The developer of a project must convene such design‑for‑safety review meetings as are necessary to —

(a)

identify all foreseeable design risks in the project; and

(b)

discuss how each of the foreseeable design risks can be eliminated or reduced.

(2)

A developer must ensure that each design‑for‑safety review meeting is attended by all the relevant designers and contractors appointed under regulation 5(1), 9(6)(a) or 10(2)(a) or (3)(a).

Subregulation 1

The developer of a project must convene such design‑for‑safety review meetings as are necessary to —

(a)

identify all foreseeable design risks in the project; and

(b)

discuss how each of the foreseeable design risks can be eliminated or reduced.

Subregulation 2

A developer must ensure that each design‑for‑safety review meeting is attended by all the relevant designers and contractors appointed under regulation 5(1), 9(6)(a) or 10(2)(a) or (3)(a).