  1. Introduction

  2. [2] This case concerned an ID company that sought to do the very opposite. The Respondent was engaged to renovate the Claimant’s HDB flat. However, one of its own interior designers allegedly went rogue: he siphoned off monies that the Claimant had paid to the Respondent and which were meant for the subcontractors working on the renovation, and committed the Respondent to a bargain that left it out of pocket. Faced with a shortfall of approximately $32,000, the Respondent looked to the Claimant to make it good by issuing a revised quotation that raised the price of the renovation by $15,466.50. When the Claimant declined to accept it, the Respondent stopped work and left him with a flat that was only partially renovated. The Claimant sued in the Small Claims Tribunals (“SCT”) for the value of the works left undone, limiting his claim to $20,000 to bring it within the tribunal’s monetary jurisdiction. I allowed the claim in full, though not on the basis on which the Claimant put it. I set out my reasons in this Grounds of Decision.

  3. Facts

  4. The parties

  5. [3] The Claimant was the owner of a five-room HDB flat at [address redacted] (the “Flat”).

  6. [4] The Respondent was an ID company incorporated in Singapore that provided renovation services. Its sole director and shareholder was [CHT], who represented the Respondent throughout the proceedings.

  7. The background to the dispute

  8. [5] On 27 July 2025, the Claimant engaged the Respondent to carry out extensive renovation works to the Flat for $70,800 (the “Contract”). The Contract was prepared and signed for and on behalf of the Respondent by [JX], one of its freelance interior designers.

  9. [6] By 24 September 2025, the Claimant had paid the Respondent $42,480, being 60% of the Contract’s value, by bank transfer in accordance with the payment terms of the Contract. The renovation works commenced on 26 September 2025.

  10. [7] On 9 November 2025, [CHT] discovered that [JX] had allegedly (a) caused the Respondent to enter into an unprofitable renovation contract with the Claimant, and (b) siphoned off monies belonging to the Respondent that were meant to pay the subcontractors who worked on the renovation of the Flat (collectively, the “Alleged Misdeeds”). [CHT] asserted that the Alleged Misdeeds had left the Respondent approximately $32,000 out of pocket on the Contract.

  11. [8] On 10 November 2025, the parties met to discuss how the renovation works were to proceed in light of the Alleged Misdeeds. A major sticking point was the electrical works, which were to be carried out free of charge under the Contract but which the Respondent now wanted to charge for. On 12 November 2025, the Respondent issued a fresh quotation to renovate the Flat for $86,266.50 (the “Revised Quotation”).

  12. (a) firstly, the Respondent would not complete the electrical works that were to be provided free of charge under the Contract, and would enter the Flat to remove those that had already been installed and affixed to it;

  13. (b) secondly, the Respondent would not install the vinyl flooring required under the Contract;

  14. (c) thirdly, the Respondent would place the renovation of the Flat on hold.

  15. [10] Faced with [CHT]’s threat to trespass into the Flat and strip out those electrical works, the Claimant changed the lock to the gate of the Flat on 13 November 2025.

  16. [11] As the Respondent would not continue with the renovation works, the Claimant asked for a refund of the value of the unfinished works under the Contract (the “Unfinished Works”). At trial, I directed the Claimant to isolate that value, and he ascertained it to be $21,450. The Unfinished Works consisted of the following:

  17. S/No.

  18. Item in the Contract

  19. Description

  20. Value

  21. 1

  22. “D. Electrical Works”

  23. This entailed installing electrical wiring and fixtures.

  24. Free

  25. 2

  26. “E. Plumbing Works (Supply Labour & Install)”

  27. This entailed supplying and installing a variety of plumbing fixtures in the Flat.

  28. $2,185

  29. 3

  30. “F. Gypsum Board Works (Supply Material and Labour)”

  31. This entailed fabricating false ceilings and partition walls for the Flat.

  32. $7,616

  33. 4

  34. “H. Painting Works (Supply Material and Labour)”

  35. This entailed supplying paint and painting the Flat.

  36. $1,950

  37. 5

  38. “I. Vinyl Floor Works (Supply and Install)”

  39. This entailed supplying and installing vinyl flooring for the Flat.

  40. $3,913

  41. 6

  42. “K. Countertop Works (Supply and Install)”

  43. This entailed supplying and installing a quartz stone countertop for the kitchen cabinets.

  44. $2,090

  45. 7

  46. “L. Door Works (Supply and Install)”

  47. This entailed replacing the metal gate at the front of the Flat.

  48. $480

  49. 8

  50. “M. Glass Works (Supply and Install)”

  51. This entailed supplying and installing (a) glass doors for the study room and two bathrooms, (b) a shower screen for the common bathroom, and (c) a glass backing for the cooking area in the kitchen.

  52. $2,886

  53. 9

  54. “N. Others”

  55. This entailed general cleaning after completion of all renovation works.

  56. $330

  57. Total:

  58. $21,450

  59. [12] [CHT] rejected the Claimant’s request because [JX] had allegedly misappropriated the Respondent’s money. In a WhatsApp voice message, which was professionally translated, [CHT] said this: “[l]et me tell you, I can’t refund in full, that bastard has already taken my money.” Since the Respondent would neither perform the Unfinished Works nor refund their value, the Claimant engaged another ID company (the “New ID”) to carry them out.

  60. [13] The $21,450 fell within the $42,480 that the Claimant had already paid to the Respondent. In other words, of the works covered by that payment, the Respondent had completed a portion and left the Unfinished Works undone. The Claimant had therefore paid the Respondent in advance for works he did not receive, and [CHT] said nothing to the contrary at trial. The Claimant paid the New ID $39,558 to carry out the Unfinished Works, and he filed the present claim for $20,000 in compensation.

  61. The parties’ cases

  62. [14] The parties’ cases may be summarised as follows:

  63. (a) The Claimant’s case was that the Respondent was in breach of the Contract because it refused to perform the Unfinished Works. On that footing, he sought a refund of the $21,450 that he had transferred as advance payment for them. However, since the default monetary jurisdiction of the SCT was $20,000 (see s 5(3)(a) read with s 2(1) of the Small Claims Tribunals Act 1984 (2020 Rev Ed) (the “SCTA”)), the Claimant abandoned the excess to bring his claim within that threshold.

  64. (b) The Respondent denied that it was in breach of the Contract. Its defence had two aspects. First, it said that the Claimant was the party in breach when he changed the lock to the gate of the Flat on 13 November 2025, thereby shutting its workers out. Second, it disavowed the Contract altogether, on the basis that [CHT] never read it, that it was signed by [JX] rather than by [CHT], and that the Respondent’s company chop was not affixed to it.

  65. Issues to be determined

  66. [15] In view of the foregoing, three issues arose for my determination:

  67. (a) first, whether the Respondent was bound by the Contract (the “First Issue”);

  68. (b) second, if the First Issue was answered in the affirmative, which party repudiated the Contract (the “Second Issue”); and

  69. (c) third, if it was the Respondent that repudiated the Contract, what quantum of damages the Claimant was entitled to (the “Third Issue”).

  70. [16] I address each issue in turn.

  71. First Issue: the Respondent was bound by the Contract

  72. [17] I begin with the First Issue. I found that the Respondent was bound by the Contract, and that its reasons for disavowing it were nothing more than a flimsy afterthought. My reasons were as follows:

  73. (a) First, [CHT]’s own evidence at trial was that [JX], as the Respondent’s freelance interior designer, secured deals for the Respondent. In relation to the Claimant’s renovation specifically, [CHT] confirmed that the Respondent even paid [JX] his commission of $18,700 for securing the Contract.

  74. (b) Second, [CHT] testified that it was the Respondent that engaged and paid the subcontractors who carried out the renovation works at the Flat.

  75. (c) Third, it was undisputed that the Respondent received $42,480, being 60% of the Contract’s value, and that this sum was correctly paid into the Respondent’s bank account pursuant to the Contract.

  76. (d) Fourth, [CHT] personally signed the indemnity form issued by the HDB in order to obtain approval for the hacking works to be carried out at the Flat.

  77. [18] Taken together, the foregoing showed that the Respondent was well aware of the Contract, adopted it, and acted pursuant to it. It was far too late in the day for the Respondent to disavow it. In any event, the Respondent’s argument that it was the Claimant who breached the Contract was self-defeating because that argument could only be run on the footing that the Respondent was itself bound by the Contract. Put simply, the Respondent could not approbate and reprobate the Contract as and when it suited its convenience.

  78. [19] The above was sufficient to dispose of the First Issue, but I go on to make two observations.

  79. (a) First, I found that [JX] had actual authority to enter into the Contract on the Respondent’s behalf. As stated earlier, [CHT]’s own evidence was that [JX] secured deals for the Respondent and was paid commission calculated on the value of the contracts so secured. Even if [JX] had no actual authority, I would have readily found that he had, at the very least, apparent authority to contract on the Respondent’s behalf. Apparent authority may arise where a principal places an agent in a position in which a reasonable third party would regard that agent as having authority to enter into the transaction in question (see Armagas Ltd v Mundogas SA [1986] AC 717 at 777 as cited in Tribune Investment Trust Inc v Soosan Trading Co Ltd [2000] 2 SLR(R) 407 at [48]). In my view, a reasonable person apprised of the facts would regard [JX] as having authority to enter into renovation contracts on the Respondent’s behalf. [JX] was held out as the Respondent’s interior designer, he prepared and signed the Contract in that capacity, and the Contract itself required payment to be made to the Respondent’s bank account rather than to [JX] personally. This accords with what is commonly understood of the residential renovation industry, where individual interior designers routinely prepare and execute such contracts for and on behalf of the companies they work for. As there was no evidence to suggest that the Claimant’s reliance on [JX]’s signature was unreasonable, the Claimant was entitled to presume that [JX] had been duly authorised by the Respondent to enter into the Contract (see The “Bunga Melati 5” [2015] SGHC 190 at [28] and [29]).

  80. (b) Second, the indoor management rule provides that a person who deals in good faith with a company is entitled to assume that all steps necessary to authorise the transaction have been duly taken (see Tan Cheng Han, The Law of Agency (Academy Publishing, 2nd Ed, 2017) at para 05.097 citing Royal British Bank v Turquand (1856) E & B 327). The Respondent did not provide any evidence to suggest that the Claimant acted in bad faith in dealing with it. The Claimant was accordingly entitled to rely on [JX]’s issuance and execution of the Contract for and on behalf of the Respondent. The absence of the Respondent’s company chop and of [CHT]’s signature, even if these were genuine irregularities, did not preclude a finding that the Respondent was bound by the Contract.

  81. [20] For completeness, I say nothing about whether the Alleged Misdeeds were made out. [CHT] testified that several police reports had been lodged against [JX], yet no action had been taken against him by any authority as at the date of the trial. But even taking the Alleged Misdeeds at their highest, while certainly unfortunate, they were a matter between the Respondent and [JX]. To put it plainly, they were not the Claimant’s problem, and they did not relieve the Respondent of its obligations under the Contract.

  82. Second Issue: the Respondent repudiated the Contract

  83. [21] I turn to the Second Issue. I found that the Respondent’s conduct on 13 November 2025 cumulatively amounted to a repudiation of the Contract.

  84. [22] When the Claimant declined to accept the Revised Quotation, the Respondent’s response was to declare (a) that it would not complete the electrical works due under the Contract and would enter the Flat to strip out those already installed, (b) that it would not install the vinyl flooring required under the Contract, and (c) that it would place the renovation on hold (see [9] above). Those three positions, taken together, could only be understood as a refusal to carry on with the Contract. The Respondent was therefore in repudiatory breach.

  85. [23] The Claimant accepted that repudiation by conduct on 13 November 2025 when he changed the lock to the gate of the Flat and informed [CHT] of the same. Those acts brought all further works under the Contract to a halt and unequivocally communicated his acceptance of the Respondent’s repudiation.

  86. [24] It follows that I rejected the Respondent’s argument that the Claimant was the party in breach for changing the lock and thereby shutting out the Respondent’s subcontractors. The chronology paints a clear picture: the Claimant changed the lock only after, and in direct response to, [CHT]’s threat to trespass into the Flat and remove the electrical works which had already been installed. As fixtures, those works had become part of the Flat and therefore the Claimant’s property. It did not lie in the mouth of the Respondent to complain that the Claimant took reasonable steps to guard his own property against that very threat.

  87. [25] Before moving on, there was one further matter which merited comment. It was not strictly necessary for me to address it in order to dispose of the Second Issue because [CHT] did not raise it as a defence to the claim. He mentioned it only in passing at trial. His point was that the increase of $15,466.50 was occasioned by the Claimant’s own additions to, and removals from, the scope of works under the Contract at the meeting on 10 November 2025. The Claimant was therefore the author of the increase, and yet he refused to accept the Revised Quotation. In this way, [CHT] sought to lay the blame for the stoppage of the renovation works at the Claimant’s door. I did not accept this:

  88. (a) The short answer is that a contractual variation requires offer and acceptance, and must be supported by consideration (see Aero-Gate Pte Ltd v Engen Marine Engineering Pte Ltd [2013] 4 SLR 409 at [36]). The Revised Quotation was, at highest, an offer to vary the Contract, and the Claimant plainly did not accept it. There was accordingly no variation, and the Contract stood as it was. Put in practical terms, it was not open to the Respondent to name whatever price it wished and expect the Claimant to fall in line. The Contract bound both parties until there was a valid variation of it, and the Respondent could not bring one about on its own. That disposes of [CHT]’s assertion. If the Respondent had no right to insist on the Revised Quotation, it does not matter who was the author of the increase.

  89. (b) In any event, I found that the Respondent failed to prove that the increase was genuinely referable to any change in scope. [CHT] spent approximately an hour at trial working through his own figures in an attempt to explain how the increase of $15,466.50 came about. His explanations were broad-brush and convoluted. Having been given all that time, he was still unable to reconcile the increase against the changes to the scope of works. To state it plainly, the burden lay on the Respondent to substantiate its own figures, and it was not the place of this tribunal to do that work for it. I therefore did not accept that the Claimant was the author of the increase.

  90. [26] Given [CHT]’s inability to account for the increase, I found that the Claimant’s stated reason for rejecting the Revised Quotation rang true. That reason was that it was nothing more than an attempt by the Respondent to recoup the losses occasioned by the Alleged Misdeeds (see [9] above). Two matters bore that impression out:

  91. (a) The first is [CHT]’s own testimony that the Contract was a loss-making deal for the Respondent to the tune of approximately $32,000 because of the Alleged Misdeeds (see [7] above). The very shortfall the Claimant suspected the Respondent of trying to recover was one that [CHT] himself confirmed at trial. The Claimant’s impression was therefore not a matter of speculation on his part.

  92. (b) The second is the objective evidence tendered. In a WhatsApp voice message sent to the Claimant on 13 November 2025, which was professionally translated, [CHT] said:

  93. I want to tell you first, I won’t do this if you are like this, I can’t cover it back, I must charge you for the electricity, think about it, if you keep cutting everything, I can’t cover it back, I must charge you for the electricity, didn’t I tell you honestly, I’m just balancing the cost.

  94. [emphasis added]

  95. [27] [CHT]’s own words are telling. What he was doing was not pricing a varied scope of works – he was balancing the Respondent’s books, and looking to the Claimant to make up the shortfall. Charging for the electrical works, which the Respondent had agreed to provide free of charge, was only one of the levers it pulled. The other increases across the various line items in the Revised Quotation, which [CHT] could not reconcile, served the same purpose.

  96. Third Issue: the claim was allowed in full

  97. [28] I turn finally to the Third Issue. In short, I allowed the Claimant’s claim in full. However, that was not because he was entitled to a refund of the value of the Unfinished Works. I explain.

  98. [29] It is understandably intuitive for a lay customer in the Claimant’s position to frame his loss as a refund. He had paid the Respondent $21,450 for the Unfinished Works, that sum forming part of the $42,480 he transferred by 24 September 2025. He received nothing for it, and the Respondent made no refund. On that view, the money ought simply to be returned to him. But in the context of a contract of this kind, that is not how damages for breach are computed.

  99. Costs and disbursements

  100. Conclusion

  101. [33] For the foregoing reasons, I ordered the Respondent to pay the Claimant $20,275, which consisted of $20,000 plus $275 for disbursements, by 3 September 2026.

  102. [34] I conclude with two brief observations.

  103. [35] The first arises from the Respondent’s attempt to pass its own losses to the Claimant. A company that undertakes to renovate a home for a fee takes on the risk of delivering that renovation. That is precisely what it is being paid for. If difficulties arise within the company, for instance with an errant employee, agent, subcontractor or supplier, those are matters between the company and that party. However genuine and however serious such difficulties may be, they do not affect the customer’s entitlement under his contract with the company, and it cannot look to him to make good losses of its own.