Singapore legislation
Regulation 10
Regulation 10
Duties of builder
Subregulation 1
Any builder who erects a temporary building must ensure that —
the building works are carried out in accordance with the approved plans given to the builder by the professional engineer under regulation 9(2)(d); and
the building works are carried out in accordance with the conditions of the preliminary approval in respect of the temporary building.
Subregulation 2
Where a lightning protection system is required to be installed in the temporary building, the builder must —
ensure that a professional electrical engineer supervises the installation of the lightning protection system; and
no later than 7 days after completing the building works in respect of a temporary building, submit, to the owner of the temporary building, the professional electrical engineer’s certificate of supervision in respect of the installation of the lightning protection system.
Subregulation 3
A builder who contravenes paragraph (1) or (2) shall be guilty of an offence.