Workplace Safety and Health (Construction) Regulations 2007 · As enacted · Part X · Demolition
70. Preparation of demolition work
Feedback & supportBefore commencing any demolition work in a worksite —
all glass and claddings on the exterior of the building to be demolished shall be removed; and
all gas, electric, water, steam and other supply lines shall be shut off and capped.
Where it is necessary to maintain any power, water, gas or electric lines during demolition in a worksite, such lines shall be so re-located or protected with substantial coverings so as to protect them from damage and to afford safety to every person.
Subregulation 1
Before commencing any demolition work in a worksite —
all glass and claddings on the exterior of the building to be demolished shall be removed; and
all gas, electric, water, steam and other supply lines shall be shut off and capped.
Subregulation 2
Where it is necessary to maintain any power, water, gas or electric lines during demolition in a worksite, such lines shall be so re-located or protected with substantial coverings so as to protect them from damage and to afford safety to every person.