Skip to content
Grounds publishedDecided 20 Jan 2009
Contents

High Court

Teo Chin Lam v Lead Management Engineering & Construction Pte Ltd

Feedback & support

[2009] SGHC 23Case no. DC Suit 3286/2007, RAS 77/200827 paragraphs

What happened, in plain English

There is no plain-English summary of this judgment yet.

Ask about this judgment

Grounds of decision

Official text from eLitigation

  1. [1] This case was an appeal from the District Courts on the issue of whether the doctrine of res judicata applied to proceedings between the same parties arising out of the same subject matter resolved in an earlier suit.

  2. [2] Teo Chin Lam (“the plaintiff”) is the sole-proprietor of Singecon Engineering & Construction which business is the welding, fabrication and installation of piping works. Lead Management Engineering & Construction Pte Ltd (“the defendant”) is a construction company which at the material time had been awarded a contract at Jurong’s Manufacturing Building and Warehouse Zone II (“the MSD project”).

  3. [3] The plaintiff was the defendant’s subcontractor for seven projects between June 2006 and February 2007. One of these projects was to supply the defendant with labour (primarily fitters and welders) for the fabrication and installation of piping works for the MSD project.

  4. [4] Between 19 January 2006 and 22 September 2006, the defendant issued seven purchase orders to the plaintiff totalling $709,950.12 for the MSD project. The first purchase order was a lump sum of $400,000 for the subcontract while the remaining six purchase orders were for modifications, additional, commissioning and miscellaneous works for the MSD project.

  5. [5] The defendant claimed it had paid the plaintiff $640,050 in respect of all the works done (this was not disputed by the plaintiff). The defendant further alleged that the plaintiff then submitted a final claim in the sum of $66,885.35 for the balance due under the seven purchase orders. The plaintiff’s invoice no. 07/001/LM dated 20 January 2007 for $66,885.35 contained the description Final Claim for MSD Project No. MSDS5491 (“the Final Claim”).

  6. [6] The plaintiff commenced Suit No. 370 of 2007 (“the first action”) against the defendant on 15 June 2007 claiming the sum of $394,447.12 for the seven projects of which the sum of $68,678.12 was for work done for the MSD project. In the statement of claim, in relation to the MSD project, the plaintiff’s invoices were variously dated between 18 June 2006 and 3 December 2006.

  7. [8] On 15 October 2007, the plaintiff commenced DC Suit No. 3286 of 2007 (“the second action”) against the defendant. In the (amended) statement of claim, he claimed $188,151.00 in respect of five invoices (“the invoices”) issued between 3 July 2006 and 4 October 2006 for providing labour for the MSD project, pursuant to an oral contract he had allegedly made with the defendant’s assistant general manager Yeo Peng Kiat Avery (“Yeo”) in June 2006.

  8. [9] The defendant in its defence disputed the claim on the basis that it had paid the plaintiff his claim for the MSD project in the first action in full and final settlement. It was contended that the invoices were not contracted for nor were they supported by the actual work done and/or they were double claims. In the further alternative, the defendant contended that the plaintiff was estopped from claiming under the invoices as the pleadings in the first action constituted a representation by the plaintiff that all his claims and rights relating to the MSD project were limited to the sum of $68,678.12 which the defendant had paid in full. The defendant then counterclaimed against the plaintiff a setoff of $177,967.00 as a further alternative.

  9. [10] In his reply and defence to the counterclaim, the plaintiff asserted that the invoices related to additional works that Yeo (who denied) had requested and for which the defendant was to (but failed) to issue purchase orders. The plaintiff alleged that it was expressly agreed between him and Yeo that the plaintiff would charge for all modification works based on the agreed hourly rates for workers and based on the number of hours worked as reflected in the workers’ timecards. The plaintiff denied the defendant was entitled to a setoff as claimed.

  10. [11] The plaintiff deposed in his affidavit of evidence-in-chief (“the AEIC”) that he did not want to include the invoices in the first action in the absence of purchase orders from the defendant. He had not been paid by the defendant for more than a year, he was in desperate need of funds and he did not want the first action to be delayed with a defence by the defendant that there were no purchase orders to support the invoices.

  11. [12] In the AEIC of the defendant’s executive director Ng Cheng Chuan (“Ng”) it was explained that the defendant delayed payment of the “Final Claim” to the plaintiff for the MSD project over concerns that the plaintiff was overcharging for the other projects which were the subject of the claim in the first action. Heng Swee Keng Roy (“Heng”) the defendant’s project manager filed an affidavit denying the plaintiff’s allegation in [10]. In an earlier affidavit filed to oppose the plaintiff’s application for Order 14 judgment, Yeo had similarly denied he had made any oral agreement with the plaintiff. Yeo had also denied that the claim in the second action was due to the defendant’s failure to issue purchase orders, pointing out the plaintiff required the defendant to issue blanket purchase orders before he would commence work in order to avoid the very defence the plaintiff was alleging could have been raised by the defendant. Blanket purchase orders in the sums of $100,000 and $50,000 were indeed issued by the defendant to the plaintiff.

  12. The proceedings below

  13. [13] The second action proceeded to trial after the plaintiff decided not to pursue his application for summary judgment. (His counsel was of the view that the defendant’s show cause affidavits raised triable issues). On the first day of trial (11 June 2008), the defendant’s counsel withdrew his client’s counterclaim and as a preliminary issue, applied to strike out the second action on the basis of res judicata. As counsel for the plaintiff had no prior notice of the striking-out application, it was adjourned to another date.

  14. The decision

  15. [15] As was stated by the district judge in her grounds of decision (“GD”) at [2008] SGDC 227, the issue is whether the doctrine of res judicata in the extended sense propounded by Wigram VC in Henderson v Henderson [1843-1860] All ER 378, applied so as to bar the plaintiff from making his claim under the invoices. In allowing the Appeal, I had disagreed with the district judge who held that it did not.

  16. [16] I will not repeat all the other facts extracted from the AEICs which were set out in the GD of the court below. Neither is there a need to refer in extenso to all the cases cited by the court below as I am in full agreement with the applicability of those cases.

  17. [17] What is noteworthy is that the court below (at para 20 of the GD) appeared to be greatly influenced by the plaintiff’s allegation that the defendant had failed to pay him $394,447.12 for more than a year. That would mean that the court ignored the defendant’s explanation given in Ng’s AEIC (see [12]) as to why the defendant withheld payment on the Final Claim. In this regard, the court below had referred to the following extract from p 31 of Lord Bingham’s judgment in Johnson v Gore Wood & Co (a firm) [2002] 2 AC 1 where he said:

  18. On the plaintiff’s own case however, this allegation was untrue. The particulars of the plaintiff’s invoices attached to the statement of claim showed he received periodic payments from the defendant up to invoices dated 18 November 2006, which was seven months before the first action was filed on 15 June 2007. By way of example, I refer to the plaintiff’s invoice no. 06/111/LM dated 3 November 2006 for the MSD project. It was paid and so too were four other invoices for projects S5569 and 5543 for sums totalling $65,602.25 (invoices nos. 06/108/LM, 06/112/LM, 06/113/LM and 06/116/LM). It bears remembering that the plaintiff had received before 15 June 2007 payments totalling $640,050 from the defendant for the MSD project.

  19. [18] Far more significant was the lack of reference by the district judge to the plaintiff’s invoice no. 07/001/LM dated 20 January 2007 (for the Final Claim) except in passing (at para 19 of the GD). Clearly, she must have overlooked its significance. Her comment there that ‘it was not disputed that the defendant were aware of the claimed invoices” is neither here nor there. It was precisely for that reason that the defendant thought the plaintiff’s claim on the invoices had been withdrawn or subsumed when he presented his Final Claim. It bears noting that in the first action (see [6]), the plaintiff’s claim for the MSD project was on invoices dated 18 June 2006 and ending on 3 December 2006. That being the case, it was reasonable of the defendant’s three representatives particularly Ng (see [12]) to think (as invoice no. 07/001/LM was dated 20 January 2007), that the Final Claim was the last invoice the plaintiff was issuing for the MSD project, bearing in mind that the plaintiff’s services to the defendant ended in February 2007. Consequently, the defendant assumed (not unreasonably) that their payment of the Final Claim was in full satisfaction of the plaintiff’s work for the MSD project, until he commenced the second action.

  20. [19] The court below had placed too much weight on the plaintiff’s excuse for not including the invoices in the first action viz that he did not want to face a defence of no purchase orders from the defendant. If that was indeed the plaintiff’s thinking, it was incorrect. Even if the invoices in the second action had been included in the first action, the defendant may not necessarily have raised such a defence, successfully or at all. Further, the court could still have awarded summary judgment to the plaintiff on that part of his claim for which he could rely on purchase orders (on the ground of no triable issue) and allowed the (disputed) invoices not supported by purchase orders to go to trial. Such a practice is not uncommon.

  21. [20] However, it was also equally possible that had the plaintiff included the invoices in the first action, that the defendant may well not have voluntarily paid the plaintiff the sum of $68,678.12. The plaintiff’s omission of the invoices from the first action and his commencement of the second action irreversibly prejudiced the defendant. His conduct in issuing the Final Claim and omitting the invoices from the first action led the defendant to believe he had no more claims for the MSD project. It would be an abuse of process at the very least even if res judicata does not apply, to allow the plaintiff to relitigate any claim pertaining to the MSD project.

  22. [21] In his AEIC (at para 37) the plaintiff deposed that he did not agree with Heng’s reduction of the sums in his 23 quotations from $301,164 to $211,956.10 although he acknowledged the reduced sum. What he did not say was he had notified the defendant of his disagreement without which the defendant would have believed he accepted the reduced sum by his acknowledgement. In para 39 of his AEIC, the plaintiff deposed:

  23. while in para 40 he said:

  24. [22] The plaintiff’s statement in his para 40 was incorrect. He had been paid $68,678.12 which was more than the Final Claim sum; the payment was based on the total unpaid invoices set out in his statement of claim in the first action for the MSD project; the excess sum paid amounted to $1,792.77 ($68,678.12- $66,885.35). Counsel for the defendant had informed this court that the difference between the two figures was due to a discount of $3.014.77 plus $96. Unfortunately, the figures still did not tally. I note the defendant’s submission that the defendant could not ascertain the total value of invoices issued by the plaintiff for the MSD project but that the plaintiff presented claims of not less than $896,783.12 in value.

  25. The law

  26. [23] I turn next to the main authorities cited by the parties in particular Henderson v Henderson (supra [15]) and Johnson v Gore Wood & Co (a firm) (supra [17]). The plaintiff had argued that Henderson v Henderson did not apply as there was no adjudication by the court on the merits in the first action. I do not disagree that in Henderson v Henderson, Wigram VC referred to the prerequisite of adjudication by a court of competent jurisdiction for the doctrine to apply. At p 381 he said:

  27. [25] In Greenhalgh v Mallard [1947] 2 ALL ER 255, Somervell LJ said (at p 257H).

  28. [26] The Court below had quoted the following extract (at pp 32-33) from Lord Bingham’s judgment in Johnson v Gore Wood & Co where he addressed the issue of whether res judicata applied in the case (he held it did not):

  29. [27] The court below had also cited Goh Nellie v Goh Lian Teck [2007] 1 SLR 453 and quoted the following extract from Sundaresh Menon JC’s decision (at [41]):

  30. [28] Earlier, the same view was expressed by our Court of Appeal in Lee Hiok Tng (personal capacity) v Lee Hiok Tng (representative capacity) [2001] 3 SLR 41 where Chao Hick Tin JA, at [25] after citing Wigram V-C’s dictum in Henderson v Henderson (see supra [23]) said:

  31. Conclusion

  32. [29] In the light of all the authorities cited above, it would be an abuse of process under the extended doctrine of res judicata, to allow the plaintiff to maintain the second action.

  33. [30] It would be unfair to the defendant as directed by the court below, for the question of issue estoppel relating to the invoices to proceed to trial. The plaintiff should not in effect be given a second bite of the cherry, when his previous conduct in presenting the Final Claim led the defendant to believe the balance of his entire claim for the MSD project was encapsulated in that last invoice and prompted the defendant to pay him $68,678.12 in the first action. The plaintiff’s explanation relating to his deliberate omission of the invoices from the first action was unsatisfactory and upon closer examination, when verified against his claim documents in both actions, was unlikely to be true.