Regulation 4

of Electric Vehicles Charging (Requirements for Building Works and Electrical Work) Regulations 2023

Regulation 4

Prescribed information and documents to demonstrate completion of works under section 64(5) of Act

For the purposes of section 64(5)(a) of the Act, the prescribed information and documents, for the purpose of demonstrating that the works covered by the proposals and plans approved under section 64(3) of the Act in respect of a development have been completed, are all of the following endorsed by a qualified person appointed by the developer of the development:

(a)

an as‑built single line diagram, with the electrical load provided for the purpose of charging electric vehicles in the parking places of the development clearly indicated on that diagram;

(b)

an as‑built car park plan, with the number of charging points and the power rating of any EV charger associated with each charging point clearly indicated on that plan;

(c)

a list of all of the EV chargers installed within the development and the respective registration codes for those EV chargers assigned by the LTA under section 20(1)(a) of the Act;

(d)

photographs that show clear and unobstructed views of all of the following within the parking places of the development:

(i)

areas where the EV chargers are installed;

(ii)

every EV charger that is installed, with the registration mark issued by the LTA under section 20(1)(c) of the Act showing the registration code of the EV charger affixed to that EV charger;

(iii)

the electrical infrastructure installed for the supply of a minimum electrical load under section 64(1)(a) of the Act.