Official text
Subregulation 1
These Rules are the Housing Developers (Amendment) Rules 2026 and, except for rules 8(i), (j) and (l), 10(c), (e), (f) and (i) and 13(a), (b), (c), (d), (e), (f), (i), (j) and (l), come into operation on 31 December 2026.
Subregulation 2
Rules 8(i), (j) and (l) and 10(c), (e), (f) and (i) come into operation on 1 June 2027.
Subregulation 3
Rule 13(b) is deemed to have come into operation on 1 October
Subregulation 4
Rule 13(a), (c), (d), (e), (f), (i) and (j) is deemed to have come into operation on 31 December 2021.
Subregulation 5
Rule 13(l) is deemed to have come into operation on 1 July
reg 2025
reg 2Amendment of rule 2
In the Housing Developers Rules (R 1) (called in these Rules the principal Rules), in rule 2 —
replace the definitions of “Commissioner of Buildings” and “Commissioner of Building Control” with — “ “Commissioner of Building Control” and “temporary occupation permit” have the meanings given by section 2(1) of the Building Control Act 1989; “Commissioner of Buildings” has the meaning given by the definition of “Commissioner” in section 2(1) of the Building (Strata Management) Act 2004; “competent authority” and “planning permission” have the meanings given by section 2 of the Planning Act 1998;”; (b) after the definition of “Registrar of Titles”, insert — “ “relevant authority” means any person empowered to approve plans for development of any land or plans relating to the construction of any building under any written law;”; and (c) delete the definition of “temporary occupation permit”.
reg 3Replacement of rule 2A
In the principal Rules, replace rule 2A with — “Prescribed amount of paid-up capital, deposit and security 2A. For the purposes of section 5(1)(a) and (b) of the Act, the Controller must not grant a sale licence to a housing developer to carry out or undertake a housing development described in the first column of the Second Schedule unless —
if the housing developer is the sole applicant for the sale licence —
if the housing developer is a company —
the housing developer has at least an issued and paid‑up capital of the amount specified in the second column of the Second Schedule opposite the housing development; or (B) the housing developer lodges with the Controller a deposit or security of at least the amount specified in the third column of that Schedule opposite the housing development; or (ii) if the housing developer is an individual, a group of persons, a partnership, a society or a limited liability partnership — the housing developer lodges with the Controller a deposit or security of at least the amount specified in the third column of the Second Schedule opposite the housing development; and (b) if the housing developer makes the application for the sale licence jointly with one or more other housing developers —
if every housing developer applying for the sale licence is a company —
each of the housing developers has at least an issued and paid‑up capital of the amount specified in the second column of the Second Schedule opposite the housing development; or (B) all of the housing developers jointly lodge with the Controller a deposit or security of at least the amount specified in the third column of that Schedule opposite the housing development; or (ii) in any other case — all of the housing developers jointly lodge with the Controller a deposit or security of at least the amount specified in the third column of the Second Schedule opposite the housing development.”.
reg 4Amendment of rule 3
In the principal Rules, in rule 3 —
renumber the rule as paragraph (1) of that rule; (b) in paragraph (1)(b), after “tenure of the land”, insert “(including in the case of a leasehold estate, the commencement date and term of the lease)”; (c) in paragraph (1)(c), before “the expected date”, insert “the date of the grant of the temporary occupation permit or the date of the issue of the certificate of statutory completion (as the case may be) for all units of the housing project or, if the temporary occupation permit or certificate of statutory completion has not been granted or issued,”; (d) in paragraph (1)(e), replace “and Mukim/Town Subdivision.” with “, Mukim/Town Subdivision and street name;”; (e) in paragraph (1), after sub‑paragraph (e), insert — “(f) if the advertisement contains information on the layout of the units in the housing project as approved by the competent authority under the Planning Act 1998 — a drawing of all balcony screens approved, as part of the planning permission granted for the housing project, for installation in the balcony of a unit of the housing project, showing the specifications and dimensions of each approved balcony screen; (g) if the advertisement is in the form of a sale brochure or is published on the licensed housing developer’s website — all of the following: (i) if applicable — a statement indicating that the sale of uncompleted units by at least one relevant person had previously been suspended during the period of years immediately before the relevant licence date of the housing project; (ii) if applicable — a statement indicating that at least one relevant person had previously been disqualified from participating in any sale of State land (on which housing accommodation may be developed) under the Government Land Sales Programme during the period of 3 years immediately before the relevant licence date of the housing project; (iii) if applicable — a statement indicating that the housing project will be subject to the requirements of Tier 3 of CONQUAS as at least one relevant person had completed a housing project with a significant number of major defects, or that had been assigned Band 6 under CONQUAS during the period of 3 years immediately before the relevant licence date of the housing project; (iv) a statement indicating the total number of housing projects completed by every relevant person during the period of 6 years immediately before the relevant licence date of the housing project (called in this sub‑paragraph the designated class of housing projects), the total number of housing projects from the designated class of housing projects that were assigned Band 4, 5 or 6 under CONQUAS, and the total number of housing projects from the designated class of housing projects that did not undergo any CONQUAS assessment.”; and (f) after paragraph (1), insert — “(2) In this rule — “CONQUAS” means the Construction Quality Assessment System administered by the Building and Construction Authority established under section 3 of the Building and Construction Authority Act 1999; “Government Land Sales Programme” means a programme under which State land is sold by or on behalf of the Government for development through a public selection process; “related corporation” has the meaning given by section 6 of the Companies Act 1967; “relevant licence date”, in relation to a housing project, means the date on which a housing developer is first granted a licence to carry out or undertake development of the housing project; “relevant person”, in relation to a housing project, means any of the following persons: (a) the licensed housing developer (X); (b) a director or related corporation of X; (c) if X is a company — a substantial shareholder of X, or a director or related corporation of a substantial shareholder of X; “State land” has the meaning given by section 2 of the Singapore Land Authority Act 2001.”.
reg 5Amendment of rule 6
In the principal Rules, in rule 6 —
renumber the rule as paragraph (1) of that rule; and (b) after paragraph (1), insert — “(2) An advertisement of a housing project must not contain any statement, information, visual image or material relating to any part of the development of the housing project or a unit in the housing project unless the licensed housing developer of the housing project has obtained the approval of all relevant authorities for that part of the development of the housing project or unit.”.
reg 6Amendment of rule 7
In the principal Rules, in rule 7(a), after “information”, insert “, visual image”.
reg 7Replacement of rule 8
In the principal Rules, replace rule 8 with — “Booking fee 8.—
A licensed housing developer must, before granting an option for the purchase of a unit in a housing project to an intending purchaser, require the intending purchaser to pay a booking fee or make any other payment by whatever name it is called, that is not less than 5% but not more than 10% of the purchase price of the unit. (2) A licensed housing developer (or the licensed housing developer’s agent or nominee) must not offer or give any benefit (in the form of payment, rebate, reimbursement, allowance, discount, voucher or other benefit (whether monetary or otherwise)) to any intending purchaser to be used to offset any booking fee payable or paid by the intending purchaser.”.
reg 8Amendment of rule 10
In the principal Rules, in rule 10 —
in paragraph (4), replace sub‑paragraph (a) with — “(a) provide the intending purchaser with the documents and information relating to the unit and the housing project, and information on the licensed housing developer’s track record, as described in, and in accordance with the requirements of, Form 3 in the First Schedule;”; (b) in paragraph (5), replace “Where” with “In addition to the requirements under paragraph (4), where”; (c) in paragraph (5)(a), replace “his inspection” with “the intending purchaser’s inspection free of charge at a place, and during the hours, specified by the licensed housing developer”; (d) in paragraph (5)(a)(i), after “Commissioner of Buildings”, insert “under section 11 of the Building (Strata Management) Act 2004”; (e) in paragraph (5)(a), after sub‑paragraph (ii), insert — “(iii) a copy of a drawn‑to‑scale floor plan of the storey on which the strata lot of that unit is located that —
corresponds exactly with all plans approved by all relevant authorities for that unit and that housing project; and (B) includes the location of all communal facilities on that storey;”; (f) in paragraph (5)(b), replace “such documents” with “the documents mentioned in sub‑paragraph (a)”; (g) in paragraph (5)(b), delete “and” at the end; (h) in paragraph (5), after sub‑paragraph (b), insert — “(ba) notify the intending purchaser of the share value allotted to the unit against —
the total share value of the housing project; and (ii) the total share value of the units in the housing project the purchasers of which will be entitled to the exclusive benefit of the limited common property (if any) of the housing project; and”; (i) in paragraph (5)(ba), delete “and” at the end; (j) in paragraph (5), after sub‑paragraph (ba), insert — “(bb) if the licensed housing developer’s application for planning permission for the housing project is made under the Planning Act 1998 on or after 1 June 2027 — notify the intending purchaser of the maximum rate approved by the Commissioner of Buildings (as mentioned in section 18(1) of the Building (Strata Management) Act 2004) for the calculation of the charges for the management and maintenance of each of the following: (i) the common property of the housing project; (ii) the limited common property (if any) of the housing project; and”; (k) in paragraph (5)(c), replace “sub‑paragraphs (a) and (b)” with “sub‑paragraphs (a), (b) and (ba)”; (l) in paragraph (5)(c), replace “and (ba)” with “, (ba) and (bb)”; and (m) after paragraph (5), insert — “(6) For the purpose of this rule and rule 11, an option to purchase a unit in a housing project includes any contract, agreement or arrangement that grants or purports to grant a person a right to be given an option to purchase a unit in the housing project. (7) In this rule, “communal facilities” includes a lift, staircase, mechanical and electrical services room, refuse chute, refuse chute chamber and service duct.”.
reg 9Amendment of rule 14
In the principal Rules, in rule 14 —
in paragraph (1)(c), replace “the Commissioner of Building Control or other relevant authorities” with “all relevant authorities”; and (b) in paragraph (2), replace “the developer’s” with “the licensed housing developer’s”.