Regulation 11

of Building Control (Buildability and Productivity) Regulations 2011

Regulation 11

Departure and deviation from approved plans

Amended byS 819/2019 wef 15/12/2019S 335/2022 wef 30/04/2022

Subregulation 1

Despite regulation 18 of the Building Control Regulations 2003 (G.N. No. S 666/2003), a person who wishes to make any change to the following must apply to the Commissioner of Building Control for approval under section 5A(1) of the Act:

(a)

the approved buildability detailed design and implementation plan of any building works;

(b)

a Deemed Acceptable Proposal or Project Productivity Improvement Plan submitted to the Commissioner of Building Control;

(c)

the approved plan of the building works if the change affects —

(i)

the buildable design score; or

(ii)

if the plan contains an alternative solution, whether the requirements of the alternative solution will be met.

Subregulation 2

Amended byS 819/2019 wef 15/12/2019S 335/2022 wef 30/04/2022

The application referred to in paragraph (1) must —

(a)

be accompanied by —

(i)

the amended buildability detailed design and implementation plan;

(ii)

the amended plan of the building works;

(iii)

the amended Deemed Acceptable Proposal; or

(iv)

the amended Project Productivity Improvement Plan,as the case may be, showing clearly the departures or deviations; and

(b)

bear an endorsement, by every specified person in respect of the building works, that —

(i)

where the plans of the building works do not contain any alternative solution — the building works are designed such that the buildable design score of the building works is not less than the minimum buildable design score; and

(ii)

where the plans of the building works contain any alternative solution — the building works are designed to meet either the requirements of the deemed acceptable solution or the requirements of the open solution.