PS 23 Interior Pte. Ltd. v Andrew Tan Tong Sin

Feedback & support

[2026] SGMC 71Case no. [2026] SGMC 71

What happened, in plain English

There is no plain-English summary of this judgment yet.

Ask about this judgment

Laws this judgment relies on

Grounds of decision

Official text from eLitigation

  1. A Introduction.

  2. [1] The Claimant, PS23 Interior Pte. Ltd., a company in the renovation and interior design business, sues the Defendant, Andrew Tan Tong Sin, its client at the material time, on the basis of unpaid invoices issued pursuant to a renovation contract. The contract in question takes the form of a quotation for design and renovation works dated 23 September 2021 (the “Quotation”), which was subsequently varied at least three times. These design and renovation works (the “Works”) were to be carried out at the Defendant’s landed property located at Old Upper Thomson Road, Singapore (the “Property”).

  3. [2] It is not disputed that the terms of parties’ agreement are captured in the Quotation. What is disputed, as I will discuss later on in this judgment, pertains to which document accurately captures the terms of the subsequent variations. In short, there are two versions of the said document containing the details of these variation orders, with material differences between the two. In this judgment, I will collectively refer to the Quotation and the three variation orders as the “Contract”. This definition will encompass the terms of the variation orders which I find parties to have agreed to later in this judgment.

  4. B Summary of parties’ cases.

  5. [3] The Claimant’s case is that the Defendant failed to make payment of a sum of $31,604.13 for the works done under the Contract. The Defendant was billed for these works via two Invoices, Invoice 22003 and Invoice 23004 (the “Two Invoices”), which the Claimant says have not been paid to date.

  6. C Issues.

  7. [5] Four key issues arise for my determination:

  8. (a) First, as a preliminary question, who did the Defendant contract with to renovate the Property? (“Issue 1”)

  9. (b) Second, which version of the variation orders accurately captures the terms of parties’ Contract? (“Issue 2”)

  10. (c) Third, does the Defendant owe the Claimant a total sum of $31,604.13 based on the Two Invoices? (“Issue 3”)

  11. (d) Fourth, did the Claimant breach the Contract by failing to complete its works and/or causing or creating the Alleged Defects? (“Issue 4”)

  12. [6] I proceed to deal with these issues in the order stated above.

  13. D Issue 1: Who did the Defendant contract with to renovate the Property?

  14. [8] There is some allusion in the Defendant’s Affidavit of Evidence-in-Chief (“DAEIC”) as to whether the Claimant was the proper contracting counterparty. According to the Defendant, the company he contacted to renovate his Property was not the Claimant but Oak3 Design and Build Pte Ltd (“Oak3”). For unknown reasons, it was the Claimant and not Oak3 that ended up issuing the Quotation to the Defendant. It was also the Claimant and not Oak3 that issued the Two Invoices to the Defendant. The Defendant then rounded all this off by stating that “Jackie was my interior designer whether she was representing Oak3 or [the Claimant]”. Implicit in this statement is an assertion that Ms Jackie Ong Chiew Yen (“Ms Ong”) ought to have been the proper contracting party instead of the Claimant.

  15. [9] Arising from all this is the suggestion there might be three potential candidates in respect of the party who actually contracted with the Defendant to perform the Works to the Property: the Claimant, Oak3, or Ms Ong. Despite this, the parties (including the Defendant) did not spend any time on this question at trial. They seemed to be content to assume that the Claimant was the correct plaintiff in this case. The Defendant also did not raise any argument to the opposite effect in his closing submissions.

  16. [10] In light of the above, and despite the somewhat unsatisfactory lack of address on this issue from either side, I take it that parties do not dispute that the Claimant was the entity who provided the design and renovation services to the Defendant under the Contract and is therefore the correct party in law to bring the claim.

  17. [11] I therefore proceed to consider the merits of the claim and counterclaim.

  18. E Issue 2: Which version of the variation orders accurately captures the terms of parties’ Contract?

  19. [12] A potential discrepancy regarding the number of variation orders issued by the Claimant to the Defendant must first be reconciled. In Invoice 22003, a particular line refers to the “contract plus 4 VO, 1 ommison (sic)”. It is not disputed that the acronym “VO” stands for variation order, and was in fact used by parties to refer to “variation orders” at the trial. However, the details and balances payable under the Contract for only three VOs were listed following that line, not four. I do not know why this is the case, and the Claimant gave no explanation for this apparent contradiction. Hence, despite that line, I will take the variation works that Invoice 22003 is referring to as only encompassing the three VOs which are explicitly listed, being VO1, VO2, and VO3. What I am therefore concerned about in this judgment are these three VOs only.

  20. [13] To set the scene, I briefly summarise parties’ cases in respect of the variation works under these three VOs before moving on to the material discrepancies in the documents alluded to at [2] above.

  21. (a) The Claimant argues that it had completed all the works under each VO by February 2023.

  22. (b) The Defendant disputes several aspects relating to the variation works for which the three VOs were issued. First, he denies the Claimant’s assertion that all variation works had been completed. Here, he raises the Alleged Defects on which his counterclaim rests. Second, the Defendant highlights that the version of the document titled “VO2” which he received from the Claimant is different from the version of “VO2” which the Claimant tendered at trial. Based on [36] to [45] of the DAEIC, the Defendant’s case is that the version he received ought to be followed, in terms of the work allegedly done and the cost of the same.

  23. [14] Having examined both sets of documents, it is clear to me that the versions of the “VO2” document tendered by both parties are different in several material respects. I set out some of these differences out below:

  24. Claimant’s version tendered at trial

  25. Defendant’s version received from Claimant

  26. Sub-total (G7) for Omission 1

  27. $28,295

  28. $33,385

  29. Sub-total for Omission 2

  30. $13,680

  31. $21,910

  32. Omissions (total)

  33. $41,975

  34. $55,295

  35. [16] What is also concerning is the fact that the first time the Defendant had sight of the Claimant’s version of the document titled “VO2” was at the point Ms Ong’s AEIC was served on the Defendant. In his closing submissions (the “CS”), counsel for the Claimant did not dispute the existence of these inconsistences between the two versions of the “VO2” document, and also did not dispute the fact that the first time the Defendant would have been aware of these discrepancies was only after pleadings had closed, at the point AEICs were exchanged. Despite all this, counsel for the Claimant sought to persuade me not to consider these discrepancies on the basis that they had not been pleaded by the Defendant.

  36. [17] I have little difficulty in rejecting this argument. Whilst I agree that the technically correct thing for the Defendant to have done was to apply to amend his pleadings after reviewing the Claimant’s version of the “VO2” document, the more important issue is that the Claimant, being the creator of both versions of the “VO2” document and presumably being aware of that fact that it intended to adduce and rely on a different version of this document from the one it had sent to the Defendant, failed to explain why there were two versions of the said document, why it did not send its version of the “VO2” document to the Defendant, or why its version ought to be relied on. Equally worrying is Ms Ong’s testimony that her “omission and VO is a bit not right (sic)”, which I take to be her concession that the omissions and VOs – be it the Claimant’s version or the Defendant’s version of the “VO” document – are not correct. All these are important factors in my consideration of which copy of the “VO2” document accurately captures parties’ agreement as to the scope of the variation works to be carried out.

  37. [18] Going back to the point on pleadings, the case cited by the Claimant in support of its argument – How Weng Fun and ors v Sengkang Town Council and other appeals [2023] SGCA 21 (“How Weng Fun”) – in fact also stands for the proposition that the Court can allow an unpleaded point to be raised and determined where it would be clearly unjust for the Court not to do so (at [20]). This is precisely the result here if I do not consider this unpleaded point on the discrepancies between the two “VO2” documents. Doing so would severely limit my ability to decide on which version of the “VO2” document ought to be followed. This decision has critical consequences for my decision on the claim because Invoice 22003 bills the Defendant for the works done under these three VOs and gives credit to the Defendant for two sets of works that were not done (i.e., referred to as “Omission 1” and “Omission 2”). All this would affect the quantum of the Claimant’s award if the claim were allowed. The justice of the case, and the pursuit of the truth as to what parties’ agreement in relation to the variation works was, demand that the inconsistencies between both sets of the “VO2” document be examined. Finally, the Claimant cannot claim prejudice as a result of my decision on this matter because it was given a fair chance to explain these discrepancies and answer to which variation works the Claimant did or did not carry out in cross-examination. Counsel for the Claimant also dealt with these discrepancies in closing submissions.

  38. [19] I therefore proceed to consider which version of the “VO2” document accurately captures the nature and scope of the variation works which had been agreed on by parties. To avoid confusion, I will refer to the version of the “VO2” document adduced by the Claimant in the CBOD as the “CVO” and the version adduced by the Defendant in his AEIC as the “DVO”. I will refer to the terms of the second variation order contained within each document as “VO2”. In undertaking this analysis, I start by considering the three VOs to see whether these items of work have been agreed on by parties and, if so agreed, whether these agreed items of work had in fact been completed by the Claimant. I will then proceed to consider Omissions 1 and 2 to see if they correctly reflect the works that were removed from the scope of the Contract and which the Claimant did not eventually carry out.

  39. (a) The Claimant is entitled to payment of $13,609.73 for the works done in respect of VO3.

  40. [20] I start by considering VO3 rather than VO1, as VO3 is, practically and evidentially speaking, the neatest of the three VOs to deal with. The items allegedly agreed on by parties in respect of the third set of variation works are identical across the CVO and DVO, save for one item pertaining to the construction of a washing machine kerb at $200. This item was only reflected in the CVO and not the DVO. Hence, in respect of VO3, the following works are what the Claimant asserts were agreed on under the third variation of the Contract:

  41. s/no.

  42. Works

  43. Cost

  44. 1

  45. TABLE TOP BILL direct :FROM HUA KIAN

  46. $9,434.73

  47. 2

  48. Unchoke x2 during reno

  49. $700

  50. 3

  51. Repair timber

  52. $350

  53. 4

  54. Connect/run water dispenser pipes

  55. $400

  56. 5

  57. Run Dish washer point

  58. $250

  59. 6

  60. Alter/Pvc pipes @ dry kitchen

  61. $850

  62. 7

  63. Additional Ceiling work see attachment

  64. $1,625

  65. 8

  66. Construct Washing machine kerb

  67. (only appears in CVO)

  68. $200

  69. Total:

  70. $13,809.73

  71. [21] To be entitled to payment of $13,809.73, the Claimant must prove that parties had agreed for the eight above-stated work items to be carried out and that it had in fact completed the works required by these eight items.

  72. [22] The evidence adduced by parties in this respect was far from helpful.

  73. (a) The Claimant did not adduce any objective proof of it completing these variation works. If any of the photographs or messages appended to the Claimant’s Affidavit-of-Evidence-in-Chief (“CAEIC”) do in fact depict these completed variation works, counsel for the Claimant did not draw the link between those pieces of evidence and these works. I am also unable to discern which items listed in [11] of Ms Ong’s AEIC, which asserts all the variation works that the Claimant had carried out, pertain to the items in VO3.

  74. (b) On the other hand, the Defendant, despite highlighting the conflicting documentary record pertaining to VO3 and despite seeking to rely on the smaller figure of $13,609.73 as being value of the works done under VO3 , did not put to Ms Ong his disagreement with any of the terms of VO3 or that the Claimant had failed to carry out any of these eight items of work.

  75. [23] I am therefore constrained by this state of affairs in making my decision on VO3. My findings in this respect are as follows:

  76. (a) The legal and evidential burdens of proof ultimately rests on the party bringing the claim (see Section 103 of the Evidence Act 1893 (“EA”)). In other words, the Claimant must adduce sufficient evidence to prove the agreed terms under VO3 and that the works required by VO3 to be carried out had in fact been carried out.

  77. (b) Given that the Defendant was content to use the figure of $13,609.73 to calculate the value of the works under VO3, he is arguably conceding two things: first, that he had agreed to seven out of eight terms under VO3 (excluding the term pertaining to the washing machine kerb); and second, that the Claimant had, at the very least, completed all the works required by these seven agreed terms amounting to a total value of $13,609.73. Accordingly, I find that parties had agreed for the Claimant to carry out the seven additional items of work listed at s/n 1 to 7 of the table at [20] above. I further find that the Claimant had duly completed these seven items of work.

  78. (c) In his pleadings, the Defendant explicitly disputes that the Claimant had completed all variation works. (The last sentence of [1] of the CS is therefore incorrect insofar as this is concerned.) In [37] of his AEIC, the Defendant implicitly disputes, at the very least, that the Claimant had constructed the washing machine kerb. In light of this, and given that the Claimant wishes this Court to believe that it had completed all works required by VO3, the burden of proving that parties had agreed for this kerb to be constructed and that the Claimant had in fact constructed it falls on the Claimant (see s 105 EA). The Claimant adduced no such evidence in this regard. In fact, Invoice 22003, which was issued by the Claimant, contradicts the Claimant’s own version of VO3; that Invoice reflects the total value of VO3 as $13,609.73 and not $13,809.73. Accordingly, I find that the term at s/n 8 of VO3 is not proved. I further find that the Claimant has failed to prove that it had in fact constructed the washing machine kerb ostensibly as required by VO3.

  79. [24] Accordingly, the Claimant is entitled to be paid $13,609.73 for the works it had carried out pursuant to VO3.

  80. (b) The Claimant is entitled to payment of $37,360 for the works done in respect of VO2.

  81. [25] I move on to consider the work to be done pursuant to VO2. Ascertaining the terms of VO2 was particularly confusing. On the face of the CVO and the DVO, the works under the headers “Additional 1” and “Additional 2” might have been loose references to VO1 and VO2 respectively. However, a closer scrutiny of the extrinsic documents reveals that this cannot be the case. Invoice 22003 refers to the value of VO2 as being $37,360. This is the sum total of the works under “Additional 1” and “Additional 2” in the CVO and the DVO. The Defendant in his AEIC also referred to the value of VO2 as being $37,360. Invoice 22003 refers to the value of the works under VO1 as being $9,158. The Defendant appears to accept this. Critically, there is, as mentioned earlier (see [15] above), no document titled “VO1” and no document reflecting the total sum of $9,158 adduced into evidence.

  82. [26] From the above, I deduce that parties’ positions are aligned in respect of where the terms of VO2 may be found; i.e., under the headers “Additional 1” and “Additional 2” in the CVO and the DVO. The consequential conclusion must then be that the terms of VO1 are not before me.

  83. [27] The terms of VO2 as disclosed by the CVO and DVO are identical. For ease of reference, I set them out in the two tables below:

  84. ADDITIONAL 1

  85. s/no.

  86. Works

  87. Cost

  88. 2. Wet works

  89. a

  90. Kitchen door way & window

  91. 650

  92. b

  93. Living Area window area

  94. 2,250

  95. c

  96. Living Area area

  97. 2,200

  98. d

  99. Bathroom Window

  100. 1,200

  101. e

  102. Living Area

  103. 1,600

  104. f

  105. To alternate and construct new entrance steps

  106. 850

  107. g

  108. Outdoor Yard

  109. Outdoor Dining Area

  110. • To supply labour to hack the after hacked floor

  111. • To supply labour & material to lay tiles c/w skirtings Carpoarch area

  112. • To supply labour manhole x2

  113. 1,200

  114. 1,500

  115. 600

  116. h

  117. Carporch

  118. 1,260

  119. i

  120. [3] Bedroom

  121. 600

  122. j

  123. Master Room

  124. 450

  125. k

  126. Wet Kitchen

  127. 2,400

  128. 3. Rental Scaffolding

  129. Exceeded by 1mth

  130. 1,000

  131. 4. Paint Works

  132. To supply labour & material to plaster smooth the affected area after hack 2,000.00 $ & bedroom walls/ outdoor/dining area

  133. 2,000

  134. To supply labour & material to spray partial rock stone

  135. 1,600

  136. Total:

  137. $21,360

  138. ADDITIONAL 2

  139. s/no.

  140. Works

  141. Cost

  142. Living Area

  143. 1

  144. Tv Console Length:4ft approx.

  145. 880

  146. 2

  147. Stripes wood c/w both side laminated backing divider

  148. 3,600

  149. 3

  150. Platform for staircase c/w partial laminate

  151. 1,200

  152. Kitchen Area

  153. 4

  154. To supply and install kitchen island

  155. Length;5ft approx

  156. 2,250

  157. 5

  158. To supply and install quartz top depth 800mm

  159. Length;5ft approx

  160. 1,750

  161. Master Room

  162. 6

  163. Tv console

  164. Length;6ft approx

  165. 1,320

  166. 7

  167. Side table no 2

  168. Length;4ft approx x2 (8ft )

  169. 2,000

  170. 8

  171. Wardrobe

  172. Length;6ft approx

  173. 3,000

  174. Total:

  175. $16,000

  176. [28] The total value of the works in VO2 is indeed $37,360, which the Defendant does not dispute. In addition, the Defendant did not allege that any of the terms in VO2 had not been agreed on, or that the Claimant had failed to perform any of the works required by the terms of VO2. Thus, despite the lack of clarity in Ms Ong’s AEIC as to which of the works in VO2 the Claimant had actually completed, I am prepared to accept, based on the absence of any challenge by the Defendant, that parties had agreed to the terms of VO2 as reflected in the CVO and the DVO (see the tables at [27] above), and that the Claimant had in fact completed the works required by VO2.

  177. [29] Accordingly, the Claimant is entitled to be paid $37,360 for the works it had carried out pursuant to VO2.

  178. (c) The Claimant is entitled to payment of $9,158 for the works done in respect of VO1.

  179. [30] Finally, I come to VO1. As the terms of VO1 are not before me, I can only consider the secondary question of whether all the works required by VO1 have been completed by the Claimant. In this vein, the Defendant does not dispute that these works had been duly carried out by the Claimant; he in fact accepts that the value of the works under VO1 is the sum of $9,158, which is also reflected in Invoice 22003.

  180. [31] Hence, I find that the Claimant is entitled to be paid $9,158 for the works it had carried out pursuant to VO1.

  181. (d) The Defendant has only partially proved the nature of the works omitted and the price of these works.

  182. [32] I turn now to consider the meat of the parties’ dispute in respect of the discrepancies between the CVO and the DVO. This dispute centres on the items that were actually omitted from the scope of the Contract, as well as the value of the said items, under Omissions 1 and 2. As highlighted at [14] above, the value of the excluded works under Omissions 1 and 2 are materially different across the CVO and the DVO. For now, I will generally refer to the works under Omissions 1 and 2, regardless of whose version I prefer, as the “Omitted Works”.

  183. [33] The Defendant not only argues that the individual and total values of the Omitted Works should be as stated in the CVO, but goes further than mere arithmetic by arguing that certain individual items in the Omitted Works are incorrect. The incorrectness allegedly takes the form of the Claimant deliberately failing to credit him for work it did not do in order that it might pocket the difference (the “Profit Argument”). Essentially, I understand the Defendant to mean that if the value of the Omitted Work in question was actually $100, the Claimant reflected it as $80 in its CVO in order that it could profit by a sum of $20 (by depriving the Defendant of that $20 credit).

  184. [34] Given the seriousness of this allegation, I had expected to see some rebuttal to the Profit Argument in the CS. Disappointingly, there was none. The only argument the Claimant raised in the CS in response to the discrepancies between the CVO and the DVO was an indirect one specifically referring to Invoice 22003. The Claimant argues that the Defendant had purportedly accepted the accuracy of the figures in Invoice 22003 by his statement “these are the valid amounts” (the “Statement”) in his email of 20 April 2023 at 17:38 (the “20 April Email”). According to the Claimant, the Defendant was in his 20 April Email replying to an earlier email one Ms Chin Mui Foong (“Ms Chin”) had sent to him on 17 April 2023 at 12:00 on behalf of the Claimant (the “17 April Email”). The Claimant appears to take the position that a copy of Invoice 22003 had been attached to the 17 April Email (see the line “I have attached the invoice for your reference” in that Email), and that the Statement therefore meant that the Defendant had acknowledged that all the amounts contained in Invoice 22003 were “valid amounts”.

  185. [35] The Defendant denies accepting the validity of the figures in Invoice 22003. Under cross-examination, the Defendant alleged that the copy of the Invoice 22003 at page 79 of the CBOD was not the same as the copy of Invoice 22003 he was referring to in his 20 April Email. In re-examination, the Defendant claimed that his Statement referred to “a VO of the painter that she said she did on behalf”, with the “valid” sum being “two times 1,900”.

  186. [36] In my judgment, the Claimant’s argument is not only unsubstantiated as a matter of evidence, but in fact premised on a fundamental misreading of the Statement. I therefore reject it entirely. My reasons are as follows:

  187. (a) First, in order for the Claimant’s argument to get off the ground, the Claimant must prove that it was the CBOD version of Invoice 22003 that was attached to Ms Chin’s 17 April Email. There is no evidence of this at all. None of the file names of the documents attached to the 17 April Email, which can be seen at the bottom of the said Email, can reasonably be interpreted to refer to Invoice 22003. Further, the only person in the position to testify on the Claimant’s behalf as to what document was actually attached to the 17 April Email is Ms Chin, who was not called as a witness at trial. Hence, the foundational fact which the Claimant must rely on to assert the accuracy of the figures in Invoice 22003, being that Invoice 22003 was attached to the 17 April Email, is not proved.

  188. (b) Second, even if the Claimant managed to prove that Invoice 22003 was attached to the 17 April Email, I disagree with the Claimant’s interpretation of the Statement. The Claimant has misquoted the Statement in its pleadings and in the CAEIC by citing the Statement as being “these are valid amounts”. But the Statement actually reads “these are the valid amounts (emphasis added)”. The meanings of these two statements are completely different. The Claimant’s erroneous version suggests an unequivocal acceptance by the Defendant of whatever figures he was looking at. The correct version, however, suggests that there are some amounts which the Defendant considered to be “valid”, and which he identified by referring to them as “the valid amounts”. In other words, the word “the” modifies the sentence by suggesting that there are specific “valid amounts” being identified. The corollary of this interpretation, which I prefer and adopt, is that there are amounts which the Defendant felt were not valid. The Claimant’s entire argument therefore falls apart. The onus lies with the Claimant to prove what these specific “valid amounts” were, and what document the Defendant was referring to in making this Statement. But the Claimant has failed to do so.

  189. [37] Having rejected the Claimant’s argument, I proceed to consider the Defendant’s argument in relation to the two Omissions. According to the Defendant, the correct value for each set of omissions is as follows:

  190. (a) Omission 1 - $33,385 (and not $28,295); and

  191. (b) Omission 2 - $21,910 (and not $15,830).

  192. [38] The Defendant also takes issue with the correctness of several items and prices reflected in the CVO under Omissions 1 and 2. I will consider these allegations in respect of each Omission in turn.

  193. (i) The Defendant is entitled to an additional credit of $2,240 under Omission 1.

  194. [39] I start with the Defendant’s contentions in respect of Omission 1. There are two material differences between the Omission 1 items recorded in CVO as opposed to that in DVO. The first difference relates to the dry kitchen works, which only appear in the CVO and not in the DVO. These works are as follows :

  195. s/no.

  196. Dry Kitchen Works

  197. Cost

  198. 2

  199. To design, supply and install kitchen cabinets

  200. $2,420

  201. a

  202. Length:11ft approx (Top)

  203. Length:13ft approx (Bottom)

  204. $2,860

  205. b

  206. To design, supply and install full height tall unit

  207. Length:2ft approx (Full height)

  208. To design, supply and install island c/w storage

  209. Length:9.5ft approx

  210. $1,200

  211. $2,850

  212. Sub-total:

  213. $9,330

  214. [40] For all four dry kitchen items, the Claimant’s position is that it had performed all works totalling $9,330.

  215. [41] The second difference relates to the wet kitchen works, which only appear in the DVO but not in the CVO. These works are as follows :

  216. s/no.

  217. Wet Kitchen Works

  218. Cost

  219. 2

  220. To design,supply and install kitchen cabinets

  221. a

  222. Length:19ft approx (Top)

  223. $3,800

  224. b

  225. Length:18.5ft approx (Bottom)

  226. $4,070

  227. c

  228. To supply labour and material to install quartz worktop

  229. Length: 18.5ft approx (Bottom)

  230. To design,supply and install island c/w storage

  231. Length: 9.5ft approx

  232. $3,700

  233. $2,850

  234. Sub-total:

  235. $14,420

  236. [42] Ms Ong accepts that the Claimant did not carry out three of the four wet kitchen works totalling $11,570. These works pertained to the kitchen cabinets at s/n 2a and 2b and the quartz worktop at s/n 2c. Hence, for these three items, Ms Ong conceded that they were rightly reflected as omissions in the DVO. As for the fourth item pertaining to the island with storage priced at $2,850, Defendant’s counsel appears to have omitted to cross-examine Ms Ong on this point. The Defendant’s position as to whether this kitchen island had been omitted from the wet kitchen works has therefore not been established. I therefore decline to consider this item in the analysis that follows.

  237. [43] Based on Ms Ong’s own testimony, it seems that the correct way to reflect the works that were not carried out by the Claimant under Omission 1 would be to only include the three items totalling $11,570 under the wet kitchen works. The dry kitchen works, having all been performed, should not have appeared as an omission at all. Thus, the Defendant should have been given credit of $11,570 for these three omitted wet kitchen works. Instead, what that Claimant did in its own version of the CVO was to reflect the dry kitchen works as omissions – when that was not true – thereby giving the Defendant a total credit of only $9,330. In other words, the Claimant, by its CVO, purported to give the Defendant a lower credit amount via Omission 1. The illogical state of the paperwork issued by the Claimant calls for a good explanation from Ms Ong.

  238. [44] To this end, when Ms Ong was asked twice why the dry kitchen works were reflected as omissions when they were in fact carried out, her responses were meandering and difficult to follow. From her answers, I distil the following main points: (a) that there were many changes made to certain works after the Contract had been signed; (b) there was allegedly already an “agreement” to unknown terms; and (c) there were “measurement differences” which Ms Ong wanted to capture in her CVO.

  239. [45] None of these three points address the question and/or the Profit Argument directly. Changes to the scope of renovation works after a formal contract has been executed are, generally speaking, common in the industry. It is in no way an excuse for an interior designer to create and adduce into evidence a completely inaccurate VO. Further, I do not know what “agreement” Ms Ong was referring to in her answers. If by “agreement” she means that parties had agreed on the works to be excluded as reflected in the CVO, then it begs the question as to why the Claimant went ahead to carry out those works anyway (see [40] above). If by “agreement” she means that parties had agreed on the works to be excluded as reflected in the DVO, that still does not answer the question. Finally, differences in the measurements of structures and cabinetry do not explain why the Claimant had to generate an inaccurate document in the form of the CVO (in relation to the dry kitchen work).

  240. [46] The Claimant having failed to give a satisfactory explanation as to why the CVO contained incorrect line items under Omission 1, I agree with the Defendant that he ought to have been given a credit of $11,570 for the omitted wet kitchen works under Omission 1 and not a credit of $9,330 for the completed dry kitchen works. In this respect, it is the DVO and not the CVO that accurately reflects the works omitted under Omission 1. The Defendant was therefore shortchanged by $2,240 in respect of the credit he ought to have been given for Omission 1.

  241. (ii) The Defendant is entitled to an additional credit of $6,650 under Omission 2.

  242. [47] I move on to the Defendant’s contention with respect to Omission 2. There are three material differences between the Omission 2 items recorded in the CVO as opposed to that in the DVO. The first difference relates to three wet-work items which only appear in the DVO and not in the CVO. These works are the ones highlighted in grey in the table below :

  243. s/no.

  244. Works

  245. Cost

  246. Wetworks

  247. a

  248. To supply labour ,sand & cement to lay wall tiles

  249. Area:360sqft approx. tiles size 600x600

  250. $4,500

  251. b

  252. To supply labour, sand & cement to lay wall floor tiles tiles by owner

  253. c/w 3X application of waterproofing membrane

  254. Area:100sqft approx. tiles size 600x600

  255. $1,500

  256. c

  257. To supply labour & material to construct kitchen kerb

  258. $650

  259. d

  260. To supply labour & tools to seal up existing entrance

  261. $550

  262. Plumbing Works: Wetkitchen

  263. To supply labour to install 1no sink & Tap

  264. $150

  265. Powder Room: Vanity

  266. b

  267. To design, supply and install vanity cabinets

  268. Length:2ft approx

  269. $360

  270. c

  271. To design, supply and install caserstone worktop

  272. Length:2ft approx

  273. $780

  274. 3

  275. Quartz Top: Dry Kitchen

  276. a

  277. To supply labour and material to install Dry Kitchen quartz worktop

  278. Length:13ft approx (Bottom) Caserstone

  279. $3,380

  280. b

  281. To supply labour and material to install island quartz worktop

  282. Length:9.5ft approx

  283. $2,470

  284. Quartz Top: Wet Kitchen

  285. c

  286. To supply labour and material to install quartz worktop

  287. Length:18.5ft approx (Bottom)

  288. $3,700

  289. Quartz Top: Powder Room

  290. c

  291. To design, supply & install caserstone worktop

  292. Length: 2ft approx

  293. $780

  294. 4

  295. Timber Polishing: Handrail

  296. To supply labour & tool sand down existing timber c/w oilbase coat by hand

  297. $800

  298. Quartz Top: Master ROOM

  299. c

  300. To supply labour and material to install quartz worktop

  301. Length;6.5ft approx

  302. $1,690

  303. c

  304. To design, supply and install caserstone worktop

  305. Length:3ft approx

  306. $600

  307. Sub-total:

  308. $21,910

  309. [48] The second difference is in the work to be done to the powder room vanity; specifically, a Caesarstone worktop at $780 (highlighted in the light blue row in the above table). That, too, only appears in the DVO and not the CVO.

  310. [49] The third difference is the works pertaining to the polishing of timber handrail priced at $800 (highlighted in the light green row in the table at [47] above). That line item only appears in the DVO and not the CVO.

  311. [50] Hence, the total value of the omitted works under Omission 2 in the DVO amounted to $21,910. In contrast, the total value of the omitted works under Omission 2 in the CVO amounted to $13,680.

  312. [51] In respect of Omission 2, Ms Ong conceded that the Claimant did not carry out the works in the three grey rows of the table at [47] above (the “Three Items”). As for the row highlighted in blue, Defendant’s counsel did not specifically put to Ms Ong that this worktop had not been constructed. Hence, I say no more about it. Finally, for the row highlighted in green, parties are at odds as to whether this job relating to the timber handrail was carried out. In my judgment on the counterclaim, I have found that the Defendant is unable to prove that the Claimant failed to stain the timber handrail (see [151] below). Because of this, this line item ought not to be reflected as an omission, and consequently the Defendant ought not to be given credit of this sum of $800. The CVO, by leaving out this item under Omission 2, is therefore correct to this extent.

  313. [52] In sum, the Claimant’s evidence, at the very least, suggests that the Three Items were in fact omissions which should be reflected under Omission 2. Like with Omission 1, the fact that these Three Items are missing from Omission 2 in the CVO calls for an explanation from the Claimant.

  314. [53] Like with her answers vis-à-vis Omission 1, Ms Ong’s response to the question as to why the Claimant wrongly omitted the Three Items from her CVO was not convincing. She raises two points in this respect: (a) that there were changes made to certain works after the Contract had been signed; and (b) there was allegedly a change in location for some works to be carried out (to the wet kitchen, it seems).

  315. [54] Neither answer assists the Claimant. It bears repeating that all the documents the Claimant issues to its clients and tenders to Court must be accurate. Where there are amendments made to the scope and/or nature of these works, the Claimant must be all the more careful to ensure the accuracy of its documentary record. This is important not just as a matter of professional standards, but also as a matter of principle. The Claimant cannot justifiably withhold a credit to the Defendant for works which parties have agreed should not be carried out and which were in fact not carried out. Further, Ms Ong’s answer pertaining to the change in location of certain works is beside the point. It again fails to address the core issue of why her CVO did not simply accurately reflect this.

  316. [55] I therefore find that the Defendant ought to have been given an additional credit of a sum of $6,650 under Omission 2, being the total value of the works in respect of the Three Items. In this respect, it is the DVO and not the CVO that accurately reflects the Three Items under Omission 2.

  317. [56] Thus, the total value of the additional credit the Defendant ought to have been given in relation to the Omitted Works is the sum of $8,890. I will set off this sum against any amount owing by the Defendant to the Claimant under Invoice 22003 (see [69] to [71] below).

  318. [57] In sum, the answer to Issue 2 is that the DVO appears to be relatively more accurate as to the contents of the three VOs and the Omitted Works in comparison to the CVO.

  319. F Issue 3: Does the Defendant owe the Claimant a total sum of $31,604.13 based on the Two Invoices?

  320. [58] At this point, I have dealt with the rather involved individual components of Invoice 22003. I therefore move on to consider the claim based on the Two Invoices.

  321. (a) Invoice 22003

  322. [59] The grand total of $17,204.13 reflected at the bottom of Invoice 22003 comprises the following:

  323. (a) The total bill, comprising:

  324. (i) The value of the Contract, being $177,595;

  325. (ii) The sum total of the value of the three VOs;

  326. (iii) A sum of $20,456.40 for “outdoor ceiling”; and

  327. (iv) A sum of $3,800 “payable to Jackie”,

  328. (b) From which is subtracted:

  329. (i) The total value of the Omitted Works under Omissions 1 and 2; and

  330. (ii) The sum total of payments made by the Defendant to the Claimant as of the date of Invoice 22003, being $203,000.

  331. [60] Before I delve into the substance of the individual line items, I pause to flag a number of problems evident on the face of Invoice 22003. These problems substantively affect the quantum of the claim.

  332. [62] This brings us to the second problem with Invoice 22003. There are a number of arithmetic errors evident on the face of the Invoice.

  333. (a) The Invoice reflects the sub-total of the values of the Contract and the three VOs as “$237,922.73”. A quick calculation shows, as the Defendant points out, that the correct total is actually $237,722.73. The Claimant was aware of this arithmetic error as of the date it received the DAEIC, and sought to avoid addressing it by arguing that this computational error was not pleaded. This objection is a feeble one which I reject for two reasons. One, the Claimant had ample notice of more than two months between the date the DAEIC was filed (19 January 2026) and the date of the trial (27 March 2026) that the Defendant intended to raise and rely on this computational error in defending the claim. There is therefore no prejudice caused to the Claimant to have to address this computational error in proving its claim (see How Weng Fun at [20]). Two, regardless of whether the Defendant pleaded this computational error, it is an absolute mathematical truth that this sub-total is incorrect. If this Court were to blinker itself from recognising and factoring in this error in computing the money award to the Claimant, that would result in the Claimant being unjustly overcompensated by $200. This is something that no Court should countenance, and is in fact the sort of injustice that should be overcome by permitting an unpleaded point to be raised (see How Weng Fun at [20]). For the avoidance of doubt, my rejection of the Claimant’s argument pertaining to the Defendant’s omission to plead the former’s computational errors applies to all such errors evident on the face of the Claimant’s documents.

  334. (b) The Invoice reflects the total sum of the two sets of omissions from the Contract, individually valued at $28,295 and $15,830, as “$41,975”. Again, this is wrong as a matter of basic arithmetic; the correct total ought to be $44,125. I do not know why or how the Claimant made this error or why this arithmetical mistake was not caught at the point the pleadings and/or the AEICs were filed; no explanation was given by the Claimant in this regard. In any case, the effect of this error will be nullified in the course of my decision on the value of the Omitted Works and the claim premised on Invoice 22003.

  335. [63] I proceed to address each line item in Invoice 22003 in the order in which they appear on that Invoice.

  336. (i) The value of the Contract, pre-variations, is admitted by the Defendant.

  337. (ii) The Claimant has only partially proved the total value of the three VOs and the Omitted Works.

  338. [65] Based on my findings at [12] to [57] above, the total value of the works carried out by the Claimant in respect of the three VOs, and for which it is rightly entitled to payment, is the sum of $60,127.73. The breakdown is as follows:

  339. (a) VO1 – $9,158.

  340. (b) VO2 – $37,360.

  341. (c) VO3 – $13,609.73.

  342. [66] Hence, taking the sub-total of $60,127.73 and the undisputed Contract price of $177,595, the correct sub-total of the values of the Contract and the three VOs is $237,722.73. As it turns out, the substantively correct figure for this sub-total is in fact the same as the arithmetically correct figure based solely on adding up the numbers reflected in Invoice 22003 (see [62(a)] above).

  343. [67] As for the Omitted Works, I have found that the Defendant ought to have been given an additional credit of $8,890 (see [55] above). For the sake of clarity, I set out the correct values of the Omitted Works under Omissions 1 and 2:

  344. (a) Omission 1 – $30,535. I derive this figure by adding $2,240 to the total of $28,295 reflected on the CVO as the value of the credit to be given for Omission 1.

  345. (b) Omission 2 – $20,330. I derive this figure by adding $6,650 to the total of $13,680 reflected on the CVO as the value of the credit to be given for Omission 2. I do not accept the figure of $15,830 stated in Invoice 22003 as the starting value of the credit under Omission 2 because I cannot tell where this figure is taken from. The Claimant also failed to address this material discrepancy between its own Invoice and CVO.

  346. [68] Hence, the total value of the credit to be subtracted from the sum owed by the Defendant is $50,865.

  347. (iii) The Claimant is therefore owed a total of $4,314.13 in respect of Invoice 22003.

  348. [69] It is not disputed that the Defendant had to pay the Claimant a sum of $20,456.40 for “outdoor ceiling” works, as reflected in Invoice 22003. Hence, the total sum the Defendant owes to the Claimant under Invoice 22003, prior to any credit being taken into account and excluding the sum of $3,800 which I have dismissed, is $258,179.13.

  349. [70] Parties agree that the Defendant has paid the Claimant $203,000 thus far pursuant to the Contract. Adding that sum to the total value of the Omitted Works (being $50,865), the sum of $253,865 ought to be deducted from the total sum owed by the Defendant.

  350. [71] Accordingly, the claim premised on Invoice 22003 is allowed in part, in the sum of $4,314.13. This sum already factors in the sum of $8,890 referred to at [55] above.

  351. (b) Invoice 23004

  352. [72] Finally, I turn to consider the claim premised on Invoice 23004 for the sum of $14,400. The bill in Invoice 23004 was purportedly for some variation work carried out by the Claimant as documented at page 81 of the CBOD. That document is titled “Variation Work”. To avoid any confusion with the three VOs I have already dealt with, I will refer to page 81 of the CBOD as the “19 April VO”.

  353. [74] Like with Invoice 22003, I first deal with a point on pleadings raised by the Claimant. The Claimant argues that, unlike the situation with Invoice 22003, the issues the Defendant had with Invoice 23004 could have been pleaded as Invoice 23004 had been in the Defendant’s possession all along. Put another way, the Defendant did not need to wait till AEICs were exchanged to realise that he took issue with most of the items listed in Invoice 23004. Whilst the Claimant acknowledged that the Defendant pleaded his dispute with “seven out of the 10 items” listed in the 19 April VO, those items were not particularised in the pleadings. Despite these objections being raised at the trial, counsel for the Defendant did not explicitly respond to them in closing submissions.

  354. [75] The Claimant has a stronger case in respect of Invoice 23004 than with Invoice 22003. It is true that the Defendant’s objections to the items in the 19 April VO were neither identified nor particularised in the D&CC, save for item 7 pertaining to plumbing work for the sum of $6,000. However, on balance, I find it appropriate to consider the merits of the Defendant’s dispute to the remaining eight items in the 19 April VO for the following reasons. First, the Defendant ultimately substantiated his bare pleadings in his DAEIC. Second, Defendant’s counsel questioned Ms Ong on most of the components of 19 April VO, thus giving her fair opportunity to state her case in respect of the same. The Claimant (and Ms Ong) would have had notice of these contentions by the time it received the DAEIC, and cannot be said to have been caught off-guard by the same. Indeed, Claimant’s counsel set out his arguments in respect of the disputed items of the 19 April VO in closing submissions. Finally, the burden of proof ultimately rests on the Claimant to prove its claim in respect of Invoice 23004. Even if the Defendant remained silent in his DAEIC and only pleaded a bare objection to the said Invoice, the Claimant would still have to adduce sufficient evidence to make out its case.

  355. (i) The claim for $2,950 premised on Items 1a and 1b for wetworks in the master bathroom is dismissed.

  356. [76] The Claimant’s case in respect of items 1a and 1b is that these line items were necessitated by the Defendant wanting to install larger tiles in his master bathroom after the Contract had been signed. Larger tiles required more labour to install them, and thus the Claimant had to bill the Defendant an additional $950 + $2,000 for these works under item 1 of the 19 April VO on top of the $5,000 already billed under the Contract at item D2d . According to Ms Ong, parties had a verbal agreement for the Claimant to carry out these works at these prices stated in the 19 April VO.

  357. [78] In my judgment, the Claimant has failed to prove that the Defendant knew that he had to pay and agreed to pay an additional sum of $2,950 at the point of this alleged verbal agreement. I explain.

  358. (a) First, I accept that the sum billed by the Claimant for the works in item 1 of the 19 April VO were additional to the sum of $5,000 in the Contract and not a “duplicate” billing as alleged by the Defendant in his DAEIC. The additional sum of $2,950 is too small by almost half, relative to the $5,000 the Claimant charged to install tiles of a smaller dimension, for it to be a duplicate billing.

  359. (b) Second, I am prepared to accept that there was some sort of verbal agreement for the Claimant to install larger tiles in the master bathroom after the Contract was signed. The Defendant did not dispute this aspect of Ms Ong’s testimony, and in fact suggested that he “may have asked” the Claimant to change the size of these said master bathroom tiles. This is enough of a concession for me to arrive at this conclusion.

  360. (c) Third, based on Ms Ong’s own answers at trial, there was no agreement on the increased costs necessitated by the installation of these larger master bathroom tiles. An agreement to carry out works is not the same as an agreement on the price of these works. The Claimant must not only prove the agreement to install the larger tiles (which it has), but it must also prove that the Defendant knew of and agreed to the additional costs in respect of the same at the time of contract formation. In this regard, Ms Ong conceded that she did not inform the Defendant of what these additional costs were until after the works had been completed. Thus, on her own evidence, there was no agreement on price to speak of. The mere fact that the Defendant did not dispute the costs stated in item 1 of the 19 April VO until this lawsuit is neither here nor there; silence, without more, does not prove agreement.

  361. (ii) The claim for $850 premised on Item 2 for wetworks in the common bathroom is dismissed.

  362. [80] The Claimant’s case in respect of item 2 of the 19 April VO is that this sum of $850 was for additional labour necessitated by the installation of larger tiles in the common bathroom. However, unlike with item 1, this item 2 did not come about as a result of the Defendant changing his mind after entering into the Contract. From Ms Ong’s answers in cross-examination, it seems that the Claimant had initially billed the Defendant $3,800 to install 600mm x 900mm wall tiles in the common bathroom on level 2 in the Contract (see item C4d of the Contract). But because of a “typo issue” in item C4d of the Contract, the size of these wall tiles was not stated in the Contract. Eventually, the Claimant installed 600mm x 1,200mm wall tiles in the common bathroom, and billed the Defendant an extra $850 for the additional labour required to install these larger tiles.

  363. [81] The Defendant argues that item 2 of the 19 April VO is a duplicate billing for item C4d in the Contract. His case is premised on the fact that the dimensions of the wall tiles in the level 2 common bathroom were not stated in the Contract, and therefore the Claimant cannot disprove the allegation of duplicate billing.

  364. [82] In rebutting the Defendant’s case on item 2, Claimant’s counsel alleges that the Defendant had apparently conceded under cross-examination that the common bathroom tiles would be 600mm x 900mm under the Contract. This is based on a misinterpretation of the Defendant’s answers at trial. The Defendant only agreed that the floor tiles of the common bathroom were 600mm x 900mm under the Contract. But the item in issue, according to the Defendant, is the wall tiles of the common bathroom; his case is that item 2 of the 19 April VO relates to wall tiles and not floor tiles.

  365. [83] Having reviewed the documents before me and parties’ answers at trial, I am unable to make a finding either way. Item C4d of the Contract does not state the size of the wall tiles to be installed in the common bathroom. Item 2 of the 19 April VO does not make clear whether it relates to the installation of wall tiles or floor tiles. Thus, the Claimant has no evidence to prove that item 2 of the 19 April VO relates to wall tiles or floor tiles in the common bathroom, and certainly has no evidence to prove that, even if item 2 relates to wall tiles, that item C4d of the Contract was priced with 600mm x 900mm tiles in mind. I reiterate that it is not the Claimant’s case that item 2 of the 19 April VO came about as a result of an agreed variation of the Contract. On the other hand, the Defendant has no evidence to prove that item 2 of the 19 April VO relates only to wall tiles and not floor tiles. Whilst I note that Ms Ong was questioned on wall tiles in the course of Defendant’s counsel’s cross-examination on item 2, the point pertaining to item 2 referring to only wall tiles was not explicitly put to her.

  366. [84] As the burden of proof lies on the Claimant to establish the validity of its claim based on item 2 of the 19 April VO, the claim in this respect fails.

  367. (iii) The claim for $200 premised on Item 5 for the transport and purchase of trash bags is allowed.

  368. [85] For some reason, despite the Defendant taking issue with item 5 of the 19 April VO in his DAEIC, counsel for the Defendant did not cross-examine Ms Ong on item 5. Even more strangely, despite counsel for the Defendant making clear his client’s dispute to item 5 at trial, counsel for the Claimant did not make any submissions on item 5 in closing submissions.

  369. [86] In my judgment, Defendant’s counsel ought to have put his client’s dispute to item 5 to Ms Ong in order to give her a chance to respond to his client’s allegation in respect of the same. This is especially important in light of the fact that the Defendant’s detailed grounds for disputing item 5 were only made clear in his DAEIC, which was concurrently filed and exchanged with the CAEIC. Given how proceedings panned out (in that no applications for supplementary AEICs to be adduced were made by either party), the only chance Ms Ong had to substantively respond to the Defendant’s case vis-à-vis item 5 – and indeed, the rest of the disputed items in the 19 April VO – was in cross-examination. Because of this omission on the Defendant’s part to adhere to the rule in Browne v Dunn (1893) 6 R. 67, I give no weight to the Defendant’s contention in respect of item 5 of the 19 April VO.

  370. (iv) The claim for $1,800 premised on Item 6 for a round of general cleaning is dismissed.

  371. [88] There is some ambiguity in respect of how item 6 of the 19 April VO is framed. The phrase “general cleaning 3rd trips” could be referring to a bill for three rounds of general cleaning, or to a bill for only the third round (singular) of general cleaning. Under cross-examination, Ms Ong did not take issue with Defendant’s counsel framing this line item as being for the third round of general cleaning only. Nor did parties make any submissions on an alternative reading of item 6. I therefore accept that item 6 refers to a single round of general cleaning, being the third round of cleaning, for the Property.

  372. [89] The Claimant’s case is that the third round of cleaning which item 6 of the 19 April VO pertains to was for “almost the whole house”, and was carried out at the Defendant’s request. Like with items 1a and 1b, the Claimant suggests that the legal basis for item 6 was also a verbal agreement.

  373. [91] I am sympathetic to the Claimant’s argument that the Defendant seems to have materially changed his defence in respect of item 6 of the 19 April VO. In the DAEIC, the Defendant’s case was the third round of cleaning was necessitated by the Claimant’s contractor having to re-stain the staircase after an initial poor staining job. At trial, the Defendant’s case morphed to one based on a lack of agreement, be it to the third round of cleaning per se or to its price.

  374. [92] However, knowing what the Defendant’s case purported to be in his DAEIC, the Claimant had to come prepared to explain at trial its own basis for claiming the $1,800 under item 6 and for disagreeing with the Defendant. In other words, the Claimant had to show that it was the Defendant who requested for this third round of cleaning (unrelated to any allegedly poor job the Claimant’s contractors had done). In doing so, the Claimant had to prove that parties agreed, not only for the Claimant to carry out this third round of cleaning, but also to the price it would charge the Defendant for the same. As Ms Ong conceded, the first time the Defendant knew that he would be charged $1,800 for this third round of cleaning was only after the job had been done, upon his receipt of Invoice 23004. This is effectively a concession that there was no agreement on price at the time the verbal agreement was supposedly formed.

  375. [93] Hence, I also dismiss the claim for $1,800 premised on item 6 of the 19 April VO.

  376. (v) The claim for $6,800 premised on Items 7 to 9 for plumbing work, ceiling work, and paint work is allowed.

  377. [94] In their respective submissions, parties dealt with items 7 to 9 of the 19 April VO collectively. Because the defence to these three items is a highly-specific one, it makes more sense to set out the defence first before proceeding to set out the basis of the claim.

  378. [95] The Defendant argues that these plumbing, ceiling, and paint works were necessitated by a choke in the pipes of the Property caused by cement debris, for which he says “Jackie’s negligent contractors” were responsible. At trial, the Defendant clarified that this choke was found in the pipes on the second floor of the Property.

  379. [96] In response, the Claimant denies causing or being responsible for this chokage. Its case is that the Defendant had specifically requested for the Claimant to carry out rectification works to the Property’s discharge and main pipes to resolve this choke. The Claimant subsequently charged the Defendant an additional $6,000 under item 7 of the 19 April VO for these rectification and consequential works.

  380. [97] It is undisputed that the discharge and main water pipes of the Property were choked by cement and a water bottle cap (and not a water bottle as the Claimant alleges) sometime around 23 December 2022. The cause of the choke was uncovered on 23 December 2022, as evinced by the photographs and timestamps of the same at Tab 22 of the CAEIC. Ms Ong also reported the cause of this choke to Ms Carol, the Defendant’s wife, via WhatsApp message on 27 December 2022. In these messages, Ms Ong detailed that the cement was found in the level two pipes and the bottle cap was found in the pipes connected to the level one toilet bowl.

  381. [98] Thus, the key question I need to decide on is who caused the choke by pouring cement and discarding the water bottle cap into the Property’s pipes. If the Defendant cannot prove that the person(s) responsible for doing so were “Jackie’s negligent contractors”, then the entire defence falls apart.

  382. [99] Having reviewed the evidence, I find that the Defendant is unable to prove his assertion that it was the Claimant’s contractors who had caused the said choke in the pipes. Other than a throwaway assertion in his DAEIC, the Defendant has adduced no evidence of the cause or the person(s) responsible for the chokage. In fact, Defendant’s counsel did not even put to the Claimant the crux of his defence vis-à-vis items 7 to 9; viz., that it was the Claimant’s contractors who caused the choke. Furthermore, it is not a fait accompli that the Claimant must be responsible for the choke simply because the Claimant’s workers had performed cement works on the Property. Something more in terms of proof is required before I am prepared to draw such a conclusion. In any case, this does not explain the bottle cap in the level one pipes.

  383. [100] For these reasons, I find that the defence in respect of items 7 to 9 holds no water. Concurrently, I accept the Claimant’s explanation that the cause of the choked pipes is unknown.

  384. [101] Taking the above findings together with the Defendant’s lack of objection to the Claimant’s position that the works required by items 7 to 9 of the 19 April VO were in fact carried out at the Defendant’s request, I accept the Claimant’s evidence that these works were meant to rectify the choked pipes at the Defendant’s request. It seems only logical to me that the Defendant would want choked pipes on his relatively new Property to be rectified, and that he had asked the Claimant to do so. I pause to emphasise that, unlike the situation with items 1 and 6 of the 19 April VO, it is not the Defendant’s case that he did not agree to the works under items 7 to 9 or to the price the Claimant charged him for the same.

  385. [103] The claim premised on Invoice 23004 is therefore allowed in part, in the sum of $9,350.

  386. G Issue 4: Did the Claimant breach the Contract by failing to complete its works and/or causing or creating the Alleged Defects?

  387. [104] The Defendant pleaded a total of 12 incomplete works and/or Alleged Defects which he says were caused by the Claimant and for which he ought to be compensated. I will deal with them in the order in which they appear in the D&CC.

  388. [105] Before I do so, I deal with the Claimant’s argument that the Defendant had failed, throughout the proceedings, to identify any clause of the Contract that had been breached by the Claimant. While this argument is technically correct, I fail to see why this ought to obstruct my consideration of the merits of the counterclaim. Though the clarity and level of detail in the Defendant’s D&CC can undoubtedly be improved, that pleading in my view sufficiently sets out the parameters of the complaint underpinning the counterclaim. The D&CC:

  389. (a) Identifies the contract governing the original scope of works the Claimant was supposed to perform;

  390. (b) Adduces sufficient material facts to found a case of breach of that contract against the Claimant; and

  391. (c) Generally refers to specific areas of the Property and specific fixtures/fittings within the Property in respect of which the Claimant allegedly failed to perform the works it was contractually-bound to do and/or created or caused defects in. For example, the eleventh allegation in D7 refers to the staining of a wooden handrail priced at $800. This sufficiently identifies the applicable clause of the Contract as being clause J(2). To be sure, the Defendant’s failure to plead the relevant clauses which he says the Claimant has breached makes my and Claimant counsel’s task of analysing the dispute a more laborious one than if he had properly pleaded these facts. However, the appropriate place for that to be addressed is in the costs award to be made, rather than shutting out the Defendant’s arguments at the liability stage.

  392. [106] In any case, if it was the Claimant’s case that the works in respect of which these 12 allegations are made did not fall within the scope of the Contract, the Claimant had full opportunity to put its position forth in its DTCC and CAEIC.

  393. [107] For each allegation, I will undertake a three-step inquiry:

  394. (a) I will first consider whether there is a contractual basis for the allegation in question;

  395. (b) Next, I will determine whether the Defendant has managed to establish the alleged non-completion or defect as a matter of fact; and

  396. (c) Finally, I will consider whether the Claimant ought to be held liable for that non-completion or defect.

  397. (i) The counterclaim pertaining to the alleged spacing issue involving the toilet cistern and water closet in the ground floor common bathroom is dismissed.

  398. [108] The Defendant argues that the installation of a toilet cistern and water closet (collectively, “toilet bowl”) in a proper location that facilitates “ergonomic” use of the same falls within the Claimant’s contractual scope of works as set out in line items D2 to D4 of the Contract.

  399. [109] The Claimant’s chief rebuttal to this is twofold. First, the location in which the toilet bowl could be installed was constrained by the location of the existing waste/water pipe, which could not be shifted and which the Defendant did not instruct to be shifted. In other words, the Claimant’s case is that the ability to change the toilet bowl’s location within the common bathroom was contingent on the relocation of the said waste/water pipe being part of the Contract, which, according to Ms Ong, it was not. Second, the Defendant had himself orally approved the location of the toilet bowl in the said common bathroom on 5 January 2022.

  400. [110] I agree with the Claimant that the Defendant’s case fails at the first stage of the inquiry. Fundamental to the installation and proper working of a toilet bowl is that it must be connected to waste and water pipes; this is a matter of plain common sense which requires no expert testimony. It is also commonsensical that these waste and water pipes are located at fixed points, typically within or along the walls and floor of a bathroom. The long and short of all this is that a toilet bowl can only be installed in very limited positions within a bathroom unless these waste and water pipes are extended or their locations altered. In the absence of such relocation works, a homeowner has little choice but to accept that his toilet bowl has to sit in a particular spot within his bathroom.

  401. [111] Having set out this factual premise, the Defendant, in order to establish his case, must prove one of two things: either that it was physically possible for the Claimant to install the toilet bowl in a different location within the said common bathroom (that gives rise to a more spacious and comfortable user experience), or that the alteration of the location of the waste and water piping within the said bathroom, so as to allow the toilet bowl to be installed in a more ideal location, fell within the Claimant’s scope of works under the Contract.

  402. [112] In my judgment, the Defendant has no evidence for both. He has no evidence to show that the Claimant was not in fact constrained by the location of the existing piping in installing the toilet bowl as Ms Ong claims. He has also no evidence nor any meaningful argument that the relocation of the water and waste pipes fall within the Contract. Simply saying that the Claimant was obliged by the line items at D2 to D4 of the Contract to do works that would facilitate an ideal positioning of the toilet bowl is far from sufficient.

  403. (a) D2 does not even relate to works to be done in a common bathroom; that line item – of which there are two, for some reason – pertains to plumbing works to be carried out in the wet kitchen and master bathroom respectively. D2 is therefore not relevant to the present analysis.

  404. (b) Items D3 and D4 are completely identical line items. Their inclusion in the Contract suggests that there was either more than one common bathroom in the Property, or that the Claimant had erroneously included a duplicate of D3 in inserting D4 into the Contract. It seems to me, based on the answers given by Ms Ong under cross-examination, that the first option is the answer, as there is also a common bathroom located on the second floor of the Property. Regardless of whether I refer to D3 or D4, my conclusion is the same: there is no term contained in these line items to suggest that the Claimant would be responsible for changing the location of the waste and water pipes that dictate the installation locations of a toilet bowl. The term that might ostensibly be relevant to this analysis is the term pertaining to the installation of “stainless steel water piping” in items D3 and D4, but it is not the Defendant’s case that this term encompasses water and waste piping relocation works. In any case, I do not see how “stainless steel water piping” can be interpreted to include waste piping.

  405. [113] The sum total of my findings is that the Contract only obliged the Claimant to install the toilet bowl as dictated by the existing locations of the relevant waste and water piping and without altering the locations of these pipes. This is what Ms Ong says the Claimant has done, and in the absence of any evidence to the contrary I accept her version of events in this respect. The Defendant has no case in respect of this alleged defect.

  406. (ii) The counterclaim pertaining to the poorly-laid floor tiles in the ground floor and second floor bathrooms is dismissed.

  407. [114] Frustratingly, the Defendant did not identify the relevant clause of the Contract which capture these floor tiling works to be carried out in the two Bathrooms. That being said, this failure to identify the relevant contractual clauses at play is not fatal to his case for two reasons. One, there are in fact line items in the Contract at C5, D2, and C4(3) spelling out floor tiling works (as well as the installation of waterproofing membranes) to be done in one powder room and two bathrooms on level two (a master bathroom and a common master bathroom). There is at least some apparent contractual basis for these floor-tiling works. Two, the Claimant does not dispute that the installation of floor tiles in the bathrooms on the ground floor and second floor of the Property (the “Bathrooms”) fell within the contractual scope of works. I will therefore refer to these three clauses in considering this second alleged defect.

  408. [115] Having set out the contractual basis for these floor-tiling works, I turn to consider whether the Defendant has managed to prove the alleged defects on a balance of probabilities.