Singapore legislation
Regulation 8
of Building Control (Buildability and Productivity) Regulations 2011
Regulation 8
Submission of constructability score
Subregulation 1
Every builder referred to in regulation 5 shall submit the constructability score to the Commissioner of Building Control at the time of application for permit to carry out structural works under section 6(1) of the Act or within such time after the grant of the permit as the Commissioner of Building Control may, in his discretion, allow.
Subregulation 2
The submission of the constructability score referred to in paragraph (1) shall be accompanied by —
a constructability implementation plan of the building works which shall include the floor plan of each storey of the building with respect to the building works, including the basement storeys, the roof plan of the building and the elevation plans and sectional plans of the building which clearly mark out —
the types of construction techniques and processes, plant, equipment, innovative methods and systems and materials which will be used for that storey, roof or building, as the case may be; and
details on the extent of adoption of each construction technique and process, plant, equipment, innovative method and system or material; and
such document or information as the Commissioner of Building Control may determine.