Regulation 10
Regulation 10
Application for permit to carry out engineering works
Subregulation 1
An application to the Authority for a permit to carry out engineering works within a railway corridor or railway protection zone as part of a development that is required for the purpose of regulation 9(1) must —
be made and signed by a qualified person appointed under regulation 11(1)(a) or (b)(ii) to supervise the engineering works under the development; and
be accompanied by the following:
where the engineering works are part of a development of land for which the written permission of the competent authority is required under the Planning Act 1998, a copy of that valid written permission or provisional permission;
an engineering plan for the engineering works involved in the development;
the notice of approval given by the Authority in approving the development proposal for the development;
if the development involves building works — the notice of approval given by the Authority in approving the building proposal for the building works;
any other declaration, information, instrument, plan or document that the Authority requires to decide on the application.
Subregulation 2
The items mentioned in paragraph (1)(b) must be prepared and signed by a qualified person.