. In the Defendants’ oral submissions it was said that “context is everything”. As I understand it the suggested context, as matters in the knowledge of the observer, was to the effect:
(a) The Claimant knew that Judge C had been the presiding arbitrator in the three earlier arbitrations, and that Judge A had been a member of the tribunal in the CTP-13 arbitration, but did not object to their appointments.
The judgment continues past this page. Read the rest at eLitigation.