33G. New clearance certificate required for amended plans of controlled works

Feedback & support
Amended

Last amended by an amending law of 2023.

(1)

A developer of controlled works who intends to depart or deviate from any plans of those works for which a clearance certificate has been issued, must apply to the Director-General for another clearance certificate (called in this section a new certificate) for the amended plans showing the departure or deviation.

(2)

Section 33D(2) and (3) applies (with the necessary modifications) to applications made under subsection (1) as it applies to applications made under section 33D(1).

(3)

Where the Director-General has issued a new certificate pursuant to an application under subsection (1), the previous clearance certificate for the same controlled works is treated as cancelled.

Report

Part 10

Environmental Pollution Control Measures

Part 10A

Greenhouse Gas Control

Part 11

Enforcement

Part 12

Compensation, Damages, Fees, Costs and Expenses

Part 13

Miscellaneous Provisions

Schedules