Skip to content

Part 3 · Registration of Premises as Major Hazard Installation

13. Duty to notify of stoppage, etc.

Feedback & support
(1)

The occupier of a registered major hazard installation must notify the Commissioner, in the form and manner that the Commissioner requires, if —

(a)

the occupier intends to permanently decrease the quantity of a dangerous substance present or likely to be present in the premises of the registered major hazard installation such that the premises no longer fall within the description of a major hazard installation in the Second Schedule, not less than 14 days before decreasing the quantity of the dangerous substance; or

(b)

the occupier intends to cease occupation or use of the premises as a major hazard installation, not less than 14 days before ceasing to occupy or use the premises.

(2)

[Deleted by S 434/2024 wef 01/06/2024]

Subregulation 1

The occupier of a registered major hazard installation must notify the Commissioner, in the form and manner that the Commissioner requires, if —

(a)

the occupier intends to permanently decrease the quantity of a dangerous substance present or likely to be present in the premises of the registered major hazard installation such that the premises no longer fall within the description of a major hazard installation in the Second Schedule, not less than 14 days before decreasing the quantity of the dangerous substance; or

(b)

the occupier intends to cease occupation or use of the premises as a major hazard installation, not less than 14 days before ceasing to occupy or use the premises.

Subregulation 2

[Deleted by S 434/2024 wef 01/06/2024]

Report

Part 4

Duties of Occupier of Registered Major Hazard Installation

Part 5

Miscellaneous

Schedules