Singapore legislation

Regulation 13

of Electric Vehicles Charging (STRIDES Digital Pte. Ltd. — Vehicle-to-Grid Charger Trial) Rules 2026

Regulation 13

Duty to disconnect, remove and shut down specified EV chargers on end of approved trial

Subregulation 1

The specified person must, within the decommissioning period —

(a)

disconnect every specified EV charger from the electricity grid;

(b)

remove every specified EV charger from the electrical installation it is affixed to; and

(c)

shut down every specified EV charger.

Subregulation 2

In paragraph (1), the decommissioning period is —

(a)

in a case where the authorisation granted to the specified person is cancelled under rule 8 or 9 of the Electric Vehicles Charging (Trials and Special Uses) (General) Rules 2023 — the period of 30 calendar days after the date on which the cancellation takes effect; or

(b)

in any other case — the period of 30 calendar days after the end of the specified period.