Public Utilities (Protection of Water Pipes Infrastructure) Regulations 2017 · As enacted · Part 2 · Obligations Relating to Specified Activity
13. Construction survey following completion of specified activity
Feedback & supportUpon the completion of any specified activity in a part of a water pipe corridor, the contractor of the activity must within such time as may be specified by the Board —
carry out or cause to be carried out a construction survey to establish whether the water supply system which runs through that part of the water pipe corridor is damaged or adversely affected by the activity; and
submit a copy of the report of the construction survey to the Board.
A contractor who contravenes paragraph (1) shall be guilty of an offence.
Subregulation 1
Upon the completion of any specified activity in a part of a water pipe corridor, the contractor of the activity must within such time as may be specified by the Board —
carry out or cause to be carried out a construction survey to establish whether the water supply system which runs through that part of the water pipe corridor is damaged or adversely affected by the activity; and
submit a copy of the report of the construction survey to the Board.
Subregulation 2
A contractor who contravenes paragraph (1) shall be guilty of an offence.