Singapore legislation

Regulation 3

of Electricity (Pulau Ubin Micro-Grid Test-Bed — Exemption) Order 2022

Regulation 3

Exemption from section 6(1)(a), (b), (d) and (f) of Act

Section 6(1)(a), (b), (d) and (f) of the Act does not apply to Sunseap Energy Ventures Pte Ltd for the relevant period in respect of its activities carried out at Pulau Ubin in connection with the Project.