Skip to content
In forceAmended2020 Revised Edition

Part 9A · Pollution Control Requirements for Controlled Works

33I. Compliance certificate required upon completion of controlled works

Feedback & support
Amended

Last amended by an amending law of 2023.

(1)

Upon the completion of any controlled works the plans (including any amended plans) of which have been certified in a clearance certificate, the developer of the controlled works must apply to the Director-General for a further certificate (called in this Part a compliance certificate) that the controlled works have been completed in accordance with —

(a)

the plans as so certified; and

(b)

the conditions (if any) in the clearance certificate.

(2)

The Director-General may, on an application under subsection (1), require the developer or a registered inspector appointed by the developer to inspect the completed controlled works and submit a report stating whether the controlled works have been completed in accordance with subsection (1)(a) and (b).

(3)

The Director-General may, after considering the application under subsection (1) and any report submitted under subsection (2) —

(a)

issue (subject to any conditions that he or she thinks fit) a compliance certificate if the controlled works have been completed in accordance with subsection (1)(a) and (b) (except for any non-compliance that has been waived in a particular case by the Director-General);

(b)

give a written direction to the developer to comply within a specified period with any requirement that the Director-General may specify for the purpose of ensuring that the controlled works have been completed in accordance with subsection (1)(a) and (b); or

(c)

disapprove the application.

(4)

Without limiting subsection (3)(b), a direction may require specified work or alteration to be carried out at the expense of the developer, within a specified period and to the satisfaction of the Director-General.

(5)

If a direction is not complied with within the period specified in that direction, or such further period as may be allowed by the Director-General, the application under subsection (1) is, at the end of that period, deemed to be disapproved by the Director-General.

Report

Part 10

Environmental Pollution Control Measures

Part 10A

Greenhouse Gas Control

Part 11

Enforcement

Part 12

Compensation, Damages, Fees, Costs and Expenses

Part 13

Miscellaneous Provisions

Schedules