About this subsidiary legislation

Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 is Singapore Subsidiary Legislation, cited as Subsidiary Legislation EPMA-S514-2023 1999, currently marked in force and first recorded in 1999.

Regulation 1

Citation and commencement

Open as pageSuggest a correction

This Order is the Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 and comes into operation on 21 July 2023.

Regulation 2

Definitions

Open as pageSuggest a correction

In this Order —“dispatch instruction” means a dispatch instruction issued under section 9.1.3 of Chapter 5 of the market rules that —

(a)

relates to a specified open cycle gas turbine; and

(b)

requires the specified open cycle gas turbine to be operated at a loading level that is equal to or exceeds the loading level specified in the dispatch instruction;“Energy Market Authority of Singapore” means the Energy Market Authority of Singapore established under the Energy Market Authority of Singapore Act 2001;“market rules” has the meaning given by section 2(1) of the Electricity Act 2001;“specified open cycle gas turbine” means any of the following open cycle gas turbines located at 31 Senoko Road, Singapore 758103:

(a)

the open cycle gas turbine with the identification number SNKGT11;

(b)

the open cycle gas turbine with the identification number SNKGT12;

(c)

the open cycle gas turbine with the identification number SNKGT21;

(d)

the open cycle gas turbine with the identification number SNKGT22.

Definition

“dispatch instruction” means a dispatch instruction issued under section 9.1.3 of Chapter 5 of the market rules that —

(a)

relates to a specified open cycle gas turbine; and

(b)

requires the specified open cycle gas turbine to be operated at a loading level that is equal to or exceeds the loading level specified in the dispatch instruction;

Suggest a correction

Definition

“Energy Market Authority of Singapore” means the Energy Market Authority of Singapore established under the Energy Market Authority of Singapore Act 2001;

Suggest a correction

Definition

“market rules” has the meaning given by section 2(1) of the Electricity Act 2001;

Suggest a correction

Definition

“specified open cycle gas turbine” means any of the following open cycle gas turbines located at 31 Senoko Road, Singapore 758103:

(a)

the open cycle gas turbine with the identification number SNKGT11;

(b)

the open cycle gas turbine with the identification number SNKGT12;

(c)

the open cycle gas turbine with the identification number SNKGT21;

(d)

the open cycle gas turbine with the identification number SNKGT22.

Suggest a correction

Regulation 3

Exemption

Open as pageSuggest a correction

Subregulation 1

Suggest a correction

Sub‑paragraph (2) applies if —

(a)

the Energy Market Authority of Singapore has issued to Senoko Energy Pte. Ltd. a dispatch instruction for not more than 2 specified open cycle gas turbines; and

(b)

Senoko Energy Pte. Ltd. operates every specified open cycle gas turbine in respect of which a dispatch instruction has been issued (called in this paragraph an activated specified open cycle gas turbine), in accordance with the dispatch instruction.

Subregulation 2

Suggest a correction

Senoko Energy Pte. Ltd. is, in respect of the operation of every activated specified open cycle gas turbine for, or for purposes connected with the production of electricity, exempt from section 12(1) of the Act but only in relation to regulation 4(1) of, read with paragraph 1(q) of the Schedule to, the Environmental Protection and Management (Air Impurities) Regulations (Rg 8) —

(a)

for the period from 21 July 2023 to 31 December 2025 (both dates inclusive); but(b)only if the operation of each activated specified open cycle gas turbine does not result in the emission of oxides of nitrogen of a concentration that before admixture with air, smoke or other gases, exceeds 700 mg/Nm3 expressed as nitrogen dioxide.

Common questions

What is Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023?
Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 is Singapore Subsidiary Legislation, cited as Subsidiary Legislation EPMA-S514-2023 1999, currently marked in force and first recorded in 1999.
Is Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 still in force?
Yes — Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 is currently in force.
When did Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 take effect?
Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 was first recorded in 1999.
How many regulations does Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 have?
Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 contains 3 regulations.
Where can I read the official version of Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023?
The official text of Environmental Protection and Management (Senoko Energy Pte. Ltd. — Exemption) Order 2023 is published at sso.agc.gov.sg.