General Division of the High Court

Pure Group (Singapore) Pte Ltd v Siong Ann Engineering Pte Ltd

Feedback & support

[2023] SGHC 279Case no. District Court Appeal No 13 of 202310 paragraphs

What happened, in plain English

There is no plain-English summary of this judgment yet.

Ask about this judgment

Grounds of decision

Official text from eLitigation

  1. [1] This case in Siong Ann Engineering Pte Ltd v Pure Group (Singapore) Pte Ltd [2022] SGHC 73 (“Siong Ann Engineering”) was remitted to the district court for the determination of two issues of fact. The appellant, Pure Group (Singapore) Pte Ltd was a company in charge of a project converting a theatre into a restaurant and nightclub (“the Project”) in Marina Bay Sands (“MBS”). Mr Jonathan Peter Coney (“Mr Coney”) was the project manager and former general manager of the appellant. Mr Coney was assisted by Mr Tan Boon Chin (“Mr Tan”), a senior project manager in the appellant’s office in Malaysia, seconded to Singapore to assist with the project. The respondent Siong Ann Engineering Pte Ltd was one of the sub-contractors for the project. Mr Wong Chian Kok (“Mr Wong”) is the business and development manager of the respondent.

  2. [2] The dispute concerns the design, supply, and installation of a temporary ramp (“Ramp Works”). After discussions between the appellant and respondent, the respondent prepared the construction materials for the Ramp Works and delivered them to the work site. Then, Mr Coney abruptly told Mr Wong to stop work. A dispute arose as to how the respondent was to be paid for work done up to the delivery of the materials. No agreement could be reached, and the respondent filed Adjudication Application No. SOP/AA435 of 2018 for payment. The adjudicator determined that the appellant has to pay the respondent $123,897.77 for work done. The money was paid.

  3. [4] The relevant terms and conditions of the agreement are set out as follows:

  4. [7] As for the second milestone, the appellant says that the respondent was required to procure the approval of Arup Singapore Pte Ltd (“Arup”), the structural engineer for the Project, before the fabrication and installation of the Ramp Works. The appellant says that it had not waived this requirement, and there is no dispute that the respondent did not procure Arup’s approval. Therefore, since Arup’s approval was not obtained prior to the fabrication of materials for the Ramp Works, the second milestone cannot be said to have been completed by the respondent, notwithstanding the delivery of materials to the worksite.

  5. [8] In contrast, the respondent says that there is no requirement in the agreement that requires Arup’s approval to be obtained before the respondent is paid for the second milestone. According to the respondent, it could proceed with the fabrication works while seeking Arup’s approval. Moreover, the respondent says that there is also no evidence that the materials delivered to the worksite were not suitable for the Ramp Works. The respondent acknowledges that although Arup’s approval remained an important part of the Ramp Works, the failure to obtain Arup’s approval only went towards affecting the fulfilment of milestone three, the remaining “20% upon installation [being] completed”. This was a payment which the respondent had not claimed from the appellant.

  6. [10] Reading the communications between parties show that the parties were not concerned with getting Arup’s approval before the fabrication of materials (outside of the agreement). The urgency of the short time frame in which the works were needed to be completed had clearly made this, at best, a secondary concern. Mr Chia submitted that the emails sent by Mr Tan to Mr Wong (on 17 January 2018 and 2 February 2018) were evidence that Arup’s approval was required before the fabrication of materials. However, those emails must be read in context with the subsequent emails that signalled a change in the appellant’s position. For instance, while Arup’s approval was still being sought, and while discussions were ongoing about that issue, on 6 February 2018, Mr Wong had emailed Mr Tan stating that the respondent would “immediately fabricate the structural steelworks and deliver to site for installation”. Despite this being different from the respondent’s earlier instructions about Arup’s approval being required, no protest was forthcoming from Mr Tan. On 8 February 2018, Mr Tan had emailed Mr Wong, instructing him to ensure that “the steel materials [are] ready for your fabrications- installed by 23 Feb 2018”. Mr Wong had acknowledged this and replied that the respondent would “start to prepare the steelworks materials first ready for site installation”. Likewise, Mr Coney messaged Mr Tan on 9 February 2018 and told him to proceed with the Ramp Works. This was despite approval not having been obtained from Arup yet.

  7. [11] Taking into account the entirety of the communications between the appellant and the respondent, it is clear to me that by 8 February 2018, it was a common understanding between parties that the respondent would proceed with the fabrication of materials for the Ramp Works first, even though Arup’s approval had not yet been obtained. Presumably, this was because of the nature and urgency of the short timelines involved.

  8. [12] Turning to the next issue of whether the respondent had breached the contract, and if any damages were payable to the appellant if such a breach had occurred. The appellant says that the respondent had failed to achieve the milestones under the agreement and had, therefore, “failed to earn the contract price stipulated therein”. According to the appellant, the materials delivered by the respondent “could not be used” and were in fact not used, since Arup’s approval was not obtained. Alternatively, the appellant claims that the respondent breached the agreement by “failing to deliver materials which could be used for the construction of the [Ramp Works] and/or in not completing the installation of the [Ramp Works]”.

  9. [13] The respondent denies the allegation of its breach, and says that it was the appellant, in its email dated 22 February 2018, who stopped the Ramp Works. The respondent also points to its repeated requests (six attempts in March and April 2018) to resume the Ramp Works in various subsequent emails, and WhatsApp messages to Mr Coney — all of which were ignored by the appellant. Counsel for the respondent, Mr Tan Jin Yong, submitted that having ignored the respondent’s repeated requests to resume the Ramp Works, the appellant cannot now blame the respondent for not completing the Ramp Works.

  10. [14] I agree with Mr Tan. From the emails and the WhatsApp messages to Mr Coney, it is clear that the respondent had made every effort to resume the Ramp Works. This was the best the respondent could do, given that the appellant had stated clearly to the respondent in its 22 February 2018 email to “please do not do any further work on this until we discuss these works”. In this connection, I am unable to accept that Mr Coney only asked the respondent to suspend the physical works (i.e. the installation of the ramp) on-site, and that he did not direct the respondent to stop efforts at trying to obtain Arup’s approval. This position is untenable based on the email evidence. Hence, had the respondent been allowed to continue and Arup’s approval eventually obtained after the second milestone, there would not have been any case for the appellant to reject the work, and claim for damages for a breach of the agreement.