Skip to content
In forceAmended2020 Revised Edition

Part 5A · Electricity Rationing

41D. Protection from liability

Feedback & support
Amended

Last amended by an amending law of 2024.

(1)

The Authority is not liable for any loss or expense suffered by any person in or as a result of complying with any direction made under section 41B(1) or any order made under section 41C(1)(a) by the Authority in good faith and with reasonable care, or as a result of any reduction or discontinuance of any supply of electricity to the person following from such direction or order.

(2)

A market support services licensee and a transmission licensee are not liable for any loss or expense suffered by any person as a result of the market support services licensee or transmission licensee (as the case may be) complying in good faith and with reasonable care with any order made by the Authority under section 41C(1)(a).

(3)

The Authority, a market support services licensee, a transmission licensee and any person authorised by the Authority or such licensee, are not liable for any loss or expense, or damage, suffered by any person as a result of the exercise in good faith and with reasonable care of any powers under section 41C(1) or (3) by the person so authorised by the Authority or such licensee.

Report

Part 5B

Matters Relating to Generation Entities

Part 6

Wholesale Electricity Market

Part 7

Competition

Part 8

Appeal Panel

Part 9

Electrical and Supply Installations, Cable Detection Work and Electrical Workers

Part 10

Offences

Part 11

Miscellaneous