Skip to content
Grounds publishedDecided 28 Apr 2010

High Court

Gammon Pte Limited v JBE Properties Pte Ltd (SCDA Architects Pte Ltd, third party)

Feedback & support

[2010] SGHC 130Case no. Suit No 235 of 2009 (Summons No 1224 of 2009)14 paragraphs

What happened, in plain English

There is no plain-English summary of this judgment yet.

Ask about this judgment

Grounds of decision

Official text from eLitigation

  1. Chan Seng Onn J:

  2. Introduction

  3. [1] This is an application by the plaintiff, Gammon Pte Limited, for an injunction to restrain the defendant, JBE Properties Pte Ltd, from receiving payment from BNP Paribas Singapore on a performance bond.

  4. Background facts

  5. [2] The defendant is a developer and the owner of a building at 6 Handy Road (“the Building”). By a letter of award dated 19 January 2006, the defendant engaged the plaintiff to construct the Building for a sum of $11,515,000. SCDA Architects Pte Ltd (“SCDA”) was engaged as the architect and the superintending officer for the works. The contractual completion date was 17 May 2007. However, SCDA certified an extension of the completion date to 16 August 2007.

  6. [3] During the period between 12 October 2007 and 7 January 2008, defects with the façade cladding of the building were highlighted to the plaintiff through the issuance of superintendent officer instructions (“SOIs”). The plaintiff undertook to rectify these defects in its letter dated 28 January 2008.

  7. [4] On 12 February 2008, SCDA issued the completion certificate certifying completion on 16 January 2008 (“completion certificate”). Enclosed with the completion certificate was a schedule of 52 outstanding classes of defects. To date, not all the defects have been rectified by the plaintiff. Owing to the plaintiff’s failure to remedy the outstanding defects despite several reminders by the defendant, the defendant called on the performance bond on 6 and 27 February 2009 to fund the completion of the rectification work to be done by other contractors engaged by the defendant.

  8. The performance bond

  9. [5] The relevant terms of the on-demand performance bond excerpted in the defendant’s submissions are as follows:

  10. Unconscionability

  11. [6] The plaintiff did not dispute that there were outstanding defects but alleged that it would be unconscionable for the defendant to call on the performance bond. It is settled law in Singapore that in addition to fraud, an injunction to restrain a call on a performance bond may be granted on the ground of unconscionability. Whether unconscionability can be established largely depends on the factual matrix of each case.

  12. [7] The Court of Appeal in Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of HRH Sheikh Sultan bin Khalifa bin Zayed Al Nahyan [2000] 1 SLR(R) 117 at [38] cited Raymond Construction Pte Ltd v Low Yang Tong & Anor [1996] SGHC 136 (per Lai Kew Chai J, at [5]) for the proposition that:

  13. Outstanding sums due to defendant inclusive of the cost of rectification

  14. [10] In my view, the plaintiff had shown a strong prima facie case of unconscionability. The glaring item was defendant’s claim of $2,200,800 for the rectification of cladding defects in SOI 266/08 and SOI 271/08 which according to the defendant was awarded to Weng Thai Construction (“WTC”) on 10 February 2009. The plaintiff alleged that the award to WTC was a sham. The letter of award was a one page document with no scope of work detailed at all. No time frame to carry out the work was specified. The method of rectification was not stipulated. The address of WTC was an HDB flat which appeared to be owned and occupied by one Mr Teoh Weng Thai. WTC did not appear to have any expertise in design, fabrication and installation of cladding. WTC operated as a sole proprietor and was owned by someone not known in the industry. WTC’s incompetence in carrying out the rectification works was confirmed by its supposed intention to appoint another entity, CLK Systems Pte Ltd, to carry out the work. The price of $2,200,800 for the contract awarded to WTC was wholly out of proportion to the value of the works. By comparison, the sub-contract awarded to Seiko for the design, supply and installation of the curtain wall and glazing works was for only $1,690,000. The portion to design, fabricate, supply and install the aluminium panel cladding for the whole façade of the building was only S$371,664. However, the price quoted by WTC for merely rectifying the defects to the aluminium panel cladding was a hefty six times more.

  15. [11] I concluded that WTC’s tender price of S$2.2 million essentially to repair some 83 relatively minor cladding defects was astronomical and grossly inflated so as to enable the defendant to justify the call on the full sum of the performance bond. Serious questions had crossed my mind as to whether there was collusion between the defendant and WTC in this regard.

  16. [12] According to the plaintiff, the defendant still had not paid the plaintiff the following sums:

  17. [13] On top of this sum due to the plaintiff, the defendant still sought to call on the performance bond for a further sum of S$1,151,500. The total amount in excess of $2.9m which the defendant claimed the plaintiff owed primarily for defective works amounted to more than 25% of the original contract value of $11,515,000, which the defendant awarded to the plaintiff to construct the entire building. It would in my view be most surprising that SCDA would have issued a completion certificate certifying that the works were in all respects completed (save for 52 minor outstanding works) when some $2.9 m worth of rectification works remained outstanding if the defendant were to be believed.

  18. [15] In GHL Pte Ltd v Unitrack Building Construction Pte Ltd and another [1999] 3 SLR(R) 44, the Court of Appeal addressed an instance where the call would be unconscionable at [24]:

  19. [16] In the course of the hearing, I asked the plaintiff to obtain quotations so that a comparison could be made with WTC’s tender price. The quotations obtained by the plaintiff were so much lower than those obtained by the defendant. Five quotations were obtained and the highest of those was $560,000 based on a total replacement of the panels. The next highest quotation was $335,000 based on repairing the panels. These were nowhere near the amount quoted by WTC. These huge discrepancies confirmed my belief that WTC’s price of $2,200,800 for the panel repairs had been grossly inflated. I had grave doubts that WTC’s quotation for the rectification work obtained by the defendant was not a sham.

  20. Orders made

  21. [17] Accordingly, I made the following orders:

  22. (a) Call on the bond is to be deferred until further order, with liberty to apply;

  23. (b) All rectification works to be completed by the plaintiff within 6 months. Inspection of rectification work to be carried out in the month of October 2010;

  24. (c) Any dispute on the quality of the rectification works in accordance with the warranty will be determined by the court. If the court determines that the rectification works in accordance with the standard set out in the warranty is not satisfied, the court may direct that, subject to call on the bond, a joint tender be carried out in order to rectify the balance of the unrectified defects as determined by the court. The completion of the balance of rectification works, through the joint tender, shall be deemed to be in accordance with the standard set out in the warranty. The specifications for the contractors for the joint tender, shall be the original specifications for the works; and

  25. (d) Costs are reserved.