Regulation 16
of Public Utilities (Regulated Works and WSI Design Works) Regulations 2018
Regulation 16
Duty to submit certificates of satisfactory completion
Subregulation 1
This regulation applies to WSI works mentioned in regulation 15 where completed.
Subregulation 2
For the purposes of section 40P(1)(b)(ii) of the Act, every professional engineer must, without delay after the completion of the WSI works, submit to the Board a certificate of satisfactory completion —
in such form and manner as the Board may require; and
with a certification by the professional engineer that —
the WSI works carried out on a water service installation (called in this paragraph the relevant water service installation) are in compliance with the requirements imposed by or under the Act;
the relevant water service installation, and its associated electrical devices and equipment, have been tested and are safe and acceptable for operation; and
the relevant water service installation has been tested to be watertight and is fit to convey piped water suitable for drinking.