About this subsidiary legislation

Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 is Singapore Subsidiary Legislation, cited as Subsidiary Legislation EA-S530-2022 2001, currently marked in force and first recorded in 2001.

Regulation 1

Citation and commencement

Open as pageSuggest a correction

This Order is the Electricity (Pulau Ubin Micro‑Grid Test‑Bed — Exemption) Order 2022 and comes into operation on 1 July 2022.

Regulation 2

Definitions

Open as pageSuggest a correction

In this Order —“Project” means the project known as the “Pulau Ubin Micro‑Grid Test‑Bed”;“Project Agreement” means the Project Agreement dated 7 March 2022 entered into between the Authority and Sunseap Energy Ventures Pte Ltd;“relevant period” means the period starting on 1 July 2022 and ending on the earlier of the following:

(a)

30 June 2034;

(b)

the date of termination of the Project Agreement.

Definition

“Project” means the project known as the “Pulau Ubin Micro‑Grid Test‑Bed”;

Suggest a correction

Definition

“Project Agreement” means the Project Agreement dated 7 March 2022 entered into between the Authority and Sunseap Energy Ventures Pte Ltd;

Suggest a correction

Definition

“relevant period” means the period starting on 1 July 2022 and ending on the earlier of the following:

(a)

30 June 2034;

(b)

the date of termination of the Project Agreement.

Suggest a correction

Regulation 3

Exemption from section 6(1)(a), (b), (d) and (f) of Act

Open as pageSuggest a correction

Section 6(1)(a), (b), (d) and (f) of the Act does not apply to Sunseap Energy Ventures Pte Ltd for the relevant period in respect of its activities carried out at Pulau Ubin in connection with the Project.

Regulation 4

Revocation

Open as pageSuggest a correction

The Electricity (Pulau Ubin Micro‑Grid Test‑Bed — Exemption) (No. 2) Order 2021 (G.N. No. S 1008/2021) is revoked.

Common questions

What is Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022?
Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 is Singapore Subsidiary Legislation, cited as Subsidiary Legislation EA-S530-2022 2001, currently marked in force and first recorded in 2001.
Is Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 still in force?
Yes — Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 is currently in force.
When did Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 take effect?
Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 was first recorded in 2001.
How many regulations does Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 have?
Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 contains 4 regulations.
Where can I read the official version of Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022?
The official text of Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022 is published at sso.agc.gov.sg.