Regulation 15

of Public Utilities (Regulated Works and WSI Design Works) Regulations 2018

Regulation 15

Duty to submit notices before start of WSI works

Amended byS 205/2025 wef 01/04/2025S 205/2025 wef 01/04/2025S 205/2025 wef 01/04/2025

Subregulation 1

This regulation applies in relation to any WSI works that may result from any WSI design works carried out by a professional engineer.

Subregulation 2

Amended byS 205/2025 wef 01/04/2025S 205/2025 wef 01/04/2025S 205/2025 wef 01/04/2025

For the purposes of section 40P(1)(b)(i) of the Act, every professional engineer must, before the start of any WSI works mentioned in paragraph (1), submit to the Board a written notice —

(a)

in such form and manner as the Board may require;

(b)

accompanied by one or more plans showing the particulars of those works, including any drawing, diagram or calculation concerning such works; and

(c)

accompanied by a fee of $1,100.