Skip to content
Grounds publishedDecided 11 Apr 2012

High Court

Sato Kogyo (S) Pte Ltd and another v Socomec SA

Feedback & support

[2012] SGHC 76Case no. Suit No 422 of 200976 paragraphs

What happened, in plain English

There is no plain-English summary of this judgment yet.

Ask about this judgment

Grounds of decision

Official text from eLitigation

  1. Judith Prakash J:

  2. Introduction

  3. [1] This is a claim in tort for damage resulting from two fires that took place on the night of 27/28 June 2007. The second plaintiff, Singapore Telecommunications Limited (“SingTel”), is the lessee of the premises in which the fires took place. The first plaintiff, Sato Kogyo (S) Pte Ltd (“SKS”), was the main contractor employed by SingTel to carry out certain works on the premises. The defendant, Socomec SA, is the manufacturer of certain electronic items which were purchased in connection with the works. It is the plaintiffs’ case that the fires were caused by the malfunctioning of the defendant’s goods but this is denied by the defendant.

  4. Background

  5. Relationships between the parties and the Works

  6. [2] SingTel is the lessee of a building known as Kim Chuan Telecommunications Complex (the “Complex”). It leased the Complex for the purpose of containing a data storage facility which could be rented out to customers. SingTel subsequently (October 2006) employed SKS as its main contractor to undertake the construction, completion and maintenance of upgrading and fit out works (the “Works”) at the Complex so as to make it suitable for the intended purpose.

  7. [3] The Works consisted of additions and alteration works to the first, second, seventh, eighth and tenth storeys of the Complex. Among the things which SKS had to do were to supply, install, test and commission nine generator sets, four water cooled chillers, ten oil-immersed type transformers, high tension switchgears and eight Uninterruptible Power Supply (“UPS”) systems consisting of eight UPS units and ancillary electrical components.

  8. [4] The purpose of installing the UPS systems in the Complex was to prevent, in the event of a power failure from the main supply, loss of electrical power to the computer equipment that store the database. If a power failure were to occur, the UPS systems would immediately take over the supply of electricity to the computer equipment connected to the main power supply to ensure no loss of data in the computer equipment. The UPS systems basically consist of the UPS units, batteries, battery racks, battery protection boxes, cables and connectors linking the UPS units to the main power supply, the batteries, and computers storing the database.

  9. [5] The defendant is a well known and established manufacturer of UPS units in France. It has a subsidiary in Singapore, Socomec UPS Asia (S) Pte Ltd (“Socomec Asia”). In October 2006, SingTel appointed Socomec Asia as one of the subcontractors for the Works. Shortly thereafter, Socomec Asia ordered eight UPS units from the defendant for the purpose of installation in the Works as part of the UPS system. On 30 January 2007, the subcontract between SingTel and Socomec Asia was novated so that SKS replaced SingTel as the purchaser.

  10. [6] The consequence of all these arrangements was that there were contractual relationships between SingTel and SKS, between SKS and Socomec Asia and between Socomec Asia and the defendant. There were no contractual relations between SingTel and the defendant or between SKS and the defendant.

  11. [7] The main contract between SingTel and SKS contained an indemnification clause (cl 18(2)) which required SKS to indemnify SingTel “against any damage, expense, liability, loss, claim or proceedings due to injury or damage of any kind to any property real or personal (including property of [SingTel]) other than the Works”. The subcontract between SKS and Socomec Asia also contained an indemnification clause (cl 9.2) which required Socomec Asia to indemnify SKS “against any liability of [SKS] to indemnify [SingTel] under clause 18(2) of the Main Contract insofar as it may arise out of or in the course of or by reason of the carrying our of the Sub-Contract Works”.

  12. [8] It should be noted that as required under the main contract, SKS procured a Contractor’s All Risks Policy to cover the Works. This took effect on 1 November 2006 for the period from then to 16 October 2007. Among the co-insured under the policy were SKS, SingTel and Socomec Asia.

  13. Tests and installation of the UPS units

  14. [9] The eight UPS units supplied by the defendant were referred to in the proceedings as UPS 7-1 to UPS 7-8. Between 8 January 2007 and 18 January 2007, Automatic Tests were conducted on all eight UPS units at the defendant’s factory in France. It is not in dispute that UPS 7-8, the allegedly defective unit and cause of the two fires, passed the Automatic Test.

  15. [10] Between 14 and 18 January 2007, the specific Factory Acceptance Test (“FAT”) was conducted for UPS 7-7 in the defendant’s factory in France. It is not disputed that the specific FAT was not conducted for the other seven units, including UPS 7-8, although some readings from the Automatic Tests were incorporated into the FAT report for the UPS 7-8 and accepted by SingTel’s agent, Mr Goh Soon Huat (“Mr Goh”).

  16. [11] The eight UPS units were installed by Socomec Asia in Level 7 of the Complex with UPS 7-2, 7-4, 7-6 and 7-8 in the UPS room of the north room and UPS 7-1, 7-3, 7-5 and 7-7 in the UPS room of the south room. The north and south rooms are at opposite sides of Level 7 with the data banks in the centre and adjacent to each room.

  17. [12] The north room is divided into two “rooms” which open into each other – the UPS room which housed the four UPS units and the UPS bypass panel, and the battery room which housed the batteries, battery racks and battery protection boxes. The batteries, battery racks and battery protection boxes were supplied by third parties not connected to this action.

  18. [13] Each UPS unit was linked by four cables on overhead metal cable ladders to its own battery protection box in the battery room. From this box, eight cables were linked to its own battery in the battery room via cable ladders, ie, there were 48 cables in total above the four boxes. During the course of installation, several tests were conducted on the UPS units, the cables and the batteries.

  19. The fires

  20. [14] On 27 June 2007, representatives of HS Inspection Pte Ltd, accompanied by representatives of Socomec Asia and Hitachi Plant Technologies Ltd, conducted infrared thermal scanning tests on the 8 UPS systems. After completion of the tests, at or around 8.20pm, the same persons witnessed sparks from the UPS room in the north room, and heard cracking and loud sounds from the top of UPS 7-8.

  21. [15] Subsequently, several of those persons present heard popping sounds and other heard popping sounds and saw sparks followed by fire erupting in the battery bank in the north room. They ran out of the room and the fire brigade was summoned.

  22. [16] Two fires broke out at that time: a fire in UPS 7-8 which localised and died out on its own and a fire in the battery room (together the “27 June fires”). The fire brigade (“SCDF”) extinguished the fire in the battery room. They then proceeded to damp down the area of the fire. The SCDF used water to put out the fire and broke windows in order to ventilate the battery room.

  23. [17] In the early hours on 28 June 2007, there was a second fire (the “28 June fire”) in the battery room and the SCDF firemen who were on the scene had to douse the fire again.

  24. The claim and the defence

  25. [19] This action was started on 14 May 2009 by Tokio Marine in the names of SingTel and SKS claiming damages for the loss suffered by reason of the fires. In the statement of claim, the plaintiffs pleaded that the fires caused extensive damage to level 7 of the Complex including the four UPS units, the battery bank and other electronic and electrical components located there. The particulars of the damage were given as follows:

  26. (a) Electrical components inside the UPS 7-8 were damaged.

  27. (b) Electrical lighting, cables and fittings in the battery bank section were damaged.

  28. (c) Overhead cable trays and ceilings in the battery bank section were severely damaged and partially collapsed.

  29. (d) About 600 lead acid batteries were completely destroyed.

  30. (e) DC panels located in the battery bank section were severely damaged.

  31. (f) Other contents in the UPS section were damaged by sustained heat and smoke.

  32. (g) Other areas sustained heat and smoke damage.

  33. (h) Smoke damage to property in the 2 to the 6 storeys and 9 storey of the Complex.

  34. [20] The plaintiffs’ position is that their losses were caused by the fires which in turn were caused by the defective UPS 7-8. As the manufacturer of the UPS units, the defendant owed a duty of care to the plaintiffs not to damage their property by ensuring that the UPS units supplied to SingTel were fit for the purpose intended.

  35. [21] The defendant denies liability for the loss and damage claimed by the plaintiffs. It denies that it owes a duty of care to the plaintiffs and that it has breached its duty of care; it further denies that the damage was caused by the defendant’s breach. It alleges that in any event, the plaintiffs contributed to and/or aggravated the first and/or second fires and that there was a break in the chain of causation.

  36. [22] The trial of the action was bifurcated and I therefore heard evidence relating to liability only.

  37. The issues

  38. [23] The issues have been formulated slightly differently by each party but they can be rephrased as follows:

  39. (a) Whether the defendant owed a duty of care to SingTel and to SKS;

  40. (b) If so, whether the defendant had breached its duty of care by acting below the standard of care required of an ordinary skilled manufacturer;

  41. (c) Whether the fires were caused by a failure in UPS 7-8;

  42. (d) Whether the actions of the SCDF in breaking the windows of the battery room and letting oxygen in constituted a novus actus interveniens and caused the 28 June fire;

  43. (e) Whether there was contributory negligence on the part of SKS because it did not arm the FM 200 fire extinguishment system; and

  44. (f) Whether the plaintiffs are estopped from claiming that UPS 7-8 caused the fires.

  45. The Law

  46. [24] The elements of a claim in negligence are well established. These were restated by the Court of Appeal in Spandeck Engineering (S) Pte Ltd v Defence Science & Technology Agency [2007] 4 SLR(R) 100 (“Spandeck”) at [21]:

  47. [25] In Spandeck the Court of Appeal decided that the two-stage test of proximity and policy considerations should be adopted to determine the existence of a duty of care in all situations, whether the damage is physical damage or pure academic loss (at [71] and [72]). It also held that this test is to be approached with reference to the facts of decided cases although the absence of such cases would not be an absolute bar against a finding of duty (at [43] and [73]).

  48. Factual foreseeability

  49. [26] Before embarking on the two-stage test, the threshold requirement of factual foreseeability has to be satisfied. The defendant argued that it was not reasonably foreseeable that a defect in UPS 7-8 would cause loss to the plaintiffs because there were several safety protection mechanisms in the form of safety fuses in the design of the UPS units which would have operated. Additionally, as regards SKS, there was no factual foreseeability that a defect in the UPS would cause loss to SKS because the defendant did not know of the existence of SKS prior to the fires.

  50. [27] I do not accept the defendant’s argument. In my judgment, it was factually foreseeable that a defect in a UPS unit which resulted in a fire could cause loss to a legitimate ultimate user in whose premises the UPS unit was installed and who had other property in the vicinity of the UPS unit. The defendant would have been well aware that any ultimate purchaser of its UPS units would install the same in constructed premises which would also contain other fixtures and fittings. The UPS units were not intended to be used outdoors. The defendant would therefore have known that any defect in a UPS unit would possibly damage the property of the end user. The fact that the defendant had provided for safety fuses in the UPS units is irrelevant. If the safety fuses worked, then no fire would have resulted and no consequent physical damage to third parties’ property would be caused. It would, however, be easily foreseeable that if the fuses did not prevent the fire, the fire could damage other physical items in the vicinity of the UPS unit. It does not matter that the defendant was not aware of SingTel’s or SKS’ identity and had no contractual relationship with them. The defendant as a manufacturer of the UPS units which were electronic items providing an uninterruptible power supply could reasonably foresee the possibility of defective units leading to fires which would be capable of causing physical damage to the property of third parties.

  51. Duty of care

  52. Duty of care to SingTel

  53. [28] It has been settled since 1932 that a manufacturer owes a duty of care to the ultimate user, at least where a defective product would cause damage to the ultimate user’s property. See M’alister (Or Donoghue) (Pauper) v Stevenson [1932] AC 562 (more commonly known as “Donoghue v Stevenson”); Grant v Australian Knitting Mills, Limited [1936] AC 85 (Privy Council) (“Grant”). This is established in this case since the UPS units were manufactured by the defendant and the ultimate user was SingTel. SingTel as the lessee of the Complex was the owner of the Complex and had a claim for the physical damage caused to the Complex. It was also the ultimate owner of the UPS system comprising the UPS units, the batteries, the cables and other components that were damaged in the fires.

  54. [31] The difference in approach was made clear in The “Sunrise Crane” [2004] 4 SLR(R) 715, in which the Court of Appeal found a duty of care where a transporter of nitric acid, when transferring a cargo of contaminated nitric acid to a second vessel, failed to inform the crew of the second vessel of the nature of the cargo. The second vessel was made of mild steel and incapable of carrying nitric acid, and the nitric acid caused physical damage to the second vessel. The court distinguished PT Bumi at [35] – [37]:

  55. [32] In the PT Bumi-type situation, the court is obliged to examine the parties’ contractual relations to determine if the parties had chosen to allocate loss in a specific manner. Where the defective product causes physical damage to the ultimate user’s own property, the duty of care is well-established and there is no need to go into long analysis based on the two-stage test. In such cases, the existence of contractual remedies is irrelevant unless there is a contractual exemption clause authorised by the ultimate user of the product to displace the pre-existing duty of care on the part of the manufacturer.

  56. [33] In Grant, Lord Wright stated at 105:

  57. [34] The court in PT Bumi cited Henderson v Merrett Syndicates Ltd [1994] 3 WLR 761 at 790 (“Henderson”), where Lord Goff of Chieveley stated:

  58. [35] No such contractual exemption clause exists here. The contractual obligations on SKS to indemnify SingTel and on Socomec Asia to indemnify SKS do not indicate a clear intention to exempt the defendant from tortious liability.

  59. Duty of care to SKS

  60. [36] SKS was not the ultimate owner of the UPS units or any of the components making up the UPS system. It was the main contractor who had contracted to procure and install the UPS system and carry out the rest of the Works. The description in the statement of claim of the loss sustained by SKS was, however, somewhat ambiguous and gave the impression that SKS was making a claim for pure economic loss.

  61. [37] SKS submitted that its claim was not a claim for pure economic loss. Its claim arose out of physical damage to property of which it was a bailee and therefore it had a legal right to sue in tort for such damage. SKS emphasised that under the main contract with SingTel it was solely responsible for the Works until the Works were completed to the satisfaction of the architect. SKS relied on cll 3(3) and 20(2) of the main contract which provide as follows:

  62. [38] SKS argued that it was clear from the clauses cited above that as between SingTel and itself, the parties had agreed that SKS was to bear the risk of loss or damage to the Works. As SKS was in sole and exclusive possession of the sections of the Complex where the Works were to be carried out and was also in possession of all the components of the Works which had been brought into those areas of the Complex, SKS was bailee of all property in the Works until the Works were handed over to SingTel upon completion. The documents that SKS had produced substantiated the assertion that the Works were handed over to SingTel by SKS on various dates after the fires. at the time of the fires, SKS was in possession of Level 7 of the Complex. It was accordingly the bailee of the chattels that were damaged by the fires being, primarily, the UPS units, the cables, cable ladders, batteries, battery protection boxes and bypass units. As the main contractor and as bailee in possession of the Works, until the Works were completed and handed over to SingTel, SKS retained possession and had the right to claim against any third party who negligently damaged the property in the Works.

  63. [39] The defendant argued that SKS could not bring an action in negligence for physical damage to property that it had no legal ownership or possessory title over and it could not bring an action for economic loss arising out of physical damage to another person’s property. It relied on the case of Leigh & Sullivan v Aliakmon Shipping (“The Aliakmon”) [1986] AC 785 at 809 (“The Aliakmon”) for the proposition that to make a claim a claimant must have either the legal ownership of or a possessory title to the property concerned at the time when the loss or damage occurred and it is not enough for him to have had contractual rights in relation to such property which had been adversely affected by the loss or damage of the property. In that case, the claimant was the purchaser of steel that was damaged while on board the defendant’s vessel. At the time of the damage, the property in the steel still belonged to the seller though it was at the claimant’s risk under the terms of the sale contract. The claimant failed in its attempt to recover damages from the defendant as it was held to have no proprietary interest in the steel but only a contractual interest.

  64. [41] The defendant argued that the facts of Nacap were very similar to those of the present case and following that case, physical possession of goods owned by some other party for example by a contractor engaged for construction purposes, does not render the contractor an owner or give it possessory title such as to entitle the contractor to make a claim for loss of or damage to the goods. A person with “possessory title” would be a person who was in a position comparable to that of the legal owner for example because he had some kind of security such as a lien. In this case, the defendant submitted, the position of SKS was essentially identical to the plaintiffs in Nacap. Therefore, since SKS had confirmed that its entire claim arose in respect of items that belonged to SingTel, it could not claim for the loss sustained in making good that damage.

  65. [42] The facts of the present case are not quite akin to those of Nacap much less The Aliakmon where the plaintiffs had no possession of any sort. In Nacap, the court said that the possession given to the plaintiffs there was a limited possession. This was not the situation here. Condition 10(2) of the Articles and Conditions of Building Contract between SKS and SingTel provided that from the commencement date of the Works, SKS would be entitled to “free and uninterrupted possession of the whole ... of the Site” in which the Works were to be conducted. That could not be limited possession. Such free and uninterrupted possession was duly given to SKS and, as shown by documents produced in evidence, SKS retained such full possession at the time of the fires. Whilst SKS might not have had possessory title to the site itself, it was definitely the bailee in possession of all moveable goods within the site until possession was handed back to SingTel.

  66. [43] It cannot be disputed that a substantial proportion of the damage caused by the fires was caused to the goods forming part of the UPS system. SKS was in sole and exclusive possession of these goods for the purpose of carrying out the Works. I note that the defendant argued that there was no evidence that the damaged items repaired by SKS were all goods as opposed to premises. However, the fact that some of the loss was not directly related to the damage sustained by the goods would not change SKS’s entitlement to sue as bailee of damaged goods. Whether it could also recover economic loss as a consequence of having to undertake repairs to real property of which it was not (and could not be) a bailee would be a question of remoteness of damage to be decided when the damages came to be quantified. Such question could not affect SKS’s title to sue as bailee when the goods bailed had been physically damaged.

  67. [44] I accept the submission made by SKS that as the main contractor and as bailee in possession of the Works, until the Works were completed and handed over to SingTel, SKS retained possession and had the right to claim against any third party who negligently damaged the property in the Works. The law on the right of a bailee to sue in such circumstances is well settled.

  68. [45] In Jet Holding Ltd v Cooper Cameron (Singapore) Pte Ltd [2005] 4 SLR(R) 417 it was held at [59] that possession on the part of a bailee would give a complete title and entitled the bailee to damages for loss or injury to the property itself. This pronouncement was based on The Winkfield [1902] P 42 where there was a collision between the steamship “Mexican” and the steamship “Winkfield” which resulted in the loss of the “Mexican” with a portion of the mail which she was carrying at the time. The question was whether the postmaster general could recover for the value of letters and parcels which were in his custody as bailee and lost while on board the “Mexican”. Collins MR held at 54:

  69. Breach of duty

  70. [46] The next issue to consider is whether the defendant breached its duty of care to the plaintiff. The law determining the relevant standard of care is the Bolam test which was laid down in Bolam v Friern Hospital Management Committee [1957] 1 WLR 582 with “the Bolitho addendum” as decided by the Court of Appeal in JSI Shipping (S) Pte Ltd v Teofoongwonglcloong [2007] 4 SLR(R) 460 (“JSI Shipping”) where VK Rajah JA said that the Bolam test had been qualified by the case of Bolitho v City and Hackney Health Authority [1997] 4 All ER 771 such that the evidence of experts must have “a logical basis” (JSI Shipping at[49]). As a result, the test to be applied is whether the standard of care displayed in any particular situation met the standard of the ordinary skilled man exercising and professing to have the special skill required in that situation. In determining this issue, the evidence from a body of experts as to whether the standard has been fulfilled, must have a logical basis.

  71. [47] The eight UPS units manufactured by the defendant were subjected to two different tests: UPS 7-7 was subjected to the Factory Acceptance Tests (“FATs”) while UPS 7-1, 7-2, 7-3, 7-4, 7-5, 7-6 and 7-8 were only subjected to the Automatic Test. The plaintiffs submitted that as the defendant knew that it had not conducted the FAT on UPS 7-7, it should not have allowed that unit to leave its factory. By shipping UPS 7-8 to Singapore without carrying out the FAT on that unit, the defendant committed a negligent act. UPS units are special equipment meant for specific purposes and the defendant must have been aware of the risks involved if a defective unit was shipped to the end-user.

  72. [48] The question that arises is whether the defendant fulfilled its standard of care by subjecting UPS 7-8 to the Automatic Test alone and by-passing the FAT.

  73. [49] The defendant argued that it had satisfied the standard of care of an ordinary skilled UPS manufacturer. This was because UPS 7-8 had been subjected to and had passed the Automatic Test. Further, the consultant employed by SingTel had confirmed that he had received the test results for all eight UPS units six weeks before they were delivered and had found the results and readings in these tests to be acceptable to him. The defendant pointed out that readings in the Automatic Tests for UPS 7-8 were incorporated into the FAT. The defendant submitted that the Automatic Test alone was sufficient to show that the defendant had satisfied the standard of care of an ordinary skilled UPS manufacturer in respect of UPS 7-8. Mr Goh was aware that the test for UPS 7-8 was different from that for UPS 7-7 when he approved the tests prior to the shipping of the units. His approval of the tests results of the Automatic Tests showed, the defendant submitted, that it had exercised the requisite standard of care.

  74. [50] No expert evidence was adduced as to the proper procedures and checks that need to be carried out by a UPS unit manufacturer. In this situation, the only evidence as to what is required of such manufacturer comes from the procedures and checks adopted by the defendant itself.

  75. [51] The defendant’s working document shows that the FATs are conducted as “proof of the stringent Quality Assurance programme of the manufacturing of the UPS system in the factory” (Document entitled “Uninterruptible Power Supply Installation: Section 7 – Work Tests, Site Tests and Commissioning”). It also represents that the following FATs shall be conducted:

  76. (a) UPS functional test with fast response output voltage waveform measurement and recording with 100% load including one step 100% load transfer

  77. (b) Input voltage and current harmonic measurement on 0%, 25%, 50%, 75%, 100% load

  78. (c) Efficiency measurement and UPS losses measurement on 0%, 25%, 50%, 75%, 100% load

  79. (d) Over load and short circuit test

  80. (e) Output voltage measurement and recoding for non-balanced load condition.

  81. The document also states that all tests shall be carried out under a load power factor of 0.8 leading, 0.9 leading, unity, 0.9 lagging and 0.8 lagging; five different situations.

  82. [52] The defendant admitted that while the report for UPS 7-7 (which was subjected to the FATs) was far more detailed and spanned 115 pages, the reports for the other UPS units including UPS 7-8 (which were only subjected to the Automatic Test) were brief and only spanned six pages. The FATs were far more stringent tests and importantly included the overload and short circuit test, which was not present in the Automatic Test. Results from those two tests would have been relevant to whether or not the UPS units would fail in a situation of current overload or short circuit. In the absence of expert evidence and where the defendant itself prescribes two types of tests which differ in the level of detail tested and the care taken, the defendant must be obliged to carry out the test which fulfils a higher standard of care. It does not lie in the defendant’s mouth to claim that the less stringent test is sufficient.

  83. [53] I do not accept the argument that Mr Goh’s acceptance of the test results for all the units absolved the defendant from its breach of duty. The evidence was that Mr Goh did not witness the tests carried out. He was therefore in no position to confirm the accuracy of the test results presented to him. In any event, any failing on the part of Mr Goh could perhaps found an argument of contributory negligence on the part of the plaintiffs. It cannot absolve the defendant from its own failure to live up to the standard of care required. The defendant breached its duty in carrying out the full range of tests required. That breach remains a breach whether or not Mr Goh accepted the tests results.

  84. Cause of the damage

  85. [54] The question here is whether there was a sufficient causal link between the defendant’s breach of duty and the damage suffered by the plaintiffs. The plaintiffs’ theory is that the fire was caused by the failure of the Insulated Gate Controlled Bipolar Transistor (“IGBT”) within the UPS unit that controlled the battery charging current. The defendant says that the cause of the fires is not strictly ascertainable, but they were not caused by UPS 7-8. Further, the fires were most likely caused by the leakage of current in the battery room, likely from the batteries and/or the cables.

  86. [55] In the discussion that follows, it must be remembered that the defendant was the supplier of only one component, albeit, a major component, of the UPS system. The main components of this system were the UPS units manufactured by the defendant, the battery bank and the cables. The batteries and the cables were supplied by Socomec Asia who purchased them from third parties.

  87. [56] The burden of proof as to causation lies with the plaintiffs. It is well established that the trial judge may accept the explanation of either the plaintiffs or of the defendant; or, if both explanations are improbable the judge may decide that the action fails because the plaintiffs have failed to discharge their burden of proof. See Rhesa Shipping Co SA v Edmunds (The Popi M) [1985] 1 WLR 948, endorsed in Cooperatieve Centrale Raiffeisen-Boerenleenbank BA (trading as Rabobank International), Singapore Branch v Motorola Electronics Pte Ltd [2011] 2 SLR 63.

  88. [57] The plaintiffs’ position all along was that the fires were caused by a defective UPS unit. In the course of the trial, however, they changed their case on what the exact defects were that led to the fires. At the start of the trial, the statement of claim averred in para 7 that the fires were caused by the defective UPS 7-8 and gave the following particulars of that averment:

  89. [58] The particulars quoted above were based on the “Investigation Report on the Kim Chuan Telecommunication Complex Fire on the 27th June 2007” dated January 2009 and prepared by Dr Jimmy Chen Wie Ying of Snowflake Technology Pte Ltd (“Dr Chen”). In January 2011, Dr Chen prepared a “Further Report on the Kim Chuan Telecommunication Complex Fire on the 27th June 2007”. In mid February 2011, just as this trial started, the plaintiffs applied to substitute Dr Keith J Cornick (“Dr Cornick”) as their expert witness in place of Dr Chen on the basis that Dr Chen was physically unable to give evidence. I allowed this application and Dr Cornick then affirmed an affidavit to which he exhibited the two reports prepared by Dr Chen. He testified that these reports had been prepared by Dr Chen in consultation with him and he adopted the reports as being his as well. Dr Cornick also referred to a Response Report dated 7 December 2010. He affirmed that he had prepared this Response Report as a reply to a report prepared by Dr Richard Fletcher (“Dr Fletcher”), the defendant’s expert. In Dr Fletcher’s report, he had opined that on balance it was more likely that the underlying cause of the fire was associated with equipment in the battery room rather than with UPS 7-8. Dr Cornick affirmed that in his opinion, the underlying cause of the incident was in UPS 7-8.

  90. [59] Dr Cornick took the stand on 21 February 2011. He was subjected to a very detailed cross-examination. In the course of the cross-examination, Dr Cornick agreed that the plaintiffs’ theory of failure in the one phase rectifier arm in the rectifier SCR bridge was wrong. In re-examination, Dr Cornick was taken through that theory again to confirm what he had said in cross-examination. He then confirmed that in the light of the further evidence he had been shown, it was no longer his view that the initial fire started because of an electrical component failure associated with one arm of the rectifier SCR rectifier bridge. He further confirmed that it was no longer his view that the failure in the one phase rectifier arm was of an intermittent nature and the rectifier arm was not able to withstand the reverse voltage intermittently resulting in intermittent short circuit across the battery terminals. Thirdly he confirmed that what was stated in paras 7.3 and 7.4 of the particulars cited in [57] above no longer constituted his view.

  91. [60] Having totally resiled from the particulars in paras 7.2 to 7.4 of the statement of claim, Dr Cornick then went on to say that he maintained that the batteries were overcharged and that the reason for this was that the IGBT controlled circuit had failed. Dr Cornick then stated how he believed the IGBT had initiated the fires. As a result of the change in Dr Cornick’s evidence, the plaintiffs applied to amend the statement of claim by amending the particulars in para 7 to reflect what he had said during re-examination. I allowed the application.

  92. [61] Consequently, at the close of the trial, the particulars to para 7 of the statement of claim read as follows:

  93. [62] The defendant submitted that the plaintiffs had not come close to discharging their burden of proof on a balance of probabilities in relation to the new theory of the failure in the IGBT. It said there was no evidence before the court emanating from the plaintiffs’ expert that the IGBT failed by itself on a stand-alone basis (as opposed to the failure of the IGBT being caused by a chain of events as had been propounded in relation to the earlier theory) such as to cause the batteries to be overcharged and to cause the fires in the battery room and the localized fire in UPS 7-8.

  94. [63] To repeat, the plaintiffs’ current claim is that the failure of the IGBT caused “a heavy current of a value well above that recommended, i.e. above 400 amps [to flow] into the battery charger circuit and the battery. This current was not enough to blow the battery fuses but sufficient to overcharge the UPS 7-8 batteries”. It is essential to note that the plaintiffs describe the IGBT failure as a “low overcurrent condition”, i.e. a current that was too low to blow the fuses gradually caused the batteries to overheat and caused the 27 June and the 28 June fires. Having considered the evidence, I find that the plaintiffs have not shown that the fires were more likely caused by a failure at UPS 7-8.

  95. [64] The 27 June fires, which occurred at 8.20 pm, consisted of two separate fires, the first occurring in UPS 7-8 itself and the second occurring in the battery room. It is not disputed that the UPS 7-8 fire was localized and died out on its own. The plaintiffs must show that the battery room fire was caused by the failure of UPS 7-8. At this point, it should be noted that even in the statement of claim, the plaintiffs do not explain the causal nexus between the UPS failure and the battery room fire. It is only said there that “the first fire started because of an electrical component failure” in the IBGT. Rather, the plaintiffs’ theory of the batteries overheating is apparently in relation to the 28 June fire that occurred at 2.10 am, more than five hours after the earlier fires. When the plaintiffs came to make their submissions, however, their stance seems to have changed as the closing submissions seek only to establish the theory of batteries overheating as the cause of the 27 June fires, not the 28 June fire.

  96. [65] The available objective evidence does not support the plaintiffs’ case with regard to the 27 June fires. First, the plaintiffs’ expert, Dr Cornick, stated that such overheating would take “many minutes” or “20 minutes”. In his report he had stated that the heating of the batteries was not a short term action. He also said that the fuses meant to protect the batteries did not blow for a long time but let in enough overcurrent to the batteries to overcharge them and to initiate battery failures. However, the evidence given by eyewitnesses who were working or present in the North Room immediately before the 27 June fires makes clear that the explosions in the battery room occurred almost at the same time as, or a few seconds after, sparks were seen at UPS 7-8. When this evidence was put to Dr Cornick, he agreed that there was a discrepancy between the timing of what the witnesses saw and the alleged IGBT failure. He also had to accept that he could not disagree with what the witnesses had seen.

  97. [66] Secondly, the plaintiffs’ theory relies heavily on the photographic evidence of (allegedly) the bulging batteries connected to UPS 7-8, and Dr Cornick’s claim that the theory of batteries overheating was proven by how there were “bubbles in the battery that have started to appear bursting”, and how the “connections have been [pushed] out at the top of the internal pressure”. This photographic evidence was put forward to establish overheating of the batteries connected to UPS 7-8. However, Mr Li Bang Hao, the photographer, testified that the photographs Dr Cornick relied on were of batteries located next to the cable ladder in the North Room. The diagram of the North Room confirms those batteries were then connected to UPS 7-6, not to UPS 7-8. Thus there is no direct evidence that the plaintiffs can rely on to show that the batteries of UPS 7-8 had overheated. Further, the internal overheating of the batteries connected to UPS 7-6 is physically incompatible with the notion that the 27 or 28 June fires was caused by the overheated batteries of UPS 7-8. A fire deriving from the batteries of UPS 7-8 would not have caused internal overheating of the batteries of UPS 7-6; a more likely explanation is that the fires were caused by internal malfunction of the batteries themselves. In addition, the fact that the batteries of UPS 7-8 remained almost completely intact, while other batteries in the battery room were burnt to a cinder, is logically inconsistent with the notion that the fire originated from the batteries of UPS 7-8.

  98. [67] Thirdly, the plaintiffs’ theory of overheated batteries relies heavily on another piece of physical evidence, viz the damaged battery charger chokes in the battery banks of UPS 7-8. Dr Cornick maintained that the damage was caused by overheating while the defendant’s expert, Dr Fletcher, maintained that the damage was caused by electric arcing. In my judgment, Dr Fletcher’s opinion bears more weight because he had physically examined the battery charger choke in situ, and peeled back the outer layer of the foil to discover no damage to the inner layer of the foil (which would indicate internal overheating). On the other hand, Dr Cornick reached his conclusion without having physically examined the battery charger chokes. Further, the battery charger chokes were fixed to the casing of UPS 7-8. Therefore if they had been overheating for some time as propounded by Dr Chen and Dr Cornick, this overheating would have, in Dr Fletcher’s opinion, been obvious to the various engineers working around the panel as discoloration or blistering of paint. The engineers from HS Inspection who were on the site at the time did not say that they had detected any such thing. Rather, the evidence of the persons who had conducted infra-red thermal testing of the unit shortly before the incident was that the thermal scanning showed no hot-spots inside UPS7-8.

  99. [68] In their closing submissions the plaintiffs sought to piggy back on certain evidence given by Dr Fletcher to help found their new theory of the cause of the fires. While some of the evidence that Dr Fletcher gave was helpful to the plaintiffs’ case, it could not by itself fill in all the gaping holes in the same. The plaintiffs’ big problem was that they came to court with one theory which was completely discredited on the stand and then had to cast about for another theory to support their case. This second theory was only enunciated in re-examination and was put forward by a witness who at the beginning of his testimony had held tightly to the first theory as being the correct explanation for the fires. Yet in a matter of a day or two, when forced to discard a theory which had been worked on for 2 years, he was able to come up, on the hop as it were, with an alternative explanation which put the blame squarely on the UPS unit. I did not find this satisfactory or convincing. In their original case, the plaintiffs had never relied on the IGBT as a component that failed on a stand-alone basis. It was always part of the “chain” starting from the alleged failed SCR rectifier. Thus there was no report before me to substantiate, and give the technical basis for, the allegation that the IGBT had failed on its own and thereby caused the overcharging of the batteries. Dr Fletcher agreed that the IGBT failed but not that it failed on its own. Rather he opined that it could have resulted from a short circuit of the battery circuit connected to the UPS unit arising from an initiating fault in the battery.

  100. [69] I have found that the plaintiffs have not established that the fires were caused by a fault in UPS7-8 for which the defendant can be made responsible. I do not have to go on to find what the actual cause of the fires was. Dr Fletcher’s opinion was that given the extent of damage, which was particularly severe in the battery room, it was not possible to determine the cause of the fire on the basis of the remaining physical evidence. He therefore went on to consider which of the two possible causes was more likely: that the fire in the battery room resulted from a fault in the UPS or that the fault in the UPS resulted from a fault in the battery room that also caused the fires. He concluded that it was relatively unlikely that the fault in the battery room that led to the fires was caused by the short-lived failure in the UPS and that it was more likely that a gradual failure of the battery equipment associated with UPS 7-8 went unnoticed but placed additional stress on the UPS ultimately resulting in the failure of the charger circuit. The resulting short circuit in the UPS might then have exacerbated the developing fault in the battery leading to the battery room ‘explosions’ and the rapid onset of fire. I make no finding on Dr Fletcher’s theory as it is not necessary for the decision in this case. Dr Fletcher was, however, a more convincing witness than Dr Cornick.

  101. Other issues

  102. [70] Having found that the plaintiffs have not been able to prove that the damage resulted from a defect in UPS 7-8, there is no need for me to deal in detail with the remaining issues. I will, however, express my views on them briefly.

  103. Novus actus interveniens

  104. [71] The first of these issues is whether the actions of the SCDF in breaking the windows on the 7th storey constituted a novus actus interveniens sufficient to relieve the defendant of liability if the same had been found. The assertion by the defendant was the acts of the SCDF in fighting the 27 June fire aggravated that fire in the battery room and caused the 28 June fire in the battery room.

  105. [72] The principles to be applied in deciding this issue were set out in Michael Jones, Anthony Dugdale (eds), Clerk & Lindsell on Torts (Sweet & Maxwell, 20 Ed, 2010) (“Clerk & Lindsell”) at p 128 as follows:

  106. The same text at p 138 also states that a deliberate act of rescue will virtually never constitute a novus actus unless the reaction of the rescuer is so grossly foolish and disproportionate to the danger as in effect to be a “sham” rescue.

  107. [73] In the present case, addressing the issues set out in Clerk & Lindsell, results in the conclusion that the acts of the SCDF cannot be consider a novus actus that could relieve the defendant of liability for its wrongdoing. First of all, the intervening conduct of the SCDF in fighting the fire could not render the initial defect in the UPS unit (on the assumption one had been found) which initiated the fire merely a part of the history of events. The actions of a professional fire fighting force in dealing with the 27 June fires cannot be considered as an unreasonable response or an effort that went beyond what was required by the circumstances. The reaction to the fire was a consequence properly attributable to the initial wrongdoing and SCDF’s acts did not eclipse that wrongdoing. From the time of the 27 June fires, damage was sustained by the batteries, the UPS units and certain other components. If SCDF’s actions in fighting the 27 June fires were not sufficient to totally deal with the problems caused by that fire and may instead have aggravated the 28 June fire, that does not mean that the 28 June fire arose solely from the SCDF’s actions. The technical evidence did not support such a conclusion. In any case, it cannot be said that the action of the SCDF in coming to the rescue and in taking the actions it considered necessary to douse the fires were grossly foolish and disproportionate to the danger caused by the fires notwithstanding that the methods that the SCDF used may not have been wholly suitable for an electrical fire.

  108. Estoppel by convention

  109. [74] The next issue is estoppel by convention. The defendant submitted that the plaintiffs were estopped under this doctrine from alleging that it was UPS 7-8 which was responsible for causing the fires. The factual background to this assertion was a meeting that took place between the plaintiffs, Socomec Asia and the defendant’s representative (via video link) on 10 August 2007. At that meeting, the defendant alleged, the parties had agreed that the cause of the fire was unascertainable but, most likely that it was the batteries or cables which caused the fire. Subsequent to that meeting, the plaintiffs redesigned the location of the battery protection boxes by reverting to the original design ie each box was placed at the end of each of its batteries so that any leakage of current and/or fire would not spread to the other three UPB systems via the cables or cable ladder. The plaintiffs submitted that by not putting the battery protection boxes back in the positions they were in prior to the fire the plaintiffs had taken the view that relocating the boxes would result in less risk of a fire and/or spread of the fire.

  110. [75] The plaintiffs disagreed that there had been a consensus at the meeting held on 10 August 2007. Mr Goh who was present at that meeting had said in evidence that he was not asked whether he agreed or disagreed with the comments of the defendant’s engineers on the cause of the fire. He said that he was at the meeting merely to listen to what the defendant’s engineers had to say about the possible cause of damage and was not asked to make a comment. Whilst the plaintiffs’ then expert, Professor Liew Ah Choy (“Professor Liew”), was also present at the meeting, as he did not give evidence at the trial, the court ought to reject the defendant’s references to Professor Liew’s purported agreement with their views.

  111. [76] I do not think it is necessary for me to decide on this dispute of facts as in any event, it is my view that estoppel by convention would not apply here. For estoppel by convention to apply, the parties must have agreed on certain statements of facts, the truth of which has been assumed by the parties to be the basis of the transaction and it must be unjust to allow one party to go back on the agreed facts. Even if at the time of the meeting the plaintiffs’ representatives had agreed that the cause of the fire was unascertainable, that was an opinion held at a particular time and not a statement of fact. Secondly, the defendant has not shown me why it would unjust to allow the plaintiffs to go back on such opinion and sue them on the basis of subsequently acquired knowledge or evidence. There is nothing before me to show any change of position on the part of the defendant by reason of the meeting of 10 August 2007 that would make it unfair to allow the plaintiffs to pursue this action if indeed they were able to establish that UPS 7-8 was the cause of the fire.

  112. Contributory negligence

  113. [77] The final issue is that of contributory negligence. The defendant submitted that whatever the root cause of the fires, the damage caused by the 27 June fire could have been substantially reduced if the plaintiffs had armed the FM200 fire extinguishment system (“the FM200 system”) on the day in question prior to carrying out the scheduled infra-red thermal testing.

  114. [78] It was not disputed that the FM200 system had been installed but was not armed on 27 June 2007. The plaintiffs explained that the system was not armed at the material time because if it had been activated by a fire, it would have asphyxiated the persons who were then present in the UPS room to carry out the infra-red thermal testing of the UPS units. Secondly, the Works were still in a “construction phase”.

  115. [79] Dr Fletcher took the view that if the FM200 system had been armed, it could have detected the slowly developed fire in the battery room at the time the infra-red thermal test were being done and it could have limited the development of the fire. Dr Cornick thought that the batteries of UPS 7-8 could not have been saved but that the system might have saved much damage to the remaining batteries and most certainly the fabric of the battery room. Whilst he expressed the view that there was a possibility that someone may be asphyxiated, Dr Cornick agreed that if there had been a delay mechanism in the FM200 system, no one would be asphyxiated by the operation of the same.

  116. [80] Having considered the facts, I think the plaintiffs were negligent in not arming the FM200 system before they commenced their infra-red thermal imaging work on 27 June 2007. They would have known that such testing would generate high heat and therefore there may be a risk of fire. The explanation regarding the danger of asphyxiation was not convincing since it was a term of the main contract that the FM200 system had to have a delay mechanism. Dr Fletcher studied the specifications of the Dupont FM200 system which SKS had installed. He reported that this document made it clear that the FM200 system was entirely safe for use in areas where people were working and therefore there was no reason why the system should not have been armed while commissioning tests were being carried out. I accept this evidence. The damage would have been reduced if the system had been operating. If I had found the fire to be caused by UPS 7-8, I would have held that due to contributory negligence on their part, the plaintiffs should recover only 75% of the damage sustained.

  117. Conclusion