Environmental Protection and Management Act 1999 · 2020 Revised Edition · Part 9A · Pollution Control Requirements for Controlled Works
33. Interpretation of this Part
Feedback & supportLast amended by an amending law of 2023.
In this Part —“amended plans” means plans showing any deviation from, or any amendment or addition to, any plans of controlled works certified by the Director-General in a clearance certificate;“building” has the meaning given by section 2(1) of the Building Control Act 1989;“clearance certificate” means a certificate described in section 33B(1) and issued under section 33D(2)(a), and includes such certificate issued under section 33D(2)(a) as applied by section 33G;“compliance certificate” means a certificate described in section 33I(1) and issued under section 33I(3)(a);“controlled works” means any building works or industrial plant works;“design certificate” means a certificate described in section 33E(1) and issued under section 33E(3)(a);“developer”, in relation to any controlled works, means the person for whom or on whose behalf the controlled works are carried out;“foundation” means that part of a building which is below or in direct contact with the ground, and through which the weight of the building and the loads acting on the building are transmitted to the ground, and includes any footing, raft or pile of the building;“plans”, in relation to any controlled works —
Director-General
“Director-General” means the Director‑General of Environmental Protection appointed under section 3(1);
includes drawings, details, diagrams, digital representations generated from building information modelling, structural details and calculations showing or relating to the works; and
building
“building” includes any house, hut, shed or roofed enclosure, whether used for the purpose of human habitation or otherwise;
if prepared in electronic form, includes the medium in which the plans of the works have been stored;“pollution control requirements” means the requirements set out in regulations made under section 77 and any prescribed codes of practice relating to the prevention, reduction or control of pollution of the environment from any completed buildings or industrial plants;“site formation works” means any kind of site formation and includes earthworks for site stabilisation, the construction of foundations, basements, sub-structures, piling, underpinning, ground anchors, trenches or any other kind of ground works;“temporary compliance certificate” means a certificate issued under section 33J(1).
pollution of the environment
“pollution of the environment” means pollution of the environment due to the release (into any environmental medium) from any process of substances which are capable of causing harm to human or any other living organisms supported by the environment;
“amended plans” means plans showing any deviation from, or any amendment or addition to, any plans of controlled works certified by the Director-General in a clearance certificate;
“building” has the meaning given by section 2(1) of the Building Control Act 1989;
“clearance certificate” means a certificate described in section 33B(1) and issued under section 33D(2)(a), and includes such certificate issued under section 33D(2)(a) as applied by section 33G;
“compliance certificate” means a certificate described in section 33I(1) and issued under section 33I(3)(a);
“controlled works” means any building works or industrial plant works;
building works
“building works” has the meaning given by the Building Control Act 1989;
“design certificate” means a certificate described in section 33E(1) and issued under section 33E(3)(a);
“developer”, in relation to any controlled works, means the person for whom or on whose behalf the controlled works are carried out;
“foundation” means that part of a building which is below or in direct contact with the ground, and through which the weight of the building and the loads acting on the building are transmitted to the ground, and includes any footing, raft or pile of the building;
“plans”, in relation to any controlled works —
includes drawings, details, diagrams, digital representations generated from building information modelling, structural details and calculations showing or relating to the works; and
if prepared in electronic form, includes the medium in which the plans of the works have been stored;
“pollution control requirements” means the requirements set out in regulations made under section 77 and any prescribed codes of practice relating to the prevention, reduction or control of pollution of the environment from any completed buildings or industrial plants;
“site formation works” means any kind of site formation and includes earthworks for site stabilisation, the construction of foundations, basements, sub-structures, piling, underpinning, ground anchors, trenches or any other kind of ground works;
“temporary compliance certificate” means a certificate issued under section 33J(1).