Singapore legislation

Regulation 3

of Environmental Protection and Management (Prescribed Regulated Goods) Order 2022

Regulation 3

Regulated goods for supply

The following goods are regulated goods for the purposes of section 40D(1)(a) of the Act:

(a)

any air‑conditioner described in Part 1 of the First Schedule, from (and including) the date specified opposite that air‑conditioner, but not if —

(i)

the air‑conditioner is a second‑hand air‑conditioner; or

(ii)

the air‑conditioner (not being a second‑hand air‑conditioner) —

(A)

was imported into or manufactured in Singapore before 1 October 2022, and is supplied between 1 October 2022 and 30 September 2023 (both dates inclusive);

(B)

is supplied pursuant to an agreement entered into before 31 March 2022; or

(C)

is supplied between 1 October 2022 and 30 September 2023 (both dates inclusive) pursuant to an agreement entered into on or after 31 March 2022 but before 1 October 2022;

(b)

any chiller described in Part 1 of the Second Schedule, from (and including) the date specified opposite that chiller, but not if —

(i)

the chiller is a second‑hand chiller; or

(ii)

the chiller (not being a second‑hand chiller) —

(A)

was imported into or manufactured in Singapore before 1 October 2022, and is supplied between 1 October 2022 and 30 September 2023 (both dates inclusive);

(B)

is supplied pursuant to an agreement entered into before 1 October 2022 and is not a substitute chiller; or

(C)

is supplied pursuant to a warranty in the agreement under which a chiller mentioned in sub‑paragraph (A) or (B) is supplied, as a replacement of the same brand and model as that chiller;

(c)

any refrigerator described in Part 1 of the Third Schedule, from (and including) the date specified opposite that refrigerator, but not if —

(i)

the refrigerator is a second‑hand refrigerator; or

(ii)

the refrigerator (not being a second‑hand refrigerator) —

(A)

was imported into or manufactured in Singapore before 1 October 2022, and is supplied between 1 October 2022 and 30 September 2023 (both dates inclusive);

(B)

is supplied pursuant to an agreement entered into before 31 March 2022; or

(C)

is supplied between 1 October 2022 and 30 September 2023 (both dates inclusive) pursuant to an agreement entered into on or after 31 March 2022 but before 1 October 2022.