Regulation 11
Authority’s approval deemed to be revoked if works are not carried out
of Street Works (Works on Public Streets) Regulations
Subregulation 1
Where —
the Authority has granted an application made under regulation 5; and
the applicant does not commence the works within 28 days of the date approved by the Authority for the commencement of the works,the approval of the Authority for the applicant to carry out the works shall, unless the Authority directs otherwise, be deemed to have been revoked at the expiry of the 28 days.
Subregulation 2
Where for any reason an applicant is unable to commence the works on the date approved by the Authority for the commencement thereof, the applicant shall forthwith notify the Authority in writing.